STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

HCAL RBX PRR Overview Jim Freeman RBX PRR March 1-2, 2001.
CALICE WHCAL testbeam at SPS H8 27 sep – 03 oct: 6 days for energies up to 180 GeV (+ polarity)
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Luminosity Monitor MWPCs, commissioning. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg,
RBX PRR - March 1-2, H C A L HCAL RBX PRR Readout Box (RBX) PRR Dan Green HCAL Project Manager.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
MTCC –II & HCAL noise chasing Mandakini Patil India-CMS meeting Jan07 Shantiniketan.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
Electrical and Optical Cables Installation at P5 What When How H. Breuker
André Augustinus 16 September 2002 Safety issues.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB Fabio Montecassiano INFN PH/CMM.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
M. Gilchriese Sector Status Module Loading Task Force Meeting November 18, 2004.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
India-CMS Collaboration Meeting Chandigarh, 7-8 Oct 2004 Report to the Collaboration A. Gurtu.
U. Of Rochester DOE Review, July 15-16, 2002: P. de Barbaro, CMS1 CMS Project at UR Pawel de Barbaro University of Rochester DoE Review July 15-16, 2002.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
Status of HO Installation and Commissioning Shashikant Dugad (DHEP, TIFR) India-CMS Meeting BARC, July 2007.
Outlook Production of the 12 DPs (220m Stations) Installation of the DPs in the LHC Tunnel Status of the RP Systems/Services Resources Production of DPs.
On behalf of joint ITEP / IHEP team: A. Arefiev, N. Filimonov, T. Kvaratskheliya, I. Machikhiliyan, P. Shatalov, T. Zakoryuchkina, A. Zhokhov, S. Zvyagintsev.
E.Guschin (INR,Moscow) 17 July 2007 CALO commissioning group meeting CERN Status of PS/SPD LED system.
DSS  Informal review Tuesday 24 th October 10:00 Room , organized by Laurent Roy.  Subsystems will not be allowed to run overnight or at weekends.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
1 OperationsOperations CSC is stable running since HI run has started. The low CSC occupancy in HI running allows us to operate all HV channels at nominal.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
TB Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
Single Module Tests (electrical) Inspect connectors and cables for visible damage C-measurement: make sure all pads are correctly connected HV test (1.5.
1 Onsite Status Itaru Nakagawa RIKEN/RBRC. 2 Schedule.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
D. Piccolo Barrel RPC Cable procurement, installation Davide Piccolo INFN Napoli.
1 HBD Commissioning Itzhak Tserruya DC meeting, BNL December 13, 2006 Progress from October 3 to November 28, 2006.
L1Calo Installation Status Murrough Landon, QMUL Level-1 Calorimeter Trigger (University of Birmingham, University of Heidelberg, University of Mainz,
Progress and plans for HO Installation S. Dugad, K. Sudhakar Tata Institute of Fundamental Research India-CMS Meeting at BARC, July 2005.
SPD VFE installation and commissioning (status and plans) I.Status of VFE test at Barcelona II.First commissioning experience at CERN (15 th -16 th March)
Status of HO Installation Shashi Dugad Tata Institute of Fundamental Research India-CMS Collaboration Meeting, Chandigar April 2007.
14 February 2007 G. Bohner, R. Bonnefoy, M. Crouau, P. Jacquet, C. Lacan, J. Lecoq, S. Monteil, P. Perret, G. Reinmuth, K. Suchorski LPC Clermont PS Very-Front-End.
Calorimeter global commissioning: progress and plans Patrick Robbe, LAL Orsay & CERN, 25 jun 2008.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Sensitivity of HO to Muons Shashi Dugad for HO group India-CMS Meeting 6-7 Oct
CMS Status & Commissioning Menu: 1 Recent Progress Commissioning Prior to and After First Beam Commissioning with first LHC Events Outlook Wolfgang Funk.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Aug 4, 2005 Hcal sx5 status/issues. overview CCM temperature readout DAQs for sx5hcal HCAL installation status SATOCRICH.
HCAL Fall meeting, Nov 11-13,`04 HCAL digital optic link and trigger mapping Ianos Schmidt The university of Iowa.
Detector status and commissioning: LUCID
09/02/2006 Muon week HV and LV systems status for Magnet Test S. Braibant, P. Giacomelli, M. Giunta.
DCS: Temperature Probes
Francois and Lau EATM 17 July 2012
DCS: Temperature Probes
Services – First Considerations Sigi Wenig / Nicolas Massol ATLAS Tracker Upgrade Workshop Valencia December 2007 Existing services (in cryostat.
Propose to replace HPDs in R1 and R2 with SIPMs, ASAP
CMS Area Working Group Meeting
DT Infrastructure: LV, HV, Gas
Pictures and comments from Vitali Smirnov August 2010
CSC Electronics Installation and Commissioning CSCE I&C
CSC Electronics Installation and Commissioning CSCE I&C
Presentation transcript:

STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007

India-cms meeting, Delhi Sep20072 STATUS OF HO All 72 honeycomb panels (with trays inside) are installed on all wheels All 36 RBXs are installed on all the wheels Already the wheels YB+2, YB+1, YB0 have gone underground Vertical panels (sectors 1 and 7) were installed after the wheels went underground Still YB-1 and YB-2 are on the surface and are expected to go underground around 10 th October. On these wheels even vertical panels were installed on the surface itself

India-cms meeting, Delhi Sep20073 STATUS OF HO For the moving wheels (YB± 2, YB ±1), there are 6 RBXs per wheel and signals from two adjacent sectors come to one RBX. For the YB0 wheel, signals from one sector go to one RBX situated on that sector Even though one wants to test the boxes after installation on surface, it was not possible for YB+1 because of lack of time and for YB0 because no proper infrastructure YB+2, YB-1 and YB-2 are tested on surface

India-cms meeting, Delhi Sep20074 STATUS OF HO DSS cables (LVTMM cables) were introduced suddenly just before YB+2 wheel went down i.e. in Jan 2007 These were meant for measuring temperature and moisture and thus to detect water leak But it was very inconvenient to install them on our boxes because of geometrical position

India-cms meeting, Delhi Sep20075 STATUS OF HO YB+2 –Everything is installed –Water leak test done –Signal patch panel is ready with all optical fiber cables from detector terminating in PP –Wheel went underground in Jan 2007 –Cable chain to take signals from PP to USC are laid –CCMs are fine for LHC locking frequency –LVTMM connections are done –Commissioning of 3 boxes remaining

India-cms meeting, Delhi Sep20076 STATUS OF HO YB+1 –Everything is installed. –Water leak test done –Wheel went underground in Feb 2007 –Cable chains are installed from PP to USC –Commissioning of boxes is done recently –LVTMM connections are done –CCMs are fine for LHC locking frequency

India-cms meeting, Delhi Sep20077 STATUS OF HO YB0 –HV cables go to different places (near, far, underground) –LV cables go to two sides (near and far) –PP is on near side only –Wheel went underground in March 2007 –PP contains only 3 cables from each RBX(TTC, calibration, laser) and from all the 12 RBXs –Data cables go from RBXs all the way to USC

India-cms meeting, Delhi Sep20078 STATUS OF HO YB0 –Water leak test done –Optical fiber cables go along the vacuum tank and then go radially along the exit path on chosen sectors to PP or USC –The chosen sectors are 11 and 1 on +side and 12 and 2 on - side

India-cms meeting, Delhi Sep20079 STATUS OF HO YB0+ –Cables to PP have been laid for the 6 sectors –Data cables have been laid to a temporary place and boxes for commissioning checks –4 CCMs checked are OK. 2 more to be checked –5 boxes are OK for data. The box on sector 6 has problem in one fiber which carries signals from three pixels. Problem is being looked into. –Thermal screen is installed already on S10 –LVTMM connections are done

India-cms meeting, Delhi Sep STATUS OF HO YB0- –Cables from RBXs to PP are laid for the lower half –LVTMM connections are done for lower half –For upper half, cables will be laid after proper cable trays are installed –Data cables will be taken again temporarily to a place for testing of boxes

India-cms meeting, Delhi Sep STATUS OF HO YB-1 –Everything is installed –Boxes are tested on surface –CCMs are tested and found to be OK –Remaining work Water tube connections and water leak test LVTMM connections

India-cms meeting, Delhi Sep STATUS OF HO YB-2 –Everything is installed –All boxes are tested and found that one RM in S4 has problem with pedestals (need to change one RM if spare is there) –CCMs are tested and found to be OK –Remaining work LVTMM connections to be done Water tube connections are almost done but leak test is yet to be done

India-cms meeting, Delhi Sep STATUS OF HO YB-1 and YB-2 –ZEC people only will do water tube connections and leak test –They should be taking up the job sometime next week –YB-1 is scheduled to go down on 10 th Oct –YB-2 is scheduled to go down on 20 th Oct –LVTMM connections also are to be done before lowering

India-cms meeting, Delhi Sep STATUS OF HO Patch panels in control room were not ready for HO They needed modification due to changes in our connections and mapping needs The panels have arrived and after some modifications they will be installed Vladimir will do connections in the control room Map is finalized

India-cms meeting, Delhi Sep STATUS OF HO The e-log entries can be seen from anywhere if you have an afs account at cern –The path is –You have to login using your afs account and then go to subsystems and under that you go to HCAL –Then you will see all entries for hcal –To understand the entries better you should be more familiar with installation related details

India-cms meeting, Delhi Sep STATUS OF HO This year during the test beam run HO is tested with RBX fitted with Si-PM diodes There is encouraging response But there is dependence on temperature People are thinking to replace HPDs with Si- PM diodes for the upgrade Sudeshna will talk about this more in detail