ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt. Alka Mathur ACCOUNTANT Sh. B.C. Jain
Financial Work Load in Unit S. No. Name of WorkClient Deptt. A& F Sanction Expenditure till date Balance Work ARE – I Sh Rajesh Gupta 1USQ & LSQ at Chainpura Home ARE – II Sh.S.K. Chejara 1Satsang Bhawan at Shri Radha Govind Deoji temple, Jaipur Trust ARE – III Sh.V.B. Mathur 1Research Hospital at RHSU, Pratap Nagar Medical Total Rs. In Lacs
Important Works Completed during last 5 years
AMBEDKAR BHAWAN, JAIPUR Completion Cost – Rs Crs. Foundation Stone laid by Hon’ble Chief Minister on Inaugurated by Hon’ble Chief Minister on
RAJASTHAN HEALTH SCIENCE UNIVERSITY, JAIPUR Completion Cost – Rs Crs. Foundation Stone laid by Hon’ble Chief Minister on Inaugurated by Hon’ble Chief Minister on
Important Works in Progress
POLICE HOUSING SCHEME No. of Quarters:200 Nos. LSQ and 8 Nos. USQ Total Cost:Rs Crores Location:Chainpura, Jaipur Date of Start: Stipulated Date of Completion: Expenditure till Date:Rs Crores Likely Completion date: Bottlenecks if any:slow progress by contractor
Satsang Bhawan at Shri Radha Govind Deoji temple, Jaipur Total Cost:Rs. 4.0 Crores Location: Shri Radha Govind Deoji temple, Jaipur Date of Start:July, 07 Date of Completion :September, 09 Expenditure till Date:Rs Crores Likely Completion date: Present Status:Structure work completed, Finishing work in progress
Research Hospital at RHSU, Pratap Nagar, Jaipur Total Cost: Rs Crores Location: Pratap Nagar, Jaipur Date of Start: Jan, 08 Date of Completion: March, 09 Expenditure till Date: Rs Crores Likely Completion date: Bottlenecks if any : Work stopped as client has not deposited money
Monitoring of Toll Projects S. No. Name of WorkModeConstruction Cost Concession Period Toll Collection Agency 1Masi Bridge on Sanganer-Malpura Road (SH-12) Actual Plus Rs lacs 13 Years 05 Months & 01 Days(upto ) Departmental (Tender for toll contract under process) 2Chomu-Ajitgarh- Shahpura Road Actual Plus Rs lacs 14 Years 11 Months & 22 Days(upto ) Departmental (Tender for toll contract under process) 3Chala- Neem ka Thana –Kotputli Road TenderRs lacs 6 Years 02 Months & 27 Days(upto ) M/s Ramfool Gurjar, Bhiwadi
Proposed New Works S. No. Name of WorkClient Deptt.ModeEstimated Cost 1.Buildings for different Bards near Ambedkar Bhawan Social Justice and Empowerment Deptt. Actual plus Rs Crores