Project: ÆON BiG FRESH DISTRIBUTION CENTRE ( FDC ) 07 th FEB 2014 ÆON GLOBAL SCM Sdn. Bhd. ( V)
AEON GLOBAL SCM SDN. BHD. Agenda – 07 th FEB General overview of ÆON Malaysia Group cold chain development General overview of ÆON BiG cold chain development Status reporting fo ÆON BiG cold chain development Further schedule and planning
AEON GLOBAL SCM SDN. BHD. ÆON Group – Cold Chain Schedule 3 Item JanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDec AGSCM ÆON Group Cold Chain AEON-Big FDC AEON(M) PTC Outsourcing Scheme ÆON BiG FDC *(6 month extend) ÆON (M) PTC *(Extended contract +1 year) Study & Data Collection *(Includes Improvement Points) MoU ÆON BiG ÆON (MY ÆON BiG FDC Go Live *(To be confirmed) -End Contract Notice Development ÆON Cold DC *(5 year contract) Tender -3PL MoU ※ Is carried out when it reaches the required amount. ※ PC operation is each business company responsibility. AGSCM NOW Each company under their own responsible.
AEON GLOBAL SCM SDN. BHD.4 ÆON Big (FDC) – Schedule Proposal (as at 23 rd JAN 2014) Stage NoAction Oct NovDec Jan Feb Mar Apr May Jun Jul AugSep 1 1Understand function request 2Study – ABSB current process 3Study – ABSB expectation 4ABSB Volume Commitment 5Draft of FDC overall design 2 6Concentrate operation detail 7WMS development detail 8Prepare facility & trucks 9Education FDC staff 10Approval terms & condition 3 11Negotiate all supplier 12Contract with all supplier 413 ÆON BiG FDC LIVE *(Target) NOW TBD
AEON GLOBAL SCM SDN. BHD.5 ÆON BiG– General Requirement ÆON BiG – General Requirement *PENDING ペンディング Annual receiving volume Y2013 By Month By Store Name By Department Code By Supplier Name By SKU number By Unit of Measurement (UOM) By Receiving Temperature By Cost Price Fresh DC development Department involvement by phrase Volume ratio FDC target VS. Direct to store Function development Flow through Cross dock Storage Returnable Item
AEON GLOBAL SCM SDN. BHD.6 ÆON BiG– General Requirement ÆON BiG – General Requirement *PENDING ペンディング Delivery Material Palletized Wooden Plastic Cart Rack Thermo cover Quality Control Management (TBD) System Implementation WMS (TBD) Other Services Processing Services
AEON GLOBAL SCM SDN. BHD.7 ÆON BiG– Temperature Requirement ÆON BiG – Temperature Requirement ÆON (M) ÆON BiG Frozen Temperature: Department: Remarks: Chilled Temperature: Department: Remarks: Fresh Temperature: Department: Remarks: *PENDING ペンディング
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – February 8 MonTueWedThuFriSatSun FDC AB Subang 10:00 – 12: AB Subang 10:00 – 12:00 15 AM PTC 04:00 – 08: AB Subang 10:00 – 12: AB Subang 10:00 – 12:00 28
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – March 9 MonTueWedThuFriSatSun AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12:
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – April 10 MonTueWedThuFriSatSun 1234 AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12:
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – May 11 MonTueWedThuFriSatSun 28 Apr29 Apr30 Apr AB Subang 10:00 – 12:00 1 PH – Labour Day AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12:00 31
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – June 12 MonTueWedThuFriSatSun AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12:
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – July 13 MonTueWedThuFriSatSun 1234 AB Subang 10:00 – 12: AB Subang 10:00 – 12: PH – Nuzul Quran AB Subang 10:00 – 12: AB Subang 10:00 – 12: *PH – Hari Raya Puasa 29 *PH – Hari Raya Puasa 3031
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – August 14 MonTueWedThuFriSatSun 1 AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: AB Subang 10:00 – 12: PH – National Day
AEON GLOBAL SCM SDN. BHD. Schedule for Meeting – September 15 MonTueWedThuFriSatSun 1 LIVE PH – Replacement National Day 2345 AB Subang 10:00 – 12: AB Subang 10:00 – 12: PH – Malaysia Day AB Subang 10:00 – 12: AB Subang 10:00 – 12: