Evaluating Hydro Capacity for Capacity Adequacy Standard: Selection of Hydro Events Eric King/ Mary Johannis PNW Resource Adequacy Technical Committee.

Slides:



Advertisements
Similar presentations
Out of Region Market Assumptions Resource Adequacy Technical Committee April 6 th, 2011.
Advertisements

Power Supply Adequacy Assessment Model/Methodology Review Steering Subcommittee Meeting January 29, 2010.
Preliminary Review of July 24 th Extreme Temperature Event & Implications for Pilot Capacity Standard Mary Johannis & Wally Gibson PNW Resource Adequacy.
Genesys Model Enhancements October 4, 2011 NW Resource Adequacy Steering Committee Meeting Gwendolyn S Shearer.
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014.
Study Results Drought Scenario Study This slide deck contains results from the 2011 TEPPC Study Program. This study shows the impact in the interconection.
Variable Generation Subcommittee Paul Arnold and Michelle Mizumori Northwest Wind Integration Forum Technical Work Group October 29, 2009.
NW Resource Adequacy Forum Steering Committee Conference Call November 4, 2010.
Study Goal:  Perform a “bottom-up” assessment of the sustained peaking capacity of the Pacific Northwest Hydro System over the highest 18 hours in a 3.
1 Planning Reserve Margin Dan Egolf Senior Manager, Power Supply & Planning.
A Resource Adequacy Standard for the Pacific Northwest Resource Adequacy Technical Committee January 17, 2008 Portland Airport.
Resource Adequacy Technical Committee Meeting April 6, 2011.
Developing an Adequacy Metric Resource Adequacy Forum Technical Subcommittee Meeting October 16, 2009.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 2009 Draft Resource Program Released: September 30, 2009 Accepting Comments until: November 30,
California Energy Commission Staff Paper - April 12,20071 Estimating the Generation Resource Mix of Electricity Imports to California – Energy Commission.
Power System Research, Inc. Review of the PNW Adequacy Standard Resource Adequacy Forum Technical Committee Meeting October 1, 2010.
Adequacy Assessment for the 2017 Pacific Northwest Power Supply Steering Committee Meeting October 26, 2012 Portland, Oregon 1.
Revising the Pacific Northwest Resource Adequacy Standard Resource Adequacy Technical Committee June 23, 2011.
Illustrative FCRPS Examples Comparing Capacity Adequacy Calculations for Federal Hydro- Dominated System Mary Johannis PNW Resource Adequacy Technical.
Comparison of LOLP Practices Mary Johannis PNW Resource Adequacy Technical Committee Mtg January 23, 2009.
Powered by the Loads and Resource Information System (LaRIS) Pacific Northwest Loads and Resources Operational Peaking Adjustment Council Briefing.
Proposed Contract to Perform Regional Sustained Hydro Peaking Capability Study Mary Johannis PNW Resource Adequacy Steering Committee January 29, 2008.
May 31, Resource Adequacy Capacity Standard Resource Adequacy Forum Technical Committee May 31, 2006 Background Image: Bennett, Christian Science.
June 27, Pacific Northwest Resource Adequacy Assessment for 2010 and 2012 Resource Adequacy Forum Steering Committee Meeting Northwest Power Pool.
Resource Adequacy Technical Committee Meeting April 6, 2011.
Evaluating Hydro Capacity for Capacity Adequacy Standard: Selection of Hydro Events Mary Johannis PNW Resource Adequacy Technical Committee Mtg November.
Martin Rule Curve Study Ashley McVicar, APC Maurice James, Water Resources Consulting LLC.
Resource Adequacy Steering Committee Meeting October 4, 2011.
January 29, 2010Resource Adequacy Steering Committee 1 Sustained Peaking Capacity Analysis Initiated by the Adequacy Forum Input Information from Utilities.
Historical Year for 2026 Common Case Load/Hydro/Wind/Solar Shapes TAS November 2015 Meeting Tom Miller- TAS Vice Chair W ESTERN E LECTRICITY C OORDINATING.
Relationship of Regional Resource Adequacy Standards to Utility Planning PNW Resource Adequacy Steering Committee Meeting June 27, 2007.
Simulation of Wind Generation in Resource Adequacy Assessments Mary Johannis, Bonneville Power Administration.
Interim and Long-term Approaches for Assessing Wind’s Contribution to Capacity Adequacy PNW Resource Adequacy Steering Committee Meeting July 21, 2008.
Providing Resource Planning Guidance to Individual Utilities PNW Resource Adequacy Technical Committee Meeting June 20, 2007.
2009 Pacific Northwest Resource Adequacy Assessment Resource Adequacy Technical Committee October 16, 2009.
Wind Power Capacity Assessment Mary Johannis, BPA, representing Northwest Resource Adequacy Forum Northwest Wind Integration Forum Technical Working Group.
1 PNW Regional Contingency Resources Resource Adequacy Technical Committee April 6 th, 2011.
2010 Work Plan Steering Committee January 29, 2010.
Moving toward a Final Resource Adequacy Standard Resource Adequacy Forum Steering Committee Meeting September 27, 2007.
Evaluation of Columbia River Sustained Hydro Peaking Capacity Eric King / Mary Johannis PNW Resource Adequacy Technical Committee Meeting May 31, 2006.
Providing Resource Planning Guidance to Individual Utilities PNW Resource Adequacy Steering Committee Meeting April 13, 2007.
Work Plan Resource Adequacy Forum Technical Committee July 29, 2009.
Capacity Metric & Hydro Capacity Assessment Decisions Mary Johannis PNW Resource Adequacy Technical Committee Meeting June 20, 2007.
Climate Change and Seattle City Light Operations Wing Cheng and Ron Tressler Seattle City Light September 16, 2009.
Utility Responsibility to Maintaining Load Reliability Resource Adequacy Forum Technical Committee Meeting June 20, 2007.
Resource Adequacy Assessment for 2015 Resource Adequacy Forum Technical Committee Meeting October 1, 2010.
Out of Region Market Assumption Resource Adequacy Technical Committee December 1, 2011.
Sustained Hydro Peaking Capacity Contract with Don Long Finalizing Phase II SOW Mary Johannis PNW Resource Adequacy Technical Committee Mtg January 23,
Using the Trapezoidal Model to Derate NW Hydro Capacity Resource Adequacy Technical Committee July 25, 2007 Portland, Oregon.
Thomas Carr Western Interstate Energy Board ColumbiaGrid Planning Meeting August 1, 2013 Grid Tracker: A web-based tool to analyze historic transmission.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Path Definition (for studies) 
Defining LOLP Resource Adequacy Forum Technical Subcommittee Meeting November 14, 2008.
Steering Committee Meeting March 9, Why talk about assumptions? Garbage in, garbage out! “Let’s go dumpster diving!” Results sensitive to key.
2010 Northwest Regional Forecast Resource Adequacy Technical Committee April 22, 2010.
Sixth Northwest Conservation & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Generating Resource Advisory Committee Meeting.
Power Supply Adequacy for the 2021 Operating Year Resource Adequacy Advisory Committee Steering Committee Webinar June 8, 2016.
Recommended Hydro Improvement April 11, 2017
Demand Response in the 7th Power Plan
Vetting the GENESYS Model
Resource Adequacy Assessment for 2015 Interim Results Resource Adequacy Forum Technical Committee Meeting July 28, 2010.
Pacific Northwest Resource Adequacy Assessment
Recommended Hydro Improvement April 11, 2017
Study Results Drought Scenario Study
Technical Committee Meeting March 18, 2016
Planning Reserve Margin
Steering Committee Webinar March 25, 2016
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014
Resource Adequacy Steering Committee Meeting October 4, 2011
Resource Adequacy Technical Committee Meeting April 22, 2010
Simulated vs. Real Hourly Dispatch Resource Adequacy Forum Technical Committee Meeting October 1, 2010.
Presentation transcript:

Evaluating Hydro Capacity for Capacity Adequacy Standard: Selection of Hydro Events Eric King/ Mary Johannis PNW Resource Adequacy Technical Committee Mtg November 1, 2007

PNW Resource Adequacy Technical Committee Meeting2

November 1, 2007PNW Resource Adequacy Technical Committee Meeting3 Historical vs. Calculated Calculated Sustained FCRPS Cap Purchases Cap to meet Expected Load Surplus + Cap to meet PRM

November 1, 2007PNW Resource Adequacy Technical Committee Meeting4 1 in 20 Probability Winter & Summer Events Suggested Approach: –Select combination 1 in 20 year probability event, which includes both adverse hydro capacity and adverse temperature-induced load conditions For purposes of reporting Hydro Capacity to WECC and for Resource Adequacy Forum purposes, best to define common winter and summer adverse event for which to evaluate hydro capacity –Utilities could then define temperature-induced adverse load conditions for their own resource planning efforts which approximate 1 in 20 probability

November 1, 2007PNW Resource Adequacy Technical Committee Meeting5 Representative NW Hydro Projects ROSS Round Butte Columbia River Hydro

November 1, 2007PNW Resource Adequacy Technical Committee Meeting6 Suggested Representative Projects FCRPS –FCRPS & Probably all Columbia River Hydro not very sensitive to Selection of Adverse Event Non-Columbia River Projects –PGE’s Round Butte Project on Deschutes River is representative of Williamettes –Seattle’s ROSS on Skagit River is a representative West-side project

November 1, 2007PNW Resource Adequacy Technical Committee Meeting7 Selection of Winter Event

November 1, 2007PNW Resource Adequacy Technical Committee Meeting8 Selecting Adverse Hydro Condition for Winter Event Approach –Look at candidate events, which constitute similar adverse probabilities (except Columbia River) –Investigate events with February flows close to 1 standard deviation (α) lower than mean, except for Columbia River –Pick event closest to 1 α for river systems other than Columbia River Candidate Events – : too adverse (≤ 1 α) for Round Butte – : not sufficiently adverse for Round Butte & ROSS – : too adverse for ROSS – : not sufficiently adverse for Round Butte & ROSS – : ≈ adverse for Round Butte & ROSS= Selected Event

November 1, 2007PNW Resource Adequacy Technical Committee Meeting9

November 1, 2007PNW Resource Adequacy Technical Committee Meeting10

November 1, 2007PNW Resource Adequacy Technical Committee Meeting11

November 1, 2007PNW Resource Adequacy Technical Committee Meeting12

November 1, 2007PNW Resource Adequacy Technical Committee Meeting13

November 1, 2007PNW Resource Adequacy Technical Committee Meeting14 Suggested Winter Hydro Event Use historical modified February 1969 flows for Columbia River, West-side and Williamette hydro projects Evaluate 18 hour Sustained Peaking Capacity for individual hydro PNW hydro projects using Methodology on Slide 2 Compare ∑ individual hydro capacities to 18 Trapezoidal Approximation of Regional Hydro Capacity under February 1969 water condition Decide whether to select February 1969 Event as Winter Event for which to Evaluate PNW Hydro

November 1, 2007PNW Resource Adequacy Technical Committee Meeting15 Selection of Summer Event

November 1, 2007PNW Resource Adequacy Technical Committee Meeting16 Next steps Decide whether to use same approach to select summer event as winter event Form subcommittee to perform hydro evaluations of individual PNW hydro projects for winter event (either Feb 1969 or other events from this meeting) Have subcommittee explore possible summer events