Assembly Organisation and Duration. Work Site Organisation STORAGE SMA18 UNLOADING CLEAN ROOM CERN-SITE CLEANING MANUFACTURE DIRTY TRIAL ASSEMBLY ISO7.

Slides:



Advertisements
Similar presentations
1.  Preparation of larger parts in a Clean room Class (ISO7)  Preparation of smaller parts in a “baldaquin” annex  Assembly in a clean-room Class.
Advertisements

Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Development and Quality Plans
Technology Use Plan Mary Anderson 7/29/08 EDTECH 571 click to go to each slide.
Special Linac WG meeting: Assembly of the ISOLDE Cryomodules – HIE-ISOLDE Survey and Alignment – March 19 th 2014 Jean-Christophe GaydeEN/MEF-SU Guillaume.
Business Continuity Check List PageOne. - Why Does Your Business Need A Continuity Checklist? Should the unexpected occur, your business will be able.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Pre-Project Activities Text Chapters 5 and 6. Pre-Project Activities 1.Contract Review 2.Development Plan 3.Quality Plan.
Software Quality Assurance Activities
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
From Research Prototype to Production
GLAST Large Area Telescope:
U N C L A S S I F I E D Progress Report on the Dual-Use Cryostat John C. Ramsey Los Alamos National Laboratory.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
Technical Support Activities in PH-ADO-PO
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
K. Foraz, S. Prodon TS-IC TS workshop – May 2005 Underground logistics K. Foraz, S. Prodon TS-IC.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
MTF – Manufacturing and Test Folder Large Scale Deployment of MTF Sonia Mallón Amérigo Elena Manola-Poggioli on behalf of the EDMS Team, TS-CSE.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
Gas System production for LHC detectors Stefan Haider EP / TA1 - Gas.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
C.MADEC - TTC meeting E-XFEL cryomodule assembly : prototyping phase at Saclay.
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
- HEMIC Facility Inspections. Common Losses A fire breaks out in a 16 story office building An employee had the tips of two fingers amputated Could these.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
1 Determining a client’s peripheral requirements  Determine current business practices  Determine peripheral requirements  Analyse and document existing.
ASSEMBLY OF THE IFMIF CRYOMODULE Janic Chambrillon On behalf of the SRF-Linac Team TTC Meetting - June 5th – 8th, Saclay.
INTERNAL JOB BULLETIN JOB TITLE : Warehouseman (Wells Operator)
WP High Beta Cavities Delivery
Crab Cavity Technical Coordination meeting:
Planning for Proto-DUNE PD Installation and Cabling at CERN
Teleconf ACS – FREIA 28th March 2017
Teleconference ACS – FREIA 31th May 2017
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Teleconference ACS – FREIA 10th May 2017
EHN1 Neutrino Installation Plans
LIU Wire Scanner Series Costs
UK RFD Pre-Series cryomodule
Teleconference ACS – FREIA 20th February 2018
L&V Manpower Development Prepared by: HR department Mar, 2013
Daresbury ESS In-Kind Contributions
Teleconference ACS – FREIA 19th June 2017
NSS integrated installation plan workshop Introduction
UPPSALA UNIVERSITY_GERSEMI PROJECT
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

Assembly Organisation and Duration

Work Site Organisation STORAGE SMA18 UNLOADING CLEAN ROOM CERN-SITE CLEANING MANUFACTURE DIRTY TRIAL ASSEMBLY ISO7 ISO5 PREPARATION CLEANING SMALL PARTS ISO5 Baldaqun Large Parts Small Parts Cavities SM18/SMA18 AREA CM Cryostat parts

Manpower and Assignment of Roles Role# FTEIdentified person(s)CompetencyRemark Assembly coordination1Y.Leclercq, L.WilliamsEng Assembly workforce Clean-Room tech.2 teams of 2G.Barlow+ X1, X2+X3 Mech Tech: Clean-room Trained and Cryo-module Trained 1 shift of 8h/day Components preparation (outside clean-room)1J.B.Deschamps, M.Souchet+FSUMech Techincludes cleaning Quality Control Team Quality Manager1 (part time)J.A.BousquetEng or tech eng Vacuum leak checks1 (part time)Technician to be identifiedVac Tech Survey alignment/checks2 (part time)G.Kautzmann, C.GaydeSurvey Tech Electr. Tests1 (part time)Technician to be identifiedElec Tech Assembly Support Team Assy follow-up and documentation1 (part time)J.A.BousquetEng Storage and Logistics1 (part time)J.B.Deschamps+FSUTech Cryo-module Design & Integration1 (part time)J.DequaireDes eng, Des tech Tooling design1 (part time)P.MinginetteDes eng, Des tech Workshop supporton needTBDWks Techre-work components/tooling Dirty trial assembly 1 (part time) TBD Mech Tech Maintenance Team Clean-room Housekeeper1 (part time)TBDTech Clean-room tooling1 (part time)J.A.Bousquet+FSUMech Tech Supporting Services Handling and transport1 (part time) TechSM18/SMA18 Cleaning1 (part time)M.Malabaila's teamTech HSE safetyon needTBDEng

On-site Quality Assurance Should be independent of the production Tasks specific to the first assembly: Take ownership of the draft procedures Follow the work in progress Modify/update the procedure in work according to lessons learned Photographic support Text update support Feedback to worksite Take action to modify procedures to come that may be affected by current changes General Tasks: Keep a manufacturing/assembly file up to date as work progresses Manage results of QA tests including preventive/corrective actions on non-conformities

Estimates of Time Required Recently, three people well informed about our project, did 3 independent estimates Of these, one person considered the assembly in “production-line” terms where – All resources are in place meaning: All parts immediately to hand Procedures fully tested and validated All tooling fully tested and validated Clean-room assembly staff well trained and practiced Unforeseen problems very largely ironed out of the process – This could also be called a well mastered “routine” activity. – Where we had already assembled a few cryo-modules of the same type – Where the total time required comes close to the sum of the times needed for the suite of component activities

“Routine Task” Time Required ProcedureProcedure stageTime taken in days 1Vacuum vessel assembly3 2Thermal shield and vessel assembly3.5 3Chimney assembly1.5 4Chimney on to the lifting frame1 5Top plate assembly1.5 6Upper thermal shield and He tank2 7Insertion of the chimney2.5 8Installation of the support frame4.5 9Installation of the solenoid3 10Installation of the cavities5 11Installation of the cavitiy auxiliaries7 12Cryomodule vessel closure days total Approximately 8 weeks

Real Time required? Our situation for the first cryo-module is quite different; New activity at CERN, new people, new tooling, new draft procedures, new QA activities. Equipment and tooling is now arriving on a just in time basis

What may we expect in reality? A first prototype – Debugging on 1 st CM; will be better on 2 nd – Some Re-work on components, procedures New activity, new clean-room, new tooling: – Running in phase may be long – Incomplete learning curve on 2 units (just debugging) Missing resources: slow build-up of assy team: – Specific training is needed on CM assembly New Clean-room: – Training is needed for productive clean-room work Uninterrupted work depends on “continuous flawless coordination” around the assembly (inside and outside the clean-room) Reasonable? …