LHC 1 st August 2015 08:34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Tuesday 10 th April - morning Access for:  point 3 Jerome Landaro TCSG one jaw didn't move  point 5 Qps expert on RPMBB.UJ56.RCBXH1.R5  point 6 TCDQ.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
LHC Scrubbing Runs Overview H. Bartosik, G. Iadarola, K. Li, L. Mether, A. Romano, G. Rumolo, M. Schenk, G. Arduini ABP information meeting 03/09/2015.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
LHC Scrubbing Run 1 Day 3 (27/06/2015) Scrubbing team 28/06/2015.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
Another typical LHC day. 06:15 Fill 2000 dumped 08:44 Stable beams – fill 2001  1.675e14  1.21e11  ~2 microns normalized emittance 11:34 Beams dump.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
Machine Coordinators: G. Arduini, J. Wenninger
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Summary of Week 11: 14 – 21 March
LHC Status Su Morning 17-April R. Assmann, B. Holzer et al
Yesterday Issue of injection kicker not pulsing:
Scrubbing progress - 09/12/2012
Scrubbing progress - 10/12/2012
Saturday 2/4/ :00-09:00 Problems with SPS:
Thursday 10th January 9:30 Network routers restart, all went fine, but only just. 12:00 All power converters from the arcs on at standby 12:00 ELQA test.
Friday 14th December - morning
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Finally.... We had to wait a long time.... We had many problems....
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Wednesday 03/11 – The Plan Finish electron-cloud program:
Wednesday 10/5 Cryo recovery until 18:30
Sunday/Monday & :30 Stable beams. Fill #1851.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Monday 24 October hours of 25ns MD
LHC Morning Meeting - G. Arduini
Scrubbing progress - 08/12/2012
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Saturday 24 September 2011.
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Monday 10th December - morning
Monday 27th August & night
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Saturday 26 November 2011.
Tuesday
Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33
Presentation transcript:

LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in Matching Section R8 (DFB) 11:30 Injecting and test on TDI vacuum behaviour 13:30 Re-injecting for another scrub 17:10 Beams dumped at last injection of B2 due to losses on TCP.B6R7B2, beam unstable in H 17:30 Injecting again 20:30 Cryo Start R7 lost, but managed to save the situation 21:40 Problem with SPS, no further injections for the moment. B1 kicker timed out. 22:15 Continue injection B2. Increase RF voltage and cavity Q LHC Morning meeting – MG & JU102/08/2015

23:15 Operator dump 01:00 Problems with RF settings / bunch length / RF phase noise / RF trips / RF Low Level  RF piquet restarted FESA class. However module 1B1 is still not correctly following the setpoint, with 0.58 MV/cavity instead of the 0.75 MV/cavity requested 05:00 … and some QPS problems on top 05:30 Filling again, RF still not completely fine 06:40 Dump on too low chromaticity 07:00 Filling OK again, standard RF settings LHC Morning meeting – MG & JU202/08/2015 LHC 2 nd August 2015

TDI.B2 upper left jaw position reading over last 7 days LHC Morning meeting – MG & JU302/08/ readings of same jaw position, change opposite direction when deformation due to heating 0.2 mm Saturday morning hit the interlock limit, set at 0.2 mm Interlock

TDI.B2 Position Interlock Efficient scrubbing over the last 24 h caused maximum deformation of TDI.B2 upper jaw  hit interlock of 200 µm ‘Solution’ to move the upper jaw further out by 100 µm during injection –More margin for deformation due to heating –Reduced interception of shower –No change of interlock window Lower jaw deforms by about half the amount of the upper jaw LHC Morning meeting – MG & JU402/08/ mm Chiara

TDI.B2 single jaw movement 2 x 12 bunches bunches B2 and only 2 x 12 bunches B1. First move only upper jaw out/in, then same exercise for lower jaw Vacuum behaviour a lot worse than for TDI.B1. Something is not as it should be …. LHC Morning meeting – MG & JU502/08/2015 injection Upper jaw Lower jaw 1e-10 mbar 1e-6 mbar

The Plan Sunday –Continue 25 ns scrubbing Monday –Switch over to doublets for scrubbing assuming that we can get nice beams from the SPS Short flat bottom (Shark) Use of BCMs beams for doublets  machine protection Outstanding: –Injection cleaning optimisation LHC Morning meeting – MG & JU602/08/2015