G. Carboni – Muon Meeting – 22-23 April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to 1.04.2007.

Slides:



Advertisements
Similar presentations
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
Advertisements

Line Efficiency     Percentage Month Today’s Date
Status of the LHCb RPC detector Changes with respect to Note cm strips instead of 3 cm (cost optimization) All gaps same size (standardization)
G. Carboni - Open LHCC - July 2001 Technical Design Report for the LHCb Muon System Giovanni Carboni on behalf of the Muon Group Part II: RPC Detectors,
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
Studies of radiation hardness of ECAL modules 1Yu. Guz 2013/05/28.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
Hans-Åke GustafssonLHCC review January 31, ALICE meets LHCC referees 31/01/ :00  Milestones report H-A Gustafsson  FMD questions H. Boggild.
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.
WP1.2 – Photon Detectors Stephan Eisenhardt University of Edinburgh  Budget  Milestones  Progress Report  Partners: International Collaborating Groups.
NSW SG 19 Nov Nov 2014 S. Zimmermann, NSW SG 1.
Debugging of M2-M5 G. Passaleva. 11/02/2009 Muon System mini review G. Passaleva 2 outline Short summary of Muon readout channel organization Connectivity.
LHCb CO 2 cooling meeting Burkhard Schmidt – February 18,
DT1 Gas Section Debrief of 2005 activities.. The Purpose of the Debrief  Compare plan and achievements.  Analyze how the work is done ? Do we meet the.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Muon Electronics Upgrade Present architecture Remarks Present scenario Alternative scenario 1 The Muon Group.
Status and planning of the CMX Wojtek Fedorko for the MSU group TDAQ Week, CERN April , 2012.
Flavio Gatti,Frascati-PSI, Jan 31 th, 06 1 TC status. Flavio Gatti UNIVERSITY and INFN of Genoa, Italy.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
G. Pugliese RPC requests for GIF++ G.Pugliese, N. Zaganidis and I. Pedraza on behalf of the RPC group 1.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
1 October 2003Paul Dauncey1 Mechanics components will be complete by end of year To assemble ECAL, they need the VFE boards VFE boards require VFE chips.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
G. Carboni - Muon Meeting – Draft Agenda Muon Meeting 6 April 2004 Introduction (15 min) Total 15 min MWPC prodution Material supplies,
STATUS REPORT WP7 Facilities and Component Analysis for Detector R&D Activities and Status Resources and Expenditures Work plan Mar CAPEANS 3/11/08 M.C.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Upgrade projects and APT update DT-LHCb coordination meeting 28 September 2015.
Radioactive source and cosmic-ray test for the MWPC Davide Pinci on behalf of the Frascati-Roma1 MWPC group.
Status Report on the Muon System Alessandro Cardini / INFN Cagliari (with the help of the whole Muon Group)
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Could we abandon the HW LLT option and save money (and allow possible further improvements to the upgraded muon system)? Alessandro Cardini of behalf of.
15/6/2006Gaia Lanfranchi - LNF-INFN1 Why do we have to measure efficiencies in the Muon Detector? Muon Software Meeting, June 15th G. Lanfranchi LNF-INFN.
A. Lai – 18/10/2006 – L0 workshop: Muon BX Time Alignment 1 The BX Alignment in The Muon System Summary System peculiarities concerning timing issues System.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Summary of FEE-Integration Meeting LNF, Summary of the Frascati meeting on chamber & front-end integration on 10 September 2003, provided.
Joerg Dubert’s Questions as you all aware we currently do not yet know how the final mechanical design of the new Small Wheel will look like. Nevertheless,
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
27 December 2006 LHCb Status Report (A.Vorobyov) 1 LHCb.
Final results from an extensive aging test on bakelite Resistive Plate Chambers Stefano de Capua University of Rome II “Tor Vergata” and INFN.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
News from PNPI Presented by N. Bondar for B. Bochin Cagliari 8/10/2015.
Page 1 Enterprise Data Warehouse Project Executive: Barbara Chmielewski Project Manager: Anita Sharma.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
NSW SG 10 Dec Nov 2014 S. Zimmermann, NSW SG 1.
WP2 (Detector development) Summary Gabriella Pugliese INFN – Politecnico of Bari.
ALICE Muon Tracking Upgrade
Test Beam Request for the Semi-Digital Hadronic Calorimeter
An extensive aging study of bakelite RPC
T1 status (a selection from EDR presentations)
Preparation for CERN test beam
LHCC referees’ questions, comments, requests
G. Carboni for the Muon Group
Current Status Future Progress Monitoring
Francesco Forti University and INFN, Pisa
Pierluigi Paolucci - I.N.F.N. Naples
RPC HV&LV status Introduction HV power supply tender
LHCb Muon Detector MWPC & GEM
Pre-installation Tests of the LHCb Muon Chambers
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec ITEM 1 ITEM 2 ITEM 3
University of Rome II “Tor Vergata”
Globus-M2 will be constructed by the end of 2015
Presentation transcript:

G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to (was Feb. 2006) At the moment no further details on “physics run” (was August 2006) Access to hall until that date  but when pipe under vacuum detector cannot be opened (safety) No SPS in 2005 (only PS test beam) In this meeting we have to review and readjust our milestones (in particular the “official” ones) some of them have already been missed some others risk to be missed, however: perhaps we have been too optimistic with the one-year LHC delay they don’t make much sense today In readjusting we should be as accurate and conservative as possible, avoiding too frequent corrections The updated milestones will be presented to the referees at the next LHCC

G. Carboni – Muon Meeting – April Dec Engineering design completed CARIOCA+DIALOG chip design and test completed Muon Detector Major Milestones 2002 Jul-Oct Full chain electronics test 2002 Jul-Oct Full chain electronics test MWPC Detectors RPC DetectorsElectronics 2003 Oct 2003 Jan Start chamber construction 2004 Dec Chamber construction completed Electronics assembled and tested 2003 May Start chamber construction 2002 Jun SYNC chip design and test completed Start FE-board production 2003 Oct Muon filter inst Oct Muon filter inst Jun Support structure inst Jun Support structure inst Jul Start installation at CERN 2005 Aug Commissioning completed Start IMB, SB and ODE production Mar As presented with the TDR July Jul Moved to July Moved to Nov.

G. Carboni – Muon Meeting – April 2002 Present (official) milestones

G. Carboni – Muon Meeting – April 2002 Planning for 2002 as presented by Pierluigi in Dec MWPC construction EDR

G. Carboni – Muon Meeting – April 2002 Muon Electronics Project Schedule for 2002 (DONE) 25/1 Definition of IB detailed scheme (DONE) 20/2Choice on Low Voltage regulators 31/3definition of ODE board detailed scheme and components procurement 15/4DIALOG-  submission 30/4F/E Low Voltage board prototype 30/6DIALOG-  test completed 1/7IB prototype (2 boards + back-plane) 31/7ODE-  board prototype: 96 or 192 inputs TTCRx TLK/GOL transmitter (according to availability) SYNC prototype (OTIS - Chip-  - FPGA) SB-  prototype:ELMB for I 2 C control (at least 4 channels) TTCRx + F/E pulsing system DIALOG F/E complete board (  version) CARIOCA F/E complete board (  version) 1/9Start of prototypes standalone tests and debugging 30/10DC-  version 1/11Start of full chain tests. The full chain contains: 1 MWPC n F/E boards (CARIOCA, DIALOG, LV) 1 SB prototype 2 IB + back-plane 1 ODE 1 DC (added subsequently) December LHCb week Presentation of results (!)

G. Carboni – Muon Meeting – April 2002 PNPI14 planned for MarchLNF Final design FE/LNF Design in progress Status of V0.0 prototypes: testing from May (RPC), July (MWPC) CERN

G. Carboni – Muon Meeting – April 2002 One-year shift of the various completion dates is unavoidable: Dec > Dec It was suggested at last TB (HJ) to delay the start of installation not more than 6 months goal: terminate installation by end July 2006, then start commissioning plan installation in a way to minimize cost of hired manpower (cranes, cabling...) Fine-tuning according to parts of the detector (stations, regions) construction sites (institutes) “interference” during installation Should we have a fine-structure of milestones? different milestone on sub-detectors/regions? When? What do we mean (e.g.) by “10% production?”: need to clarify terms Finally, milestones should be reflected in financial planning Proposed framework for the milestones discussion We can access the detector until and (with restrictions) until

G. Carboni – Muon Meeting – April 2002 New proposed milestones

G. Carboni – Muon Meeting – April 2002 The TDR requests for rate and cluster size must of course be met We should anyhow feel free to review them critically:  Plateau  Efficiency – redundancy - number of gaps Additional parameters should be considered also. For example: 1.GIF test 2.Efficiency/plateau uniformity over the sensitive area How to proceed towards the choice for the inner part

G. Carboni – Muon Meeting – April 2002 Why GIF testing? Rates at GIF are most likely too small for rate tests of chambers for the inner regions of M1, however very meaningful aging studies can still be performed at GIF:  For M1R1 the dose expected in LHCb is 90 kRad/y or 900 Gy/year (See Note by V. Talanov).  Placing a detector at 50 cm from the source, the dose (ABS=1) is: Dose(Gy) = 11 T(days)  80 days provide 1-year LHCb equivalent  meaningful test  Complements the high-rate tests (PSI)

G. Carboni – Muon Meeting – April 2002 The proponents of the various solutions should address these items soon, with notes describing the subsystem as a whole and indicating the appropriate milestones of the project. The proposed approach Final aspects (last but not least) Simplicity of construction Standardization Cost