05 m 10 m 12 mr 145 mr 18.5  deflection: 40  OVERVIEW: UCN Facility in Meson Hall.

Slides:



Advertisements
Similar presentations
UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.
Advertisements

UCNA specs – JWM 9/4/7 Proton beam energy = 800 MeV Peak proton current = 40 uA Duty cycle = 1/10 (1 sec on, 10 sec off) Therefore time-averaged current.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
F.Brinker, DESY, July 17 st 2008 Injection to Doris and Petra Fitting the detector in the IP-region Radiation issues Beam optic, Target cell Polarisation.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
UCN Phase 2 Design Status September 10, Design Components Bulk Shielding Target Crypt Cryogenic Insert Target Insert UCN Port Beam Window Cooling.
1 Hall A Update Thia Keppel APEX Collaboration Meeting April 2015.
Preparation for May-2013 Review of UCN Beamline March 27, Date: May 2-3, 2013 Review Committee finalized Scope – Overall concept, focusing on 2014.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
ACTIVITY J A J O J A Schedule( ) UCN Timeline & Major Milestones Remove.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
MCTF C. Johnstone MUTAC Meeting 8-10 April Debut of the MTA beamline Description, status and commissioning plans.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
2014 Shutdown Schedule & UCN FY-2013 Resources 1 February 20, 2013.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
NUMI NuMI Internal Review July 12, 2001 Infrastructure: Radiation Safety Page 1 Technical Components NuMI Beamline Radiation Safety Issues Radiation Safety.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Vault-BL1A Shielding Plug Sept 26, 2012 L.Lee. N UCN Installation-1: 2014 Shutdown Shielding “Plug” will need to be reconfigured.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
BL1U at TRIUMF UCN Beamline Spallation Target & Remote-Handling System (Aug/2010) L.Lee.
BL1U at TRIUMF UCN Beamline BL1U Layout (Nov 2011) C.A.Davis.
UCN 2014-Shutdown Schedule UCN Monthly Meeting (July 24, 2013) L.Lee, C.Marshall.
UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
BL1U at TRIUMF UCN Beamline Kicker Magnet (April 12, 2010)
UCN Facility at TRIUMF L.Lee October 3, 2012 PLACE UCN LOGO & ACRONYM HERE.
Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada Propriété.
Overview of Electron Cooling Activities at FNAL Thomas Kroc Fermilab – Electron Cooling EIC 2004 March 15-17, 2004 Jefferson Lab.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
1 Message from Management Resources for 2014 oversubscribed Need to descope Minimal 2014 work Reschedule (Delay) some work to 2015 Groups:  Define Critical.
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
BL1U at TRIUMF UCN Beamline Septum & Dipole Magnets (April 12, 2010)
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Design and construction of Nuclotron-based Ion Collider fAcility (NICA) and Mixed Phase Detector (MPD) Design and construction of Nuclotron-based Ion Collider.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Resources, Timeline & Contingency UCN CDR (Sept/2010)
SBS Magnet and Support Status Robin Wines June 2013.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
MERIT review, Dec. 2005CERN AB-ATB1 CERN installation I. Efthymiopoulos, A. Fabich, J. Lettry CERN AB-ATB MERIT review, Dec.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
After Protons from RCS 1 st DeeMe Collaboration Meeting Dec. 10, 2012 Kazami Yamamoto J-PARC Center Accelerator Division.
Update on the ESS monolith design Rikard Linander Monolith and Handling Group ESS Target Division TAC 10, Lund, Nov 5,
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
Prompt dose upstream the 12-ft concrete shielding blocks Igor Rakhno May 4, 2007.
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
UCN and SCRF/ISAC interface issues ● proposal for UCN (CFI, 2008) – 10 uA at 25% duty cycle (1 min on, 3 min off) – use BL4A (TISOL) ● duty cycle is incompatible.
Muon Facility at J-PARC Proton Driver Efficiency WS 29/Feb/2016
St. George Infrastructure
An Ultracold Neutron Source for TRIUMF
Spectrometer Solenoid Update
News and brief overview of Beamline plans for the next few months
Magnet, Support and Infrastructure
Kicker specifications for Damping Rings
Electron Collider Ring Magnets Preliminary Summary
Polarized 3He target installation
Presentation transcript:

05 m 10 m 12 mr 145 mr 18.5  deflection: 40  OVERVIEW: UCN Facility in Meson Hall

SHIELDING (Schematic Layout)

 calculations by Anne Trudel: 40  A, 500 MeV protons stopping in tungsten tgt  assumes 0.5 m empty space around target (no moderator)  figure shows shielding needed to reduce dose to 3  Sv/hr outside shielding  integrating shielding gives 125 m 3 steel and 375 m 3 concrete not allowing for practicalities of stacking the blocks. CFI cost estimate  schematic layout, based on A.Trudel’s calc. s  $1820 K  Include stacking details of blocks (20% contingency) Latest cost estimate  Based on vendor quotes  $2111 K Possible Cost savings  Dose in Skyshine direction can be higher (-1m from top) Existing Concrete (10%, $125K), Special Shielding Blocks (detailed layout, graphite?,…) “New” Steel Blocks (plate thickness) SHIELDING Shielding Quotes: Concrete$1251 k Steel (radioactive)$ 360 k (66%) Steel (new)$ 480 k (33%)

Main Focus of Recent Activities:  UCN Beamline design & cost estimates  Layout Installation Schedule with Vijay Verma UCN Beamline design & cost estimates (progress summary): - Shielding  working on 2 nd Iteration design and cost - Spallation Target & Remote Handling - Beamline Magnets & Power Supplies - Beamline Infrastructure - Cryogenics Schedule (progress summary): - Proposed Installation Schedule from Vijay Verma UCN Status: Update

OVERVIEW: Superfluid He UCN Source and EDM Exp.

05 m 10 m 12 mr 145 mr 18.5  deflection: 40  OVERVIEW: UCN Facility in Meson Hall (Note: New/updated drawing in ~ 2 weeks)

 calculations by Anne Trudel, assuming 40  A, 500 MeV protons stopping in tungsten target  assumes 0.5 m empty space around target (no moderator)  figure shows shielding needed to reduce dose to 3  Sv/hr outside shielding  integrating shielding gives 125 m 3 steel and 375 m 3 concrete not allowing for practicalities of stacking the blocks. 1 st Iteration  “schematic” shielding layout; cost estimate  $1820 K 2 nd Iteration  more refined; based on A.Trudel’s calculations  Include stacking details of blocks; other possible cost savings  New layout (~ 2 weeks) & recosting in progress (S.Austen/C.Davis) SHIELDING

Spallation Target  Remote Handling & Transportation Issues of concern (P.Bricault)  New calculations from Safety (A.Trudel) indicates target activity level after 10 years of irradiation will still be a factor of ~5 below the A 2 transport limit  Present Spallation Target conceptual design  Tungsten Cylinder, 30 mm (D) x 120 mm (L) Target Geom. Optimization (MCNPX code): Troy Dawson (U.W. grad student)  Cooling System: High Pressure He OR Water Discussions w/ P.Bricault, Y.Masuda, G.Clark & others  leaning towards Water  Discussion of conceptual design for Remote-Handling System (P.Bricault)  New Engineer being hired for Target/RH design (?)  Costing…(P.Bricault)  A stopping target of tungsten bombarded with 100 uA of 500 MeV protons.  Blue arrows correspond to 1, 5 & 10 years of irradiation.  Shown below the arrow is the total activity as a fraction of the A 2 transport limit.  The inventory of activity in the target at ten years is at approximately one fifth of the A 2 transport limit for Type A packages.

Beamline Magnets MagnetsDesign Power SupplyIssues. Kicker (1AK1)M.BarnesM.Barnes/ABBVector Fields calc. Switches  cost 1U SeptumG.ClarkG.ClarkRad-hardness Bender 1 (1UB1)G.Clark*M11 Bender (KR/DL/FM)Impact on BL1A D-Pace ?1B Bender (overkill) Retrofit existing ? Quad 1 (1UQ1)From M20From M20 Quad P.S.Refurbish Quad 2 (1UQ2)From M20From M20 Quad P.S. Bender 2 (1UB2)From PIFFrom PIFRefurbish

Preliminary Coil Design for UCN Kicker Kicker Power Supply Kicker Specs:  500 MeV protons (p = 1090 MeV/c)  15 mr maximum deflection (Bdl = Tm); normal deflection 12mr  effective length 1.5 m (physical available 2 m)  aperture 100 mm x 100 mm (possibly 130 mm horiz)  field uniform to  5% over central 80 mm diameter region  flat top 1 ms, flat to  5% over the 1 ms  fires every 3 ms (330 Hz rep. rate, able to run cont.)  can be re-configured (in <1 hr) to run as low as 100 Hz rep rate  power supply able to be located 10 m away

Beampipe & Hardware, Vacuum, Diagnostics, Controls, Safety, Services Cost Estimate  Discussions with A.Hurst & others  Relevant documents forwarded to Andy for review  Identify missing components in existing Resource Chart  Provide updated cost estimate for BL infrastructure Power Budget/Capacity  Discussions with F.Mammarella  Capacity of substation transf  Does not look like it should be a problem ( M11+M13  UCN )  Revisit after magnet P.S. details clarified  “New” load from He Liquifier needs to be included TRIUMF LHe capacity in 5YP  Enough to meet UCN requirements? Discussions with I.Sekatchev  UCN requirements can be met (and then some)  Igor’s proposed liquifier has enough capacity to service UCN as well as other Meson Hall expts (UCN requires ~1000 L.L./day) (Linde L140 can provide ~ 3300 L.L./day) Cost Estimates  Liquifier costs  5YP  UCN-incurred costs - He Transfer Lines - dependent on Liquifier siting/location (Chuck, Igor, Stu) Beamline Infrastructure Cryogenics

Vijay’s Proposed Installation Schedule for UCN (refining timetable & manpower) Installation Schedule 1* Remove M11 “cold” end (3 wk)Jan 2011 shutdown or Sep Remove M11-Q1, Q2, B1,(3 wk)Jan 2012 shutdown & blank off M11 septum 3 Remove M13-Q1 to Q7 (6 wk) 4* Remove PIENU (4 wk) 5 Take out 1BVB2 (1 wk)Jan 2013 shutdown Remove balance of 1B and PIF (3 wk) Install Kicker, Septum, 1UB1, 1UQ1-Q2, (5 mo) & restore shielding to allow 1A running 6* Install PIF in new location (6 wk) 7* Install 1UB2, Spallation Target, Shielding,(4 mo) Partially Jul-Dec 2012 (whenever possible) & UCN equipmentand finish between Jul 2013 – Apr 2014 * No shutdown required Task Shutdown Task 1 Task 2,3,4Task 5,6 Task 7

Installation Schedule & Manpower Requirements UCN INSTALLATION TASKS (Based on Vijay's and Des Ramsay’s notes of the 20 Nov 2009 meeting) TASK Remove M11 cold end.  No shutdown required. 3 weeks. 3 Techs + crane and riggers + some support from other groups Remove M11 (Q1,Q2,B1,blank off Septum)  Meson Hall shutdown only. 3 weeks. 3 Techs + remote handling + crane and riggers + support from other groups Remove M13 (Q1 to Q7)  Meson Hall shutdown only. 6 weeks. 3 Techs + crane and riggers + some support from other groups Remove PIENU  No shutdown required. Can be done anytime once PIENU finished. 4 weeks. 3 Techs + crane and riggers + some support from other groups Take out 1BVB2. Kicker will go here. 1BVB2 will also be used on UCN.  Requires Cyclotron shutdown (vault access) 1 week. 3 Techs + crane and riggers + some support from other groups Remove balance of beamline 1B and PIF  Requires Cyclotron shutdown (at least for upstream 1B). 3 weeks. 3 Techs + crane and riggers + some support from other groups Install Kicker, Septum, 1UB1, 1UQ1, 1UQ2, and restore enough shielding to run Meson Hall. To make room for the shielding, may be necessary to leave 1UQ1 and/or 1UQ2 out temporarily  Requires vault and meson hall access. 5 months. 4 Techs, crane and riggers, support from other groups Install 1UQ1 and 1UQ2 if not installed during the long shutdown.  Requires meson hall shutdown only. 4 weeks. 3 Techs + crane and riggers + some support from other groups Install PIF in new location.  No shutdown required. 6 weeks. 3 Techs + crane and riggers + some support from other groups Install 1UB2, spallation target, shielding, UCN equipment.  No shutdown required. 4 months. 3 Techs + crane and riggers + some support from other groups In addition, 6 months or so of prep work will have to be done refurbishing magnets, installing water headers on magnets, preparing vacuum boxes and stands,etc. I guess this would tie up mostly beamlines techs. Total “Shutdown” Time(s):Cyclotron shutdown5.5 months At least meson hall shutdown 3 months No shutdown required 6.5 months

UCN Important Dates Dec 5-15 UCN Experiment Run at RCNP-Osaka Jan UCN Collaboration Meeting at TRIUMF ???Gate 2 Review at TRIUMF Late MarchCFI Re-submission Apr 8-9UCN Workshop at RCNP-Osaka

Jeff Martin SHIELDING (1 st Iteration): How much room does it need? 1 st Iteration costing 

Example of Proton Beam Sharing  A 80  A 40  A 120  A 0  A 1 min.4 min. meson hall UCN source

Proposed time division of beam 10  s to 40  s 2/3 beam to  SR 1/3 beam to UCN normal TRIUMF beam, 4 min ms 2 ms 1 ms 1 min. 120  A

A stopping target of tungsten bombarded with 100 uA of 500 MeV protons. Blue arrows correspond to 1, 5 and 10 years of irradiation. Shown below the arrow is the total activity as a fraction of the A 2 transport limit. The inventory of activity in the target at ten years is at approximately one fifth of the A 2 transport limit for Type A packages. Anne Trudel

Preliminary Coil Design for UCN Kicker Mike Barnes

UCN Kicker Mike Barnes

Kicker Specs:  500 MeV protons (p = 1090 MeV/c)  15 mr maximum deflection (Bdl = Tm); normal deflection 12mr  effective length 1.5 m (physical available 2 m)  aperture 100 mm x 100 mm (possibly 130 mm horizontal)  field uniform to  5% over central 80 mm diameter region  flat top 1 ms, flat to  5% over the 1 ms  fires every 3 ms (330 Hz rep. rate, able to run continuously)  can be re-configured (in <1 hr) to run as low as 100 Hz rep rate  power supply able to be located 10 m away rise/fall time (  s) turnsinductance (  H) flattop current peak voltage A4500 V A2900 V A2500 V Examples:

Kicker Power Supply

Ramp-Up: SW1 and SW2 are closed, magnet ramps up from the high voltage + -

Kicker Power Supply End of Ramp-Up: + - SW1 is opened. Current circulates through D3, D1, and SW2

Kicker Power Supply Flat Top: + - SW3 closes as required to maintain the flattop with the low voltage supply + -

Kicker Power Supply Ramp-Down: + - All switches open. Current is against the HV for fast ramp down. Stops at I=0 when diodes become back biased.

Layout in Area B 800 MeV protons UCN Source beta- spectrometer polarizer magnet

proton beam direction shield package UCN port remote extraction

Schematic of Superfluid He UCN Source Yasuhiro Masuda