24-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, 2012 24: ATLO Support Dave Curtis Mars Atmosphere and Volatile.

Slides:



Advertisements
Similar presentations
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) GSE Timothy Quinn.
Advertisements

1 GLAST LAT Arrival at Spectrum Assuming That the LAT Transport Container Arrives on Flatbed Truck Question: Can Transport Cover Support Crane Lift With.
1 PFP MSR, 8/21/2012 Particles and Fields Package Monthly Status Review (MSR) August 21, 2012 Dave Curtis, PFP PM.
MAVEN CDR May 23-25, 2011 Particles and Fields Package Pre-Environmental Review May , 2012 Flight Software Peter R. Harvey Mars Atmosphere and Volatile.
GoetzFIELDS iPDR – I&T SPP/FIELDS Integration and Test Preliminary Design Review Keith Goetz University of Minnesota 1.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Integration and Test Critical Design Review Rick Sterling University of California – Berkeley Thm_CDR_IT_Revc.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
18-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , Package Dave Curtis, PFP Package Manager Mars.
Timothy QuinnFIELDS iCDR – EGSE Solar Probe Plus FIELDS Instrument CDR Electrical GSE Timothy Quinn UCB 1.
1 PFP MSR, 11/17/2009 Particles and Fields Package Monthly Status Review (MSR) November 17, 2009 Dave Curtis, PFP PM.
THEMIS Instrument Suite PERSuite T-V- 1 UCB, May 2, 2005 THEMIS Instrument Suite Thermal Vac Test Rick Sterling University of California, Berkeley.
25-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : SMA Jorg Fischer, MAM Mars Atmosphere and Volatile.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
C osmic R Ay T elescope for the E ffects of R adiation CRaTER Pre-Ship Review (I-PSR) Installation Procedures/Orbiter Level Test Procedures Robert Goeke.
MAVENIPSR3 - SWEA – March 1, SWEA Particles and Fields Package Pre-Ship Review March 1, 2013 Project-Level Assessment Jim Morrissey, MAVEN ISM Mars.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Safety and Mission Assurance Jorg Fischer, PFP SMA Manager.
MAVEN MARS ATMOSPHERE AND VOLATILE EVOLUTION.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
21-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : Flight Software Peter R Harvey Mars Atmosphere.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review System Engineering David Curtis, PF Package Manager.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
MAVEN CDR May 23-25, 2011 Particles and Fields Package Critical Design Review May , 2011 Integration and Test Dave Curtis PFP Package Manager Mars.
PFP Instrument Status All PFP Instruments Except SWEA have been delivered, integrated, and tested; supporting environmental tests Issues: –EUV alignment.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Overview and Status Keith Goetz University of Minnesota.
1 PFP QSR, 1/18/2012 Particles and Fields Package Quarterly Status Review (QSR) January 18, 2012 Dave Curtis, PFP PM.
1 MAVEN PFP ICDR May 23-25, 2011 Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission Particles and Fields Science Critical Design Review May ,
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration and Test 2011 March 29 Dave Mitchell.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
1 PFP QSR, 10/9/2012 Particles and Fields Package Quarterly Status Review (QSR) October 9, 2012 Dave Curtis, PFP PM.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
1 PFP MSR, 02/17/2010 Particles and Fields Package Monthly Status Review (MSR) February 17, 2010 Dave Curtis, PFP PM.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota
10-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : EMC Dave Curtis Mars Atmosphere and Volatile EvolutioN.
Pre-PDR Peer Review 1 UCB MAVEN Particles and Fields Flight Software Peer Review Requirements Definition Peter R. Harvey May 12, 2010.
15-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , SWIA (Solar Wind Ion Analyzer) J.S. Halekas.
Jan 2008 LMSSC - 1 SWEA Plume Impingements Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission.
TRIO-CINEMA 1 UCB, 2/08/2010 Integration and Test Program Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
13-1 MAVEN PFP ICDR, May 23 – 25, 2011 Particles and Fields Package Critical Design Review May , 2011 GSE Timothy Quinn.
4-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , Verification Dave Curtis, PFP Package Manager.
1 PFP MSR, 9/18/2012 Particles and Fields Package Monthly Status Review (MSR) September 18, 2012 Dave Curtis, PFP PM.
1 PFP MSR, 12/13/2011 Particles and Fields Package Monthly Status Review (MSR) December 13, 2011 Dave Curtis, PFP PM.
March 28, 2011 MAVEN SWEA instrument Pre-CDR Peer IRAP March 28-29, IRAP Management MAVEN SWEA Instrument Pre-CDR Peer Review IRAP, March.
1 PFP Team Meeting Particles and Fields Package Weekly Team Meeting, SSL April Dave Curtis, PFP PM.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
20-1 MAVEN iPSR Oct 30-31, 2012 Particles and Fields Package Pre-Ship Review October 30-31, PFDPU D. Gordon, W. Donakowski & PFDPU Team Mars.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration with PFP, Qualification, ATLO 2011 March 28 Dave Curtis.
Introduction to MAVEN Dave Brain LASP / University of Colorado On behalf of the MAVEN team.
MAVEN-SWEA Assembly, Integration & Test (AIT) Contents AIT: CESR Team Facilities Main subcontractors Applicable documents AIT documentation Cleanliness.
1 PFP Team Meeting, 10/26/2009 Particles and Fields Package Weekly Team Meeting, SSL October 26, 2009 Dave Curtis, PFP PM.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
Operational Flight Software
Working with MAVEN Data
Solar Probe Plus FIELDS MEP iPSR SOC Marc Pulupa April 10, 2017
Particles and Fields Package (PFP) SWEA Pre-CDR Peer Review
Gayle K. Martin November 14, 2016
FIELDS Mission Assurance Manager University of California, Berkeley
CINEMA System Engineering
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
FIELDS SCM Thermal iPER
Solar Probe Plus FIELDS Main Electronics Package iPER EMC Feb 2, 2017
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
Particles and Fields Package Quarterly Status Review (QSR)
Integration and Test Organization Chart
GLAST Large Area Telescope
Integration and Test Organization Chart
Presentation transcript:

24-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : ATLO Support Dave Curtis Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission

24-2 MAVEN IPSR October 30,31, 2012 Post Delivery Support PFP ATLO team consists of: –Dave Curtis, Systems, Package Manager –William Thompson (LASP), Systems, LPW/EUV, Local –Tony Mercer, Test Conductor –Paul Turin and Instrument Mechanical leads for mechanical operations –Dorothy Gordon, PFDPU lead, for electrical integration –Millan Diaz-Aguado, Thermal (esp. Thermal Vac) –Tim Quinn, GSE –Jorg Fischer, Chris Scholz, QA –MAG Team to support Magnetics Tests –Instrument leads will support critical testing William Thompson is local and can be on the spot on short notice; the rest of the team will be available as needed –Will will be trained to monitor the package during Self-Test and SVT Telemetry data will be available in real time at Berkeley for critical tests, reducing the need for large numbers of team members at ATLO –PFP GSE supports this Critical tests (CPT, EMC, Thermal Vac) will have extra team support

24-3 MAVEN IPSR October 30,31, 2012 ATLO On-The-Floor Support PFP Team Members will be on the ATLO floor to support: –Instrument Installation / Removal –LPW Whip Installation / Removal –SEP Sun Shade Installation –EGSE Stimulus Operation during functional tests SEP Radiation Source LPW Stimulus Rack EUV Stimulus –Red Tag Cover Installation / Removal –HV Enable Plug Installation / Removal –Pin-Puller stow –LPW Restraining Pin Removal

24-4 MAVEN IPSR October 30,31, 2012 ATLO GSE Both MSA and SOC can display PFP housekeeping PFP GSEOS computer will be at LM for local display of data Telemetry also available remotely in near real time for extended team support for Critical Tests On-the-floor GSE includes (per ICD): –LPW stimulus rack –SEP radiation source –EUV lamp –EUV hall effect sensor –MAG shield cans, test harness –MAG test magnetometers (for compatibility test, swing test) –Actuator reset tool, SEP flexure clamps, SEP handle –Red-tag covers, LPW deployment restraining pins

24-5 MAVEN IPSR October 30,31, 2012 Red-Tag, GSE Usage in ATLO

24-6 MAVEN IPSR October 30,31, 2012 Pre-Integration Bench Test On arrival at LM the PFP shall be bench-tested prior to integration LM shall provide facilities to support bench testing –Clean room –Purge gas provided –Adequate Bench space provided –Power provided –SSL provides instruments, EGSE, MGSE, purge manifold, test plans Will perform a CPT to ensure instrument survived shipping and is ready to integrate LM will hold a review prior to integration to verify readiness

24-7 MAVEN IPSR October 30,31, 2012 PFP Testing on the Spacecraft PFP tests consist of: –Comprehensive Performance Test (CPT) Performed right after integration and again after environments Includes external stimulus for SEP, LPW, EUV, MAG ~1-2 days –Limited Performance Test (LPT) Part of Spacecraft ‘Self Test’ performed between environments, after moves, etc. No external stimulus ‘Test Copper’ ~1-2 hours –System Verification Tests (SVT) Simulates mission events, such as science orbit PFP team has provided test scripts to LM for these tests and is working with LM to convert and verify those scripts and match them to the test cases LM is aware of PFP test constraints, such as no high voltage outside of vacuum –High voltage enable plugs shall be removed to prevent accidental HV turn on.

24-8 MAVEN IPSR October 30,31, 2012 Post Spacecraft Environment Test SWEA, SWIA, STATIC functionality cannot be assessed outside a calibration chamber –HV can’t be operated in air –Need electron/ion guns to verify detectors, electrostatic optics, foils There is a spot in the ATLO flow after environments for SWEA, SWIA, STATIC to be removed from the spacecraft and returned to SSL for test –Need a few weeks at SSL to run the three instruments through the calibration chambers. –A subset of the calibrations previously run –Use the same shipping arrangements used to get them to ATLO –Post-re-integration functional test –Current plans allow this to be completed at LM This has been the baseline since the before PDR –Supported by LM ATLO planning