Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.

Slides:



Advertisements
Similar presentations
DS Quench TEST 2  MOTIVATION and METHOD: 1. Achieve 500kW on beam 1 – TCP7 collimators.(so far 500kW with beam 2 and 235kW over 1s with beam 1 were reached.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
02/09/2010 Access conditions for test of the RB.A23 at 17:30. Splice mapping. Complete machine closed by ~18:00.Problems in getting TI2 ready for injection.
Saturday 6:13 – 15:00 STABLE BEAMS  scans etc. 15:00 moved to ADJUST Squeeze to 2 m in two steps 11 – 5 – 2  remarkably smooth  tertiary collimators.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Beam expected in the afternoon PM: – Establish first-turn – Establish closed orbit – Rough correction of machine parameters Evening: – RF capture Night:
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Preparation Status of pp Run11 Haixin Huang Time Meeting 12/21/
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Friday Access in shadow of SPS interventions (RF, extraction septa power supply) Lead into problem on the cooling of the extraction septa in SPS Both beams.
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Thursday morning – optics correction
Tuesday TOTEM and transverse loss map (1) OK
Alice solenoid – orbit distortion
LHC commissioning Week 38
Friday March 4th 08h32: Access for beam dump system.
Week 35 – Technical Stop and Restart
Monday February 28th 8h00: Injection
Planning at 5 o’clock meeting Friday
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Friday 23rd March 08:00 Access
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday :20 beta beat corrections during squeeze for flat machine finished Afterwards fixing issues at injection: BPM rephrasing for B2 solved.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary for LPC (March 7th, Ralph Assmann)
Summary Tuesday h23: Machine closed. Precycle started.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Friday 15th February - morning
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam back. Orbit corrections, injection check, tune adjustments. 15:00: PIC on 60A power converters. 16:00: Beam back. Chromaticity adjustments. Beta beat. Orbit feedback tests. LSA bugs. 21:00: Start of ramp with beam to 1.18 TeV. Arrive very nicely at top at 21:11. Availability (to 21:00): 11h00. Unplanned maintenance: 1h00. Planned maintenance: 9h00

Saturday TOTEM test finished very successfully!  All case studies were tested and the interlock logic is OK for all of them.  Results of tests documented online with snapshots. All cases associated to beam dumps are also documented by global PM events Philippe who finished the RF adjustments in SR4:  The Front-End of the phase loop has been adjusted to prepare for bunch intensity increase.  Both rings can now take at least 5E10 single bunch. Exactly what intensity limit will be clarified on Monday...Hopefully up to nominal.  With these settings we can still deal with single-bunch pilot 5E9 OK. However how far below 5E9 will be clarified on Monday. LHC status

Summary of aperture measurements. We could complete the phase space coverage for both H and V planes of beam 1. Work was done in parallel with RF tuning in preparation for higher intensities ("cross talk" not always transparent...).  Measurements were done with orbit bumps at different phases. Loss location are listed in detail in the logbook for the different cases.  Reference machine: golden orbit used for collimator setup, separation bumps on in all IPs.  No indication of major problems with the aperture. Measurements with golden orbit and with corrected beta-beat indicate a better aperture than last year. Detailed look at the data is needed to take into account the measured beta values. Main aperture bottlenecks: Q4 quadrupoles in IP6, Q6- L2 and Q6-R2. Complete list in logbook LHC status

ramp LHC status

Schedule LHC status e10