BELMONT TRANSPORT PACKAGE A49 – B4349 (Relief Road Southern Section) Meeting 14 June 2013.

Slides:



Advertisements
Similar presentations
Windsor Park & Ride (Overview & Scrutiny Panel – 29 th October 2007)
Advertisements

Institute for Transport Studies FACULTY OF ENVIRONMENT UCL Seminar - Catalysing development through transport investment – the role of appraisal and decision.
Presentation to Lancaster City Council OSC 11 June 2014 Update on the Clinical Strategy for Health Services in Morecambe Bay: Better Care Together.
REGIONAL FUNDING ADVICE 2 What’s it all about? Tyler Wakeford 16 November 2008
Why London needs the Thames Tunnel IEMA Conference 2011 Optimising Infrastructure within environmental limits Tuesday 15 November 2011.
Carbon Lite Cardiff A response to the challenges of climate change Julian Stedman September 2009.
Strategic Environmental Assessment “Back to the Future” By Dr Anne F Kerr 18 June 2005.
Institute for Transport Studies FACULTY OF EARTH AND ENVIRONMENT The Economic Evaluation of Transport Projects Seminar Madrid, November 2010 Current.
Jonathan Wheeler Team Manager Strategic Economic Infrastructure East Sussex Strategic Partnership Strategic Transport Update 30 October 2014.
Selecting and Applying Indicators for Transport Project Appraisal Dr Greg Marsden
Air Quality Action Planning – Perth & Kinross Tom J Brydone Environmental Health Manager.
DEVELOPING THE TRANSPORTATION NETWORK IN WREXHAM ‘Delivering our statutory functions’ Environment & Regeneration Scrutiny Committee 13 December 2007 Transportation.
MTF Rail Development Forum
Somerset County Council Climate Change Strategy Abigail Stretch Sustainable Development Officer.
Droitwich South Ward Meeting Yew Tree Development Community Hall 29 th June 2011 Facilitated by Cllr Richard Morris Neil Pearce, Development Manager Andrew.
© 2003 TranSystems Corporation Advisory Committee Meeting January 19, 2010.
HDM-4 Applications. 2 Project Appraisal Project Formulation Maintenance Policy Optimization Road Works Programming Network Strategic Analysis Standards.
Traffic Incident Management – a Strategic Focus Inspector Peter Baird National Adviser: Policy and Legislation: Road Policing.
Prof Andrew McNaughton HS2 Ltd Technical Director 1 Developing HS2.
EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Project Overview Ward 31 Ravine Meeting November 4, :00 to 9:00 p.m. Presteign-Woodbine United Church.
Presentation to the Executive of the Carlisle Partnership 13 July 2009.
SHORELINE MANAGEMENT PLAN REVIEW (SMP2) South Devon and Dorset Coastal Authorities Group SDADCAG.
Joint Transport Forum I Rapid Transit Line 2 Our Future Transport I West of England Sub Region.
Jonathan Wheeler Team Manager Strategic Economic Infrastructure East Sussex Strategic Partnership Local Transport Plan Update 18 th October 2013.
Mid Wales LTP Stakeholder Workshop 3 rd October Presentation by Ann Elias and Janice Hughes.
Protecting Telford’s uniqueness and our community assets Keith Harris Service Delivery Manager – Transport & Highway Development.
FUTURE OFFSHORE Update on the Consultation Nigel Peace Licensing & Consents Unit 27 March 2003.
Local Transport Plan 3 Vision and Issues. The Local Transport Plan Will replace LTP2, which expires 31 March must have LTP3 approved and operative.
EVALUATION AND APPRAISAL REPORT MAJOR COMMUNITY ISSUES RELATED TO COMPREHENSIVE PLAN Board of County Commissioners/ Local Planning Agency Joint Meeting.
SOUTH EAST PLAN South East Plan ESPACE - reminder Aim Incorporation of adaptation to climate change within spatial planning mechanisms at local, regional,
LTP3 Development Sean Parks Nottinghamshire County Council.
West of England Joint Waste Development Plan Document Allan Davies Planning Policy Officer North Somerset Council West of England Partnership Office North.
Case study: SEA for land-use plan amendments of Krasna Hora municipality.
Planning for the future of our district Core strategy options Presentation to C4B Associates February 2010.
FLOOD RISK MANAGEMENT The next steps. The National Technical Advisory Group On Flooding Issues An Overview and the Future.
BELMONT TRANSPORT PACKAGE A49 – A465 Link Meeting 19 March 2013.
TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011.
A96 Fochabers Bypass Moray Council 15 August 2007.
21st October 2015 Stillorgan Village Area Movement Framework Plan PUBLIC CONSULTATION INFORMATION PERIOD DOCUMENT.
SWIFT NETWORKING MEETING: NEW EASTERN VILLAGES (NEV) 24th September 2015 Samantha Howell Strategic Allocations Planning Manager and NEV Programme Lead.
Communities M40 J12-J14 – Data Analysis, Modelling and Scheme Development.
Developing a Transport Vision To 2050 Jon Tiley Business Manager- Spatial Planning and Economy.
Herefordshire Local Plan Members’ Seminar 9 October 2015.
TRAP 5 th interregional meeting & Site Visits Limerick & Lough Derg, Ireland 9 th October 2013 CP3 GP6 Regional Planning Guidelines PP3 – Mid-West Regional.
Simon Amor Asset Development Manager
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
‘People, Homes and Jobs’ Local Plan Consultation 2015 PPCLG 27 January 2016.
STAMFORD CAPACITY AND LIMITS TO GROWTH STUDY SOUTH KESTEVEN DISTRICT COUNCIL FINAL REPORT PRESENTATION PRESENTERS: UNA McGAUGHRIN JESSE HONEY 14 TH DECEMBER.
planning aid for scotland unique national charity helping people engage with planning impartial & independent not part of Scottish Government or any Local.
Community Infrastructure Levy S106 vs CIL July 2014.
Insert the title of your presentation here Presented by Name Here Job Title - Date How can we make London’s transport network resilient to climate change?
Colleen Williams Department of Health Yorkshire and Humber Region 11 January 2008 Health in Strategic Environmental Assessment:
Strategic Environmental Assessment (SEA) A Scottish replacement to Air Passenger Duty (APD) Elaine McCall Environmental Assessment Team The Scottish Government.
Road Investment Decision Framework
Cambourne to Cambridge Better Bus Journeys
NGTA Halton Planning and Public Works Committee
A47 / A12 Corridor Improvement schemes
Western Orbital Local Liaison Forum 11TH September 2017.
An introduction to the LiFE Index
CP3 GP6 Regional Planning Guidelines PP3 – Mid-West Regional Authority
Chisinau-Gurgiulesti Motorway, Construction of Comrat Bypass
See DIKE_ _WISE-Marine_2016_Business Plan_v2.3
Presentation to LEP Performance and Investment Committee 16 May 2018
KEYNOTE STAGE SPONSOR.
Second Stakeholder Expert Group meeting 19-20/01/2012
Western Orbital: M11 J11 Park and Ride Provision
Suffolk Chamber of Commerce Transport & Infrastructure Group
GCP Transport Update Meeting for: M11 J11 Park & Ride Engagement Group
Project Directors Report to 
Histon Road LLF Resolutions and Programme
Presentation transcript:

BELMONT TRANSPORT PACKAGE A49 – B4349 (Relief Road Southern Section) Meeting 14 June 2013

14 June Belmont Transport Package The Belmont Transport Package appraisal is considering interventions to meet local issues and challenges. These interventions will consider both measures on existing road network and a new road link in an attempt to provide suitable solutions. A full appraisal of impacts of each package of measures is being undertaken following relevant guidance. This meeting will provide an update on work done to date, provide a detailed update on the assessment of a new road link and explain work yet to be done and detail of next steps. Formal public consultation on whole package of measures will follow in coming months.

14 June A49 (T) Hereford City Centre Rotherwas Access Road A465 B4349 “Belmont” Junction layout and location to be confirmed New road link Measures on existing highway Belmont Transport Package

14 June B4349 / A465 junction layout and location to be confirmed

14 June The appraisal process follows guidance as set out in Department for Transport web based Transport Analysis Guidance (WebTAG) and considers: environmental impacts; social impacts; economic impacts; and public accounts. A49 – B4349 (Relief Road Southern Section)

14 June Progress since March: A49 – B4349 (Relief Road Southern Section) –Biodiversity surveys completed –Topographical surveys completed –Traffic surveys completed –Landscape surveys completed –Townscape surveys completed –Heritage of Historical Resources surveys completed –Site visits with landowners –Development of extension to B4349 Clehonger Road –Development of options on existing highways on-going

14 June Feedback: A49 – B4349 (Relief Road Southern Section) 1.Stakeholder discussions on-going –Local issues 2.Link from A465 to B4349 (Clehonger Road junction) –Position of junction –Type of junction 3.Junctions with Grafton Lane and / or Haywood Lane –Strategic link road –Junctions not considered –Agricultural accesses considered

14 June “Emerging Route” Although some elements of the appraisal process have not yet been completed, it is possible at this stage to provide information on the current ‘emerging preferred option for a new highway link’ which will form part of the overall package of measures. There is still further work to be completed to provide a definitive preferred option for the Belmont Transport Package. A49 – B4349 (Relief Road Southern Section)

14 June Next Stages - work yet to be completed: –traffic modelling work including scenario testing following on from the LDF modelling; –Liaison with Highways Agency regarding model outputs; –Appraisal of impacts due to noise; –Appraisal of impacts due to air quality; –Appraisal of carbon emissions (CO 2 ); A49 – B4349 (Relief Road Southern Section)

14 June Next Stages (cont’d) –Appraisal of costs (capital costs and maintenance costs); –Appraisal of economic impacts – i.e. benefits associated with Belmont Transport Package; –Appraisal of social impacts – including affordability, severance, journey quality, accidents, physical activity A49 – B4349 (Relief Road Southern Section)

14 June Indicative Timetable Traffic Modelling & Appraisal – to end September 2013 Presentation of Amey Technical Appraisal – end September 2013 Public Consultation – October 2013 Preparation of Planning Submission – Autumn 2013 – Spring 2014 Planning & Detailed Design – Spring 2014 to Spring 2015 Statutory Order Process – Spring 2015 – Summer 2016 Construction* – Winter 2016 to end 2017 A49 – B4349 (Relief Road Southern Section) * Current programme includes all statutory processes. Construction start date could be significantly brought forward if not all of these statutory process are required e.g. land is acquired by agreement.

Thank You For Your Time 14 June