Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010
2 Agenda Strategic Plan/CIP Background Scope and Architecture Spending Plan/Procurement ROI Future Steps Recommended Board Action
3 Mobile Work Management Program Loudoun Water Strategic Plan Goal – Leverage technology to optimize business practices Part of 2010 CIP
4 Background Current use of laptops in field – Clumsy, slow, require connectivity Need for more efficient mobile platform – Automate data entry/management – Boost data integrity – Mapping and routing functions – Decrease windshield time, increase time on task – Improve customer service
5 Background Initial task order $48,036 to Gannett Fleming for Implementation Plan – Define phased approach – Recommend technical solutions – Foundation for new task order
6 Task Order #3 Pilot Project, $186,600 Establish framework for mobile work management platform – Back office ‘middle-ware’ Two mobile applications on iPhones/iPads – Hydrant Flushing – Meter Service Work Completion in Q2, 2011
7 Hansen Work Orders MUNIS Service Requests GIS Maps Mobile Middleware Mobile User Applications Mobile Framework Middleware Business Applications Hydrant Flushing Meter Service
8 Mobile – CIP Total 2010 CIP$500,000$400,000$200,000$1,100,000 Revised 2011 CIP Projection $150,000$500,000$450,000$1,100,000
9 Procurement Actions Task Order #1 Implementation Plan (Complete) Task Order #3 Pilot Project Possible Future Mobile Implementation Phases - Separate Procurement(s) Today Timeline $48k $186k $866k
10 ROI 20% gain in efficiency through reduced mileage and associated costs Hydrant flushing – $20k - $40k in labor savings – Intangible benefits (data integrity, etc.)
11 Future ROI Analysis Procurement for additional mobile apps – Cross connection/backflow – Manhole checks – Easement maintenance
12 Recommended Board Action I move the Board approve Task Order No. 3 with Gannett Fleming for an estimated not to exceed cost of $186,600 and authorize an approximate 10 percent contingency to be controlled by the General Manager, for an authorized budget ceiling not to exceed $205,000 without further Board approval.
13 Questions?