OP-Navigation.ppt1 U.S Army Corps of Engineers Savannah District
OP-Navigation.ppt2 SC GA ATLANTIC OCEAN Savannah R. St. Mary’s R. Savannah Harbor Savannah Harbor Brunswick Harbor AIWW Civil Works & Navigation Boundaries Boundaries
OP-Navigation.ppt3 u Sav’h Harbor 32.5 Miles u AIWW 161 Miles u Brunswick 24 Miles Total Miles Total Miles Navigation Projects
OP-Navigation.ppt4 Scheduled FY07 Dredging Work in Savannah District South Atlantic Division Savannah & Brunswick Inner Harbor FY07 Savannah & Brunswick Entrance Chl Brunswick Deepening Sta 20 to 46, E. River to 36 ft. OCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEP Sea Turtles-screens & observers Striped bass spawning Hopper Dredge Maintenance Dredging Hydraulic Pipeline Dredge Maintenance Dredging Est. 5,180K CY Hydraulic Pipeline Dredge New Work Dredging BO10/15 Est. 2,000K CY Est. 5,063K CY BO9 BO15
OP-Navigation.ppt5 Savannah District FY 07 Hopper Dredge Program
OP-Navigation.ppt6 Scheduled FY07 Dredging Work in Savannah District South Atlantic Division FY07 Savannah & Brunswick Entrance Chl OCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEP Sea Turtles-screens & observers Hopper Dredge Maintenance Dredging BO10/15 Est. 2,000K CY BO9
OP-Navigation.ppt7 Savannah District u Project: Savannah Entrance Channel u Type of work: Maintenance u Depth: 42/44 ft u Width: 600 ft u Length: 11.4 miles u Quantity: 1.0 MCY u Type of Material: sand/silt/clay u Placement Areas: EPA approved ocean site and near shore sites u Distance to Placement Area: up to 11.5 miles u Type of Equipment: Hopper u Small Business Set Aside: No u Last Dredged: FY06 u Environmental Window: Dec 15- March 31 u Reason for Window: Right Whales and Sea Turtles
OP-Navigation.ppt8 Savannah District u Project: Brunswick Entrance Channel u Type Work: Maintenance u Depth: 32/36/38 feet u Width: 500 feet u Length: 16.8 miles u Quantity: 1.0 MCY u Type of Material: Sand/silt/clay u Placement Areas: EPA approved ocean site and near shore sites u Distance to Placement Area: up to 19 miles u Type of Equipment: Hopper u Small Business Set Aside: No u Last Dredged: FY06 u Environmental Window: 15 Dec-13 March u Reason for Window: Right Whales and Sea Turtles
OP-Navigation.ppt9 Savannah District FY07 Hydraulic Cutter Head Dredge Program
OP-Navigation.ppt10 Scheduled FY07 Dredging Work in Savannah District South Atlantic Division Savannah & Brunswick Inner Harbor Brunswick Deepening Sta 20 to 46, E. River to 36 ft. OCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEP Striped bass spawning Hydraulic Pipeline Dredge Maintenance Dredging Est. 5,180K CY Hydraulic Pipeline Dredge New Work Dredging Est. 5,063K CY BO15
OP-Navigation.ppt11 Savannah District u Project: Savannah & Brunswick Inner Harbors u Type of work: Maintenance u Depth: (SH)40/46 ft, (BH)30/36 ft u Width: (SH)500 ft, (BH)350/400 ft u Length: (SH)21.3 miles, (BH)3 miles u Quantity: 5.2 mcy u Type of Material: sand/silt/mud u Placement Area: Upland placement sites u Distance to Placement Area: up to 2 miles u Type of Equipment: Hydraulic cutterhead pipeline u Small Business Set Aside: Yes u Last Dredged: FY06 u Environmental Window: (SH) March 15-May 30 (above Station ) (BH)April 1-August 1 u Reason for Window: (SH)Striped Bass Spawning (BH) Least tern nesting
OP-Navigation.ppt12 Savannah District u Project: Brunswick Deepening Inner Harbor u Type Work: Unclassified u Depth: 36 feet u Width: 400 feet u Length: 12.3 miles u Quantity: 8.0 MCY u Type of Material: Sand/silt/clay u Placement Areas: New Bird Island & Andrews Island u Distance to Placement Area: up to 5 miles u Type of Equipment: Hydraulic cutterhead pipeline u Small Business Set Aside: No u Last Dredged: N/A u Environmental Window: None u Reason for Window: N/A