T1 status and plans Fabrizio Ferro – INFN Genova 5 th Technical Coordination Workshop 25-26 February 2014 - Bogis-Bossey.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

T1 status and plans INFN Genova November 2014 Collaboration Meeting.
1 Status of the CMS Pixel project Lorenzo Uplegger RD07 Florence 28 June 2007.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
Saverio MINUTOLITIG meeting, 10 February Report on T1 installation activities and achievements made during this shutdown.
Saverio MINUTOLITOTEM T1 Readiness Review, 30 November Readiness Report on T1 Electrical Systems and Electronics.
ECAL status Outline: Signal cable connectors quality check results: –ADC side –PM side ECAL PM/C-W channels commissioning status Access activities Further.
Antiproton Lens Replacement (Unfortunately Part 2) Keith Gollwitzer Antiproton Source Department for the Experts and Mechanical Support Department Target.
Saverio Minutoli INFN Genova 1 T1 Electronic status Electronic items involved: Anode Front End Card Cathode Front End Card Read-Out Control card Slow Control.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
20/04/2012Rui De Oliveira1 20/04/2012. Rui De Oliveira2 30 cm x 30 cm example.
41 st LSC – March 21, 2014 G.J. Coelingh, TE-MPE-EE Long Shutdown 1 Status Report The upgrade of 600 A Energy Extraction Systems.
Jump Starting ITS Deployment in Los Angeles County using Wireless Communications Lessons Learned.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
XXVI Workshop on Recent Developments in High Energy Physics and Cosmology Theodoros Argyropoulos NTUA DCS group Ancient Olympia 2008 ATLAS Cathode Strip.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT) Gennaro Ruggiero (PH/TOT) LHCC minireview – 06 May 2009.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
RADIATION SOURCE Design Review Dmitry Gudkov BE-BI-ML.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Building 16, 17, 153, 162, 173 (256) Safety - Renovation CH DENARIE CERN PH/DT MARCH 2011.
Outlook Production of the 12 DPs (220m Stations) Installation of the DPs in the LHC Tunnel Status of the RP Systems/Services Resources Production of DPs.
CERN EN-EL Cabling and Optical Fibre Section CERN EN-EL Cabling and Optical Fibre Section Mini Workshop, Simao Machado, EN/EL/CF.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
1 OperationsOperations CSC is stable running since HI run has started. The low CSC occupancy in HI running allows us to operate all HV channels at nominal.
Muon Tracking Meeting SOR issue First priority Diagnostic: MCH DetectorScriptError Arriving at the initialization stage: the whole or part.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
SLHC Engineering Upgrade FCAL Remove-Install step by step procedure. Mircea Cadabeschi-University of Toronto March 01,
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
FPD STATUS Carlos Avila Uniandes/UTA 1. FPD overview 2. Roman pot and detector status 3. FPD readout integration status 4. Software status 5. Stand-alone.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
HF Source Drivers Performance Observations and Recommendations Paul Debbins University of Iowa Nov. 10, 2004.
HF FE Radiation tests at the CHARM facility Tullio Grassi 4 June 2015 Documentation on:
Dec
Saverio MINUTOLITOTEM Electronics W.G., 9 December T1 electronics status.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
R ADIATION P ROTECTION ASPECTS LSS1 - TAN REGION Cristina Adorisio (CERN - DGS/RP)
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
T2 Status Report IP5 Installation Future plans. IP5 installation The mechanical structure has shown problems on installation and should be changed slightly.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
CALO News Pascal Perret LPC Clermont 22 January 2012.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
RF Pick-Up Measurements in the 2004 SPS Testbeam Before installation of silicon detector assemblies in the Roman Pot: Antenna insertions for measurement.
The Phase-1 Extension of the CMS Endcap RPC System Michael Tytgat on behalf of the CMS Collaboration Outline :  Introduction  RPC Upgrade  Simulation.
Kitakami Side AHCAL Assembly or anywhere in any detector.
LHC-RF activities in LHC PT 4 TS2 YETS LS2
- CT INSTALLATION PROCEDURE OVERVIEW -
Introduction Status before the 2009 run Results from the 2009 run
First data from TOTEM experiment at LHC
HF Test station at P5 A.Mestvirishvili.
CMS Area Working Group Meeting
T1 status (a selection from EDR presentations)
T1 Electronic status Conclusions Electronics Cards:
K TO 12 CHS MODULE FOR GRADE 9, PP
Integration issues at IHEP
Preparations for test of
The electronics system of the TOTEM T1 telescope
November technical stop activities:
Limited Streamer Tube Project Summary
Presentation transcript:

T1 status and plans Fabrizio Ferro – INFN Genova 5 th Technical Coordination Workshop February Bogis-Bossey

T1 at Point 5 F.Ferro - T1 status and plans

Maintenance & commissioning Already done ◦ Repaired all CSC’s damaged during extraction ◦ Checked CSC alignment (Dmitry) ◦ Readout  Replaced out-of-sync VFAT’s  Extensive check of ground connections To be done ◦ Readout  Replace VFAT’s with bad occupancy patterns  Replace position sensors and radiation monitors ◦ Commissioning  Test fibers, DAQ, etc. F.Ferro - T1 status and plans

Installation tools upgrade The procedures for insertion and extraction of T1 have been upgraded : ◦ last (first) ~1 m of insertion (extraction) will proceed with parallel and controlled (via screws) movements of the two half-arms ◦ load and tension on the assembly monitored through load cell ◦ relative z position of two half arms monitored and constrained mechanically by new temporary extensions (Roman Stefanovitch) F.Ferro - T1 status and plans Successful simulation of insertion/extraction of one arm as in real life (fast and safe)

HF+ water leak on Feb.1 st, 2014 Water leak (likely) caused by a faulty connector inside the Wiener Maraton power supply A Technical Incident Panel has been set up by Wolfram (2 meetings already done) ◦ see minutes for details on investigation and actions All 4+1 T1 power supplies need to be repaired/changed asap to reinstall them and to allow surface tests and commissioning (1 needed) F.Ferro - T1 status and plans

Installation: outlook Manpower ◦ CMS: 2-3 CMS people with experience (Dmitry+2) ◦ TOTEM: T1 crew Timing ◦ Truss installation CMS* ~6h ◦ 2 ¼ on platform CMS* ~4h ◦ Temp. services + Commissioning TOTEM 1.5d (more if viable) ◦ Cage-truss alignment CMS* ~4h ◦ Insertion, fastening, check CMS* ~1d F.Ferro - T1 status and plans Extrapolation from operations Operations can be faster now: services already installed, more experience, more tools * In case, 1-2 TOTEM technicians to support/replace CMS ones.

Looking forward to... F.Ferro - T1 status and plans...reinstalling both T1’s during LS1