Mark Woodley, SLACATF2 Project March 20-21, 20071 Summary of Tuning, Corrections, and Commissioning.

Slides:



Advertisements
Similar presentations
Sha Bai, Philip Bambade, Glen White FJPPL – FKPPL ATF2 workshop LAL, 11~13 February, 2013 Orthogonality of beam waist corrections in the presence of IPBSM.
Advertisements

Summary of the discussion for the commissioning session 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 6/ 1/ 2006 T.Okugi (KEK)
Coupling Correction in ATF2 EXT 7 th ATF2 Project Meeting, december 2008 C.Rimbault, LAL Orsay.
EXT Beam Measurements & Corrections Dispersion, Coupling, Beta Matching 10th ATF2 Project Meeting, June M. Woodley1/31.
ILC BDS Alignment and Tuning Studies Glen White SLAC/QMUL 8 November 2005 Progress report and ongoing plans for BDS alignment and tuning strategy.
-brief report of October runs and some inputs for the Nov/Dec planning – Nobuhiro Terunuma, KEK, ATF ATF session on LCWS13, Tokyo Univ., Nov. 13, 2013.
Analysis of ATF EXT/FF Orbit Jitter and extrapolation to IP (Data of ) ATF2 Project Meeting K. Kubo.
1.Beam Tuning Simulation 2.IP Beam Position Stability 2-1 ) Magnet Vibration 2-2 ) IP position jitter subtraction for 2 nd bunch with FONT feedback 2-3.
High Resolution Cavity BPM for ILC final focal system (IP-BPM) ILC2007/LCWS 2007 BDS, 2007/6/1 The University of Tokyo, KEK, Tohoku Gakuin University,
Discussion on Milestone and schedule Toshiyuki Okugi ATF2 commissioning meeting 1 / 7 / 2009.
Alignment and Beam Stability
Kicker Optics – or – Selected ATF-II EXT Line Performance Issues ATF-II Technical Review, April M. Woodley1/40.
Status of QBPM Electronics and Magnet Movers as of June 3 rd 2008 D. McCormick, J Nelson, G White SLAC S Boogert Royal Holloway Y. Honda, Y.Inoue KEK.
ATF2 optics … 1 3 rd Mini-Workshop on Nano Project at ATF ATF2 optics, tuning method and tolerances of initial alignment, magnets, power supplies etc.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
FFS Issues in the 2011 autumn continuous operation Toshiyuki OKUGI (KEK) 1/13/2011 The 11 th ATF2 project meeting SLAC, USA.
T. Okugi and M. WoodleyDecember 21, th ATF2 Project Meeting Summary of Session on Hardware/Devices for Commissioning.
Fifth ATF2 Project Meeting, dec. 2007, KEK, Japan Emittance measurements with multiple wire-scanners and quadrupole scans in ATF EXT C. Rimbault,
ATF Instrumentation Status and Planning 3 December 2007 Juan Cruz, Justin May, Doug McCormick, Janice Nelson, Tonee Smith, John Wray.
Mark Woodley, SLACATF2 Software Review (June 18, 2008)1 ATF2 Layout/Optics (v4.0) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
June 30, th ATF2 Project Meeting Andrei Seryi for the ATF2 team May 2010 Continuous Run Operation.
Summary of Commissioning and Tuning session Philip Bambade LAL-Orsay 5 th ATF2 project meeting KEK, 21 December 2007.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
ILC BDS Static Beam-Based Alignment and Tuning Glen White SLAC 1.Aims. 2.Error parameters and other assumptions. 3.Overview of alignment and tuning procedure.
Summary of Status Towards Goal1 and Future Plans Glen White, SLAC 15 th ATF2 Project Meeting, KEK January
Emittance Measurements and Related Experimental Results 15th ATF2 Project Meeting, January M. Woodley1/44.
Global Design Effort SLAC contribution to ATF2 for discussions at S4 expanded meeting April 10, 2007.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
EXT: Summary of activities, software development, and tuning performance 11th ATF2 Project Meeting, January M. Woodley1/29.
Analysis of Multipole and Position Tolerances for the ATF2 Final Focus Line James Jones ASTeC, Daresbury Laboratory.
Mark Woodley, SLAC5th ATF2 Project Meeting (December 19, 2007)1 ATF2 Layout/Optics (v3.8) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing.
Commissioning Hardware and IP Configuration of ATF / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)
Mark Woodley, SLAC6th ATF2 Project Meeting (May 27, 2008)1 ATF2 Layout/Optics (v4.0) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
Initial beam size commissioning for ATF2 T.Okugi 3rd ATF2 Project Meeting, KEK 12/ 19/ 2006.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
Mark Woodley, SLACATF2 Project March 20-21, Next version of MAD decks (v3.7): what needs to be added/deleted?
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16.
Emittance measurements with multiple wire-scanners and quadrupole scans in ATF EXT C. Rimbault, Brossard, P. Bambade (LAL) Main goal : - Try to improve.
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
ATF2 Software Review LAL June 2008 Philip Bambade & Glen White ATF2 weekly meeting June
DRAFT: What have been done and what to do in ILC-LET beam dynamics Beam dynamics/Simulations Group Beijing.
Simulation of the α, dispersion, coupling and β multiknobs in large β optics Sha Bai, Philip Bambade, Benoit Bolzon, Javier Resta Lopez
Status of EXT coupling measurement analysis 9 th ATF2 project meeting C.Rimbault (LAL) S. Kuroda, T. Tauchi, N. Terunuma (KEK), G. White, M. Woodley (SLAC)
For discussion of ATF2 beam time requests SLAC team October 1, 2008.
ISG – Damping Ring Physics and Design Group ATF – 2003// focus on the TRC challenge Marc Ross – 1.Instability about which little is known: Fast ion,
Status and plan of Beta-matching in Extraction line Kiyoshi Kubo.
Wakefield effect in ATF2 Kiyoshi Kubo
ATF2 Lattice v4.5 Matching and Tuning Performance with Lucretia Glen White, SLAC LCWS2011 Granada, Spain.
2nd ATF2 Project Meeting (May 30, 2006)M. Woodley [SLAC]1 ATF2 Layout/Optics (v3.3) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
ILC BDS Commissioning Glen White, SLAC AWLC 2014, Fermilab May 14 th 2014.
4 th ATF2 Project Meeting, 31 May 2007 A. Seryi 1 Summary of SLAC simulation study of emittance growth in the ATF extraction line SLAC team: J. Amann,
Hardwares for commissioning 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 5/ 31/ 2006 T.Okugi (KEK)
Simulation for Lower emittance in ATF Damping Ring Kiyoshi Kubo Similar talk in DR WS in Frascati, May 2007 Most simulations were done several.
IP Tuning Task Updates Glen White, SLAC January
ILC BDS Alignment, Tuning and Feedback Studies
Expected hardware status and Priority of the commissioning task
Emittance Diagnostics
Tolerances & Tuning of the ATF2 Final Focus Line
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Emittance Dilution and Preservation in the ILC RTML
DFS Simulations on ILC bunch compressor
ATF2 IP Tuning Task Simulation Updates
3rd ATF2 Project Meeting, December 18-20, 2006
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
ATF2 Layout/Optics (v3.6) Existing ATF Extraction Line
Simulation of the FCC-ee lattice with quadrupole and sextupole misalignments Sergey Sinyatkin.
Yuri Nosochkov Yunhai Cai, Fanglei Lin, Vasiliy Morozov
Presentation transcript:

Mark Woodley, SLACATF2 Project March 20-21, Summary of Tuning, Corrections, and Commissioning

Mark Woodley, SLACATF2 Project March 20-21, Tuning (0): recent results from ATF single-bunch beam up to 2×10 10 e-/bunch transported all the way through the DR and into the EXT line routine tuning in DR reproduces 25 nm normalized vertical emittance (zero current limit) current-dependent emittance growth observed in DR... consistent with IBS much larger current-dependent emittance growth observed in EXT Preliminary

Mark Woodley, SLACATF2 Project March 20-21, Tuning (1): EXT sextupoles everyone agrees not to use (4) strong EXT chromatic correction sextupoles for commissioning Okugi-san showed that their improvement to energy bandwidth (±1%) is negligible Glen White showed that they aren't needed for achieving 35 nm spots Okugi-san suggests not installing them, Woodley suggests turning them off Difference come from that of chromaticity at extraction line. FF line is optimized with Sexts in extraction line.

Mark Woodley, SLACATF2 Project March 20-21, Tuning (2a): Okugi-san's simulation (1) includes quadrupole roll errors (300 urad rms); 100 seeds uses 2 IDX skew quadrupoles at SF1X and SF4X locations (QS1X, QS2X) for vertical dispersion correction –corrects both DY and DPY using 2 independent quad strengths uses 4 IDX skew quadrupoles (QK1X,QK2X,QK3X,QK4X) for coupling correction finds all skew quadrupole strengths OK for ±5 amps

Mark Woodley, SLACATF2 Project March 20-21, Tuning (2b): Okugi-san's simulation (2) includes incoming DY/DPY and quadrupole roll errors (300 urad rms); 100 seeds uses same correction scheme as simulation (1) finds maximum correctable residual DY is 17 ML9X (IDX ±5 amps) for maximum vertical dispersion correction, QK1X needs > 12 amps, QK4X needs > 5 amps, other skew quadrupoles OK for ±5 amps if quadrupole roll error rms is reduced to 100 urad, QK1X needs > 10 amps, other skew quadrupoles OK (QK4X marginal) for ±5 amps

Mark Woodley, SLACATF2 Project March 20-21, Tuning (3a): Woodley's simulation (1) includes quadrupole roll errors only ( urad rms); 100 seeds uses 2 IDX skew quadrupoles near QD2X and QD5X (QS1X,QS2X) for vertical dispersion correction –corrects DY with skew quadrupole "sum knob" (DPY is correlated) –with no errors, vertical emittance growth from residual coupling < 2.5% for |DY| < 10 mm –QS1X and QS2X currents < 0.5 amps uses 4 IDX skew quadrupoles (QK1X,QK2X,QK3X,QK4X) for coupling correction QK1X needs > 12 amps for 300 urad roll rms, maybe OK for 100 urad roll rms; other skew quadrupoles OK for ±5 amps (QK4X marginal at 300 urad roll rms) concludes maximum skew quad strengths are completely determined by assumed rms of quadrupole roll errors (Sugahara-san suggested at 3rd ATF2 Project Meeting that urad might be achievable)

Mark Woodley, SLACATF2 Project March 20-21, Tuning (3b): Woodley's simulation (2) includes quadrupole offsets (50/30 um X/Y rms) and quadrupole roll errors (300 urad rms); 100 seeds uses same correction scheme as simulation (1) finds QS1X,QS2X,QK2X,QK3X all OK; QK1X needs > 10 amps; QK4X needs > 5 amps

Mark Woodley, SLACATF2 Project March 20-21, Tuning (3c): Woodley's simulation (3) includes quadrupole offsets (50/30 um X/Y rms) and quadrupole roll errors (300 urad rms); 100 seeds includes skew quadrupole errors in DR extraction channel that, on average, blow up vertical emittance by 100% –6 thin skew quadrupoles (extraction kicker #1, QM6R.1, QM7R.1, 3 septa) –maximum uniformly-distributed random strength ≈ 15 amps uses same correction scheme as simulation (1) finds QS1X,QS2X,QK3X all OK; QK1X needs > 15 amps; QK2X needs > 5 amps; QK4X needs > 12 amps

Mark Woodley, SLACATF2 Project March 20-21, Tuning Conclusions Okugi-san suggests using (4) existing IDX skew quadrupoles for QS1X, QS2X, QK2X, and QK3X; make 2 new skew quadrupoles for QK1X and QK4X –strength equivalent to 10 amps (0.22 T) Woodley found magnetic measurements data for IDX skew quadrupoles up to 20 amps... question to Terunuma-san: can IDX skew quadrupoles operate up to 20 amps? (magnets are not water cooled) –if so, provide 20 amp power supplies for QK1X and QK4X; still would need 2 new IDX skew quadrupoles (can we get them?) –if not, agree with Okugi-san to build 2 new stronger magnets, but would prefer strength equivalent to 20 amps (0.44 T) Woodley/Okugi-san must compare notes and decide on optimal locations for QS1X and QS2X

Mark Woodley, SLACATF2 Project March 20-21, Corrections (1): DR extraction layout present design model of extraction trajectory not consistent with installed locations of (3) septa actual extraction trajectory depends on settings of QM6R.1 and QM7R.1 (beam passes through these quadrupoles off-axis) should we realign the septa? (flexibility of vacuum chamber bellows) how do we cope with changes to settings of QM6R.1 and QM7R.1?

Mark Woodley, SLACATF2 Project March 20-21, Commissioning (1): hardware beam "presence" (current/charge/losses) –KEK will provide ICTs and screen monitors –need reference cavity amplitude values from EPICS –SLAC to provide thin-fiber PLIC system to help localize losses (?) BPMs –would like to create a temporary QBPM control panel for ATF control system for commissioning... need "raw" I & Q values from EPICS –other values from "first pulse" calibration scheme (high/low/left/right) (?) –"production" QBPM control/readout software to be provided by SLAC/UK FFTB magnet movers –movers should be pre-calibrated (X/Y/roll) –"production" mover control/readout software to be provided by SLAC/UK –hardware limit switch requested (movers self-limited due to use of cams?)

Mark Woodley, SLACATF2 Project March 20-21, Commissioning (2): activities rebuilt EXT line –optics verification, BBA, … –dispersion correction –emittance measurement and coupling correction Final Focus –diagnostic hardware to be commissioned in parallel to EXT commissioning activities (QBPMs, IPBPMs, Honda IP BSM, carbon filament IP wire scanner) –BPM offset / BBA studies will be done simultaneously with cavity BPM hardware commissioning –IP beam size tuning begins when Honda BSM and/or carbon filament IP wire scanner hardware is commissioned; fine tuning when Shintake monitor comes online