Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
LHC SUMMARY – WEEK 36 Coordination: Mike Lamont & Bernhard Holzer LHC weekly summary 1.
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
:30 meetingEBH 1  7:53 start VdM scans LHCb  8:18 beam dump: RF M2B1 crowbar (3 rd time within 24 hours)  Access for RF  Changed thyratron.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
RF observation from Saturday morning Observation of beam induced voltage/power following the two klystron trips: 03:18 3B1 just at end ramp, 1.26E14 p.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC Injection Sequencing MD 16/23/2009 Injection sequencing / BCM R, Giachino, B. Goddard, (D. Jacquet), V. Kain, M. Meddahi, J. Wenninger.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
Tue 9/8 – Wed 10/8 Stable beams # :18 RQT12.R7B1 trip. End of STABLE BEAMS # ~86 pb -1 in ~19 hours 20:30 No beam from PSB (RF problem in ring.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wed 27/7 – Thu 28/7 09:00 LHC Controls problems
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Machine Coordinators: G. Arduini, J. Wenninger
Summary Friday h38: Ramp down and pre-cycle.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday fill with 1092 bunches (6 h stable beams)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Saturday 12:00 Fill 1992 in stable beams.
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Summary of Week 16 G. Arduini, J. Wenninger
Coordination by E. B. Holzer & J. Wenninger Production
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Finally.... We had to wait a long time.... We had many problems....
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Tuesday Access for RF & QPS (others in the shadow) until ~18:00.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday 24 October hours of 25ns MD
LHC Morning Meeting - G. Arduini
Scrubbing progress - 08/12/2012
IP8 aperture measurements (07:30-10:30)
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Saturday 24 September 2011.
Coordination: Eva Barbara Holzer, Mike Lamont
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Acknowledgements: Alain Antoine, Nicolas Magnin & Volker Mertens
Wednesday morning / afternoon
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Presentation transcript:

Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production

Summary of Week 30 G. Arduini, J. Wenninger Main aims: Adiabatic increase of peak luminosity by emittance reduction Luminosity production Fill Overview FillPhasePeak L [10 33 cm -2 s -1 ] Length [h] Int. L [pb -1 ] Dump cause 1975STABLE Cryo valve PROFIBUS (UJ76) (SEU) 1976ADJUST1.6--BLM TCSG.L7 1977SQUEEZE---RF trip: crowbar - spurious 1979STABLE QPS RCO 1980RAMP---QPS RQTL7 1982STABLE EL. perturbation 1984SQUEEZE---Vacuum R2 1985STABLE El. perturbation 1986STABLE RF klystron vacuum 1990STABLE QPS trigger RCBXV3.R1 (SEU) 1991STABLE Cryo valve PROFIBUS (UJ16) (SEU) 1992STABLE Collimator control power supply (UJ16) 1993STABLE UFO (31.L8) 1994STABLE HOM on RF Line 2 B2 (spurious) 1995ADJUST>2  UFO (Q3.L1)(ATLAS BCM) 1996STABLE CRYO Pt.8 (PLC)

Peak Stable Luminosity Delivered 2.03x10 33 Fill /07/30, 22:53 Maximum Luminosity Delivered in one day 63.7 pb -1 Friday 29 July, 2011 Maximum Average Events per Bunch Crossing 9.79Fill /07/30, 22:53 Maximum Luminosity Delivered in 7 days pb -1 Saturday 23 July, Friday 29 July, 2011 Main achievements (c/o ATLAS) pb -1 Delivered during week 30 Emittances now at the minimum achievable by the injectors and consistently below 2  m in collision at the LHC Bunch population ranging from 1.12 to 1.2x10 11 p Beam-beam tune shifts close to 0.007/IP

Statistics 24.1 % of the time in stable beams

Injection kicker MKI2 untriggered turn-ons (Thu, Friday and Saturday) Cryogenics in point 8 (Sunday, ongoing). PLC problem (this was relocated during the last technical stop) Access for QPS, RF, LBDS (Tuesday 09:00 to 21:00) to fix a series of problems encountered during the previous days Other issues: – Vacuum activity in point 2 and 8 – UFOs – Power glitches Major stops

MKI2 event no. 1 (Thu 28/7) 16:30 Injected beam of 144b dumped on TDI in IR2. – Main switch erratic on PFN C. – Injected beam was not kicked, erratic was too late to prevent the extraction. – Circulating beam was not hit. – Heavy losses in IR2, but NO quench. – Vacuum spike, valves closed.

Normal (triggered) turn-on Erratic (untriggered) turn-on of MKI2 MS3 MKI2 event no. 1 (Thu 28/7) Interlocks detected erratic. Control (machine protection) philosophy is to trigger all MS and DS of system (within a delay of 1µs). Hence all 4 kicker magnets pulsed for up to 4.5µs.  Circulating beam was not hit by the kick.  Batch was extracted from SPS but saw no kick at MKI and went straight into the TDI. Note: this MS was put in place during last TS and has since made 5 erratics (only last 2 effected beam). M. Barnes

MKI2 event no. 2 (Thu 28/7) 17:00 Following investigations by expert resumed filling for physics. 18:02 Requesting 4 th injection from 36b SPS cycle : 144b. – Circulating B1: 12+2x ~500b, 6E13 p. Massive beam loss during injection – Main switch erratic on PFN C – D1.L2, triplet L2, D2.R2 quenched. – Massive losses in IR2. – Vacuum spike and valves closed again. – ALICE hit (again).

MKI2 event no. 2 BLMs: important leakage to S23 (but no quench) and IR7.

MKI2 event no. 2 – SPS extraction analysis Extraction conclusion: – Event occurred ~2 ms before extraction. – 144b were not extracted from the SPS – the losses are coming from badly kicked circulating LHC beam. Also confirmed by TI2 BCTs and BPMs – saw no beam. LHC BPF Extraction Extraction permit Extraction MKE6 PFN charging

MKI2 event no. 2 – dumped beam BTVDD and dump line BCTs indicate that ~ 200 bunches of the circulating were not dumped  to TDI. Beam kicked to TDI

Erratic (untriggered) turn-on of MKI2 MS3 PFNs 1 & 2 at normal voltage (~50kV) PFNs 4 at low voltage (~33kV) because of PFN3 switch erratic MKI2 event no. 2 (Thu 28/7)  Erratic during resonant charging and before SPS extraction. SPS beam was not extracted.  Interlocks did NOT detect erratic of MS3 (at 33kV). PFNs discharged via the DS after 4ms (no further magnet current);  The circulating beam which was swept over the aperture and protection elements (~17% of normal kick) for ~9µs. Bunches grazing on TDI quenched D1.L2, triplet L2 and D2.R2 and hit ALICE. M. Barnes

Intervention on morning of 29/7/2011: MS3 exchanged for spare All 6 erratic detection cards, for MS3 replaced. Cards used to retrigger MSs replaced; Some 50 ohm LEMO terminations, on the retriggering chain, replaced. Local operation, SoftStarts and Inject and Dump did not result in any further erratics. MKI2

 MS3 erratic during ~04:30hrs, at 51.6kV (2kV above nominal). Erratic was correctly detected, resulting in the turn-on of all 4 MS.  MS3 erratic, during ~15:06hrs, at 50.4kV (0.8kV above nominal). Erratic was correctly detected, resulting in the turn-on of all 4 MS. Intervention on afternoon of 30/7/2011: Magnetic cores added to trigger inputs of MS3 Diagnostics added Power supply and crate for MS3 heater/reservoir replaced. Trigger units for MS3 replaced. MKI2 events no. 3-4 (w/o beam – Sat 30/7) M. Barnes

 No additional erratics since Saturday afternoon  Carry out some checks on trigger cables for MS3 this morning.  Diagnostics in place in case of other events  Spares available in point 8 and laboratory MKI2 status

Solenoids off at injection to verify the possible correlation with e-cloud  No correlation of vacuum pressure with solenoid current for L8 (but for R8). e-cloud not responsible for pressure spikes Improvement of beam lifetime and B1/B2 lifetime asymmetry and reduction of the vacuum/loss activity in IP8 after LHCb polarity switch but in particular after reduction of the emittance and working point optimization Not totally understood Vacuum spikes in L8

Possible explanation (V. Baglin) is the outgassing of an ion pump when the discharge is starting from time to time. Increase the interlock level on the nearby vacuum gauge temporarily to allow cleaning Vacuum spikes in R2

Working point optimization Fill 1990 – 0.31/0.32 Fill /0.318 Fill /0.322

Working point optimization Fill 1990 after ~1hFill 1991 after ~1.2h Fill 1992 after ~0.9h

UFO are back… 30/7 - 23:45 - arc UFO – 31L8 – Fast and strong. 31/7 07:00 –  UFO Q3-Q4.L1. ATLAS BCM dumped

We can keep the very small emittances delivered by the injectors now at their minimum These small beams can be brought in collision with almost no visible lifetime dip  working point (to be continued..) Vacuum spikes seem to become weaker but not totally understood Quite a number of stops  not really seen the effect of the increase in peak performance. Particularly penalizing for LHCb. <50 % of dumps due to high intensity/luminosity effects. In spite of the number/length of stops managed to produce a good integrated luminosity Summary

Day: Cryo recovery Evening: Physics Week 31 Coordinators: Bernhard and Mike Plans