HUNTING CAMP FACILITY BY: Ryan Fremin ET 494 Senior Design II Construction Engineering Technology Professor: Dr. Koutsougeras Advisor : Mr. Rode
PURPOSE Perform complete theoretical construction process of hunting camp facility Research Needed Location Selection Giving Structure Options Rough Drawing and Estimates Design Selection Complete drawings, schedule, and estimate
WHY HUNTING In 2011 there was a total of 13.7 million hunters in the United States 23 % of all wild-life recreation is found in hunting (US Census Bureau) $564,385,000 Was spent in 2011 for trip–related hunting in Louisiana $315,763,000 Was spent in 2011 for trip-related hunting in Mississippi Louisiana-16 % Mississippi- 36 %
RESEARCH The given statistics show that this can be a lucrative business. Current pricing for pay hunts Lodging $1000-$2000 Hunting-----Min------$ 4,000 (8-Point) Mississippi is in the top 15 places that hunters like to hunt Shows profitability and demand
DESIGN OPTIONS LOG CABIN Will give the owner and customers a more luxurious feel with all of the necessities. Less cost effective PRE-ENGINEERED METAL BUILDING Will give the owner and customers all of the necessities with the option of adding luxuries after design and pricing is completed. Cost Effective (Key for this build)
LOG CABIN Example ( Gile’s Island) Nice facility to conduct business Most need separate buildings for lodging (Total sq.ft.) Lodging takes up possible land and reduces amount of huntable property Popular but expensive to construct
PRE-ENGINEERED METAL BUILDING Example ( Converted Metal Building) Cost effective Fast Construction Combines facilities into one location Gives added space for possible upgrades 40’x80’( total – 7200 sq.ft.)
ROUGH DRAWING – LOG CABIN
ROUGH DRAWING – METAL BUILDING
DESIGN DECISION Pre-Engineered Metal Building $456,264 Log Cabin $507,400 Difference $ 51,136 or 10% cheaper
DETAILED DRAWINGS The detailed drawings will be done from the last week of the semester into the break. They will be continued while doing a material takeoff at the same time. This will allow sufficient time to complete drawings and estimate.
TIMELINE Jan 21-Jan 24First Week Back to Classes Jan 27-Jan 31Update Powerpoint for Semester Feb 3 –Feb 7Continue Drawings/Material Takedown Feb 10 – Feb 14Continue Drawings/ Material Takedown Feb 17 –Feb 21 Continue Drawing/ Material Takedown Feb 24– Feb 28Finish drawings Mar 3–Mar 7Complete Survey of Location Mar 10–Mar 14Determine Foundation Plan Mar 17– Mar 21Begin Estimate Mar 24- Mar28Cont. Estimate
TIMELINE (CONT.) Mar 31– April 4Produce Final Estimate April 7- April 11Begin Planning and Scheduling April 14 – April 18Cont. Planning and Scheduling April 21– April 25Complete Planning and Scheduling April 28– May 2Begin Finalizing Project May 5– May 9Complete Final Project