Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.

Slides:



Advertisements
Similar presentations
Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
Advertisements

1 Short update Itzhak Tserruya HBD meeting BNL, April 11, 2006.
Status of the ATLAS MM project
Status Update on Mechanical Prototype in Rome November 6,
PNPI in LHCb A.Vorobyov HEPD Scientific Board meeting, December 26,2003 Status report for 2003.
PRODUCTION and CERTIFICATION of Multi Wires Proportional Chambers for the LHCb Muon System at CERN K.Mair for the LHCb Muon Group CERN* Poster anlässlich.
Construction material – All the material has been ordered with some spare (10%) Material Procurement Faraday cage – Final FEE board dimensions available.
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
G. Martellotti CERN 22/04/20021 Tooling / Test Stations for MWPC (Meeting LNF, Roma1/Pz ) Production rate : 408 chambers (Fe + LNF) :192 R4 M1.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
20/04/2012Rui De Oliveira1 20/04/2012. Rui De Oliveira2 30 cm x 30 cm example.
Ferrara 8 june 2004M.Savrié1 Production Readiness Review Ferrara MWPC Production Site.
RICH WG M.Lenti. Outlook Mirror Support Vidyo meeting on June 12, 20, 27 and on July 4 and 11 RICH WG meeting on august 27  Vessel status (see Ferdi’s.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
Status Report of activities in LNF Soldering procedure 1.Status of soldering machine 2.Measurement of wire position Chamber prototypes 1.Construction of.
M. Alfonsi LNF/INFN Cagliari 5 May 2006 M1R1 mechanical requirements  Space constraint Frame and pannel Pads readout and trigger sectors Gas inlet and.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Production Readiness Review Production steps and quality control 1.Panel production 2.HV bar gluing 3.Preparation of side material 4.Wiring and gluing.
T.Schneider/LHCb Muon EDR
The Bigbite second GEM tracker. SBS GEM Trackers Front Tracker Geometry x6 18 modules In Italy  50 cm x 40 cm Modules are assembled to form larger chambers.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
MWPC sandwich panels C.Forti INFN-LNF / LHCb-MUON EDR CERN 16 th April sandwich panels typologies of cathodes the mould the production procedure.
SD-HCAL technological prototype – Chamber and cassette production Nick Lumb Lyon, 3 February 2011.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
MM detector construction One or several modules per sector considerations.
11/05/2000Wire Chamber Working Group Visit to Fermilab Participants: –Giulio Auriemma, Thomas Schneider, Burkhard Schmidt General Remarks: –Visit was organized.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Status of MWPC production and quality control The measure of the gas leakage, is obtained by correcting the P(t) behavior by using the data of the reference.
M. Bianco On behalf of the ATLAS Collaboration
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status.
Introduction Straw Working group meeting CERN group 1 NA62 Collaboration meeting, Brussels 7-10/9/2010.
MFT WG5: ladder disk and global assembly Stéphane BOUVIER & Sébastian HERLANT MFT WG7: Mechanics and Thermal studies Jean-Michel BUHOUR & Emili SCHIBLER.
Total Cross Section, Elastic Scattering and Diffraction Dissociation at the LHC January 17, 2003TOTEM plenary meeting -Marco Bozzo1 CSC detectors for T1.
Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August (still at 50% of FR4 sheets delivered by ELTOS) – Restarted.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
22/04/20011Wire Chamber Working Group Status on O-ring closed Prototype Foam panels from Frascati (size: 279mm*341mm) No pad structure 4 independent gas.
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
DOE/NSF Review of U.S. ATLAS May 21-23, 2003 CSC Mechanics and Electronics Paul O’Connor Tom Muller BNL May 22, 2003.
Radioactive source and cosmic-ray test for the MWPC Davide Pinci on behalf of the Frascati-Roma1 MWPC group.
QA/QC in MM SM1 Mod 0 Production at INFN QA/QC MM SM1 Mod 0 - G. Maccarrone 19-Jan
Chamber Quality Control Before the construction several checks are performed on:  Panels (cathode and pad PCB)  GEM foil Tests on assembled detector.
CMS Upgrade Workshop, FNAL, Nov 19-21, O.Prokofiev CMS Upgrade Workshop Updated ME4/2 chamber construction costs and prototype Status and plans.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
To measure 0, mechanical oscillations of the wire to be tested are induced by applying a periodic high voltage (about 900 V) with a frequency of 300 ÷
M23 Inner Regions Upgrade with Triple-GEM detectors The EVLGG (Davide, Gianni & Ale) INFN Cagliari LNF Frascati INFN Roma.
Status of production at LNF E.Dane’ and C. Forti – Meeting with LHCb referees Firenze 14-mar-05 Christmas 3 ch/week Ch. 43.
G. PassalevaFirenze - September 8, 2004 Production Readiness Review Firenze MWPC Production Site G. Passaleva.
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
Results on a Large Area triple-GEM Detector at LNF 5 th RD51 Collaboration Meeting Freiburg, 25 May 2010 D. Domenici - LNF.
Production and installation plan Construction sharing Production plan Installation sequence Material procurement P. Campana LNF – LHCb Muon EDR Cern April.
T2 GEM Production in Helsinki Kari Kurvinen TOTEM T2 EDR meeting Radiation Detector Laboratory of Helsinki Institute of Physics (HIP) and Department.
1 Chamber Interfaces Adalberto Readout-, I2C-, HV-, LV-, Gas- and chamber support interface. Space issues.
Activity report from LNF Panels Soldering tests Production site and tooling status WPC miscellanea (+7 cm layout, cathode costs, aging tests)
TOTEM CSC construction and Quality Control Status report A.Krivshich Petersburg Nuclear Physics Institute March 07, 2006 CERN.
Status of straw production straw module assembling
T1 status (a selection from EDR presentations)
Gluing jigs for Demonstrator
Overview of the Frascati Production Facilities
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
Presentation transcript:

Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003

Construction tools Several steps in the chamber construction have been automated to speed up production, reduce the needed manpower and increase precision and reliability of the MPWC. Tools are used to glue the frames to the panel wire the panels solder the wires control the wire pitch control the wire tension assembly the layers close the chambers Each production site will have a set of tools.

Among the various sites, tooling has small differences (mainly due to characteristics of the different regions) : anode readout (R4) cathode readout (R3 and inner M4-M5) anode-cathode high density readout (inner M2-M3) These “theme variations” do not change the main conceptual design of the chambers that remains uniform in the whole detector These differences in the tools explain the small variations in the procedures for chamber assembly in the various sites Some of these procedures have still to be validated with the experience we will accumulate in the first months of the production

Glueing the frames to the panel Technique : perform a precise glueing of the frames (HV bars, lateral and side bars) onto the panels at the quote of 2.5 mm (to set the anode plane at the right level) with micron precision PANEL GLUEING TOOL HV BAR GLUE 2.5 mm 2 panels can be glued per day on one glueing frame This procedure is the same in all sites

Status : 1 table ready for PNPI1 (4 needed), 1 table ready for CERN (1 needed) 1 table under construction in Potenza/Ferrara and 1 (simplified version) in Florence (6 needed in the INFN sites) CERN/PNPI Glueing table with vacuum system for the frame and the panel positioning The material is glued with structural epoxy and left under vacuum for several hours Very good precision achieved

Wiring methods COMBS CERN (2 pairs) PNPI (6 pairs needed !) INFN (3 pairs) 1 panel = 2 anode planes 1 panel = 1 anode plane WIRE

The different wiring methods do not affect the layout of the chambers The time needed for the cure of the glue is a limiting aspect of chambers production (for PNPI site in particular, a large number of combs is needed) Winding is performed at a speed of turns/min The largest chamber is wired in about 2 h (positioning included) Status : CERN, PNPI and Ferrara, ready LNF under setup (control of the uniformity of the wire tension)

Wiring Machines

Automated soldering (laser)

Status : LNF (2 laser heads + cameras for wire pitch control) ready; mechanical settings to be adapted to the final chamber dimensions Ferrara (2 laser heads + cameras for wire pitch control, integrated in the wiring machine) under setup CERN, PNPI (iron head) device under procurement and setup Ferrara

Laser 25 W 805 nm working at 60% nominal power Soldering pads adapted for a continous soldering and for eye-guiding wire positioning Tin-plates traces shows better results (true also for iron soldering) at lower power Low flux, low T, soldering wire (same of CSC-CMS) Solder velocity : 5 cm/min (largest chamber done in 30 min with two- heads setup) Two small cameras control the process Afterwards, visual, detailed control of the soldering quality

Production sites (clean rooms) CERN, PNPI, LNF ready; Ferrara, Florence under setup

Travelers : material preparation & construction procedures 1)Preparation, cleaning and controls of panels and of side material (HV, side and closing bars; wire, etc...) >> check of wire quality : visual inspection + stress test? >> dimensional controls 2)Glueing of bars on panels >> dimensional controls 3)Wiring, glueing of wires 4)Wire soldering

5) QC on wire pitch and tension 6) Cutting wires’ end, cleaning of anode panels (for R4, mounting of R and C on anode bars) 7) HV test of single anode panels

8)Preliminary assembly of WPC, test with HV and dry gas >> the 4 anode layers are assembled without glue for dimensional control and undergo preliminary tests with HV in dry gas environment 9)Final glueing/closing >> two lines pursued: in the high density region (all the boundary is filled with HV connections and FEE pins), the baseline is the use of O-ring the rest would be closed permanently with glue ( this decision has to be validated also with the yield in the chamber construction)

10)Gas leak test >> in case of closing with glue, a supplemental peripheral glueing has to be applied 11)HV training with final gas mixture 12)Chamber uniformity control 13)Final assembly of Faraday cage and FEE - Cosmic Ray test >> this step is largely linked to the availability of the final electronics (only in July 2004). One part of the production will be equipped only afterwards. Tests on full preproduction and after on a small sample of chambers will be done with ASDQ

Manpower needed Evaluation from “Travellers” SiteChambers/ week Manpower (fte) Notes Ferrara2.55Panels glued in Potenza, chamber assembled and tested in Rome2 PNPI 1514 CERN12 LNF person from Rome1 for chamber assembly

Conclusions (open points) Final choice of glue Validation and commissioning of tooling Validation of closing methods HV training procedures