SunGuide SM Software Development Project Status Meeting November 9, 2004.

Slides:



Advertisements
Similar presentations
Current Status of the FDOT SunGuide SM Software Project Robert W. Heller, Ph.D. March 16, 2005.
Advertisements

FDOT Central Office ITS Software Update
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting for SunGuide Release 4.1 October 14,
Indistar: Updates, Additions, and Coming Soon Stephanie Benedict, ADI.
Evaluation Tools to Support ITS Planning Process FDOT Research #BD presented to Model Advancement Committee presented by Mohammed Hadi, Ph.D., PE.
UGDIE PROJECT MEETING Kranjska Gora – April WP8 - Project Management 3 rd Amendment formalised –Budget transfer request –Time extension request.
2009 Indiana Election Administrator’s Conference Statewide Voter Registration System (SVRS) Project Update December 2,
MAINTENANCE & TRAFFIC OPERATION INCIDENT MANAGEMENT.
Statewide Transportation Management Center Software Library System Status Meeting February 17, 2004.
SunGuide SM Software Development Project Status Meeting February 23, 2005 CDRL
ITS Sketch Planning Tool Webinar 2:00 – 4:00 PM January 8, 2009.
1 ITS America Palm Springs, CA June 6, 2007 SunGuide SM Software – Florida's ITS Software ITS America Palm Springs, CA June 6, 2007 Trey Tillander, P.E.
FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.
SunGuide SM Software Development Project Status Meeting March 9, 2004.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting for SunGuide Release 4.0 August 18, 2008 August 18,
SunGuide SM Software Development Project Status Meeting (via teleconference) October 4, 2005 CDRL
Web Trnsport – Beta Testing and Implementation TUG Roundtable Discussion Elizabeth Rodgers Info Tech, Inc. October 9, 2007.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting January 11, 2005.
January 11, 2007Map Alternatives Workshop 1 SunGuide SM Map Alternatives Workshop.
Benefit-Cost Analysis of the SMART SunGuide Operations in Fort Lauderdale, Florida June 2006 Steve Corbin District ITS Operations Manager FDOT District.
May 16, 2007Change Management Board Meeting1 Local: Toll-Free: Ext
1 What’s Next for Financial Management Line of Business (FMLoB)? AGA/GWSCPA 6 th Annual Conference Dianne Copeland, Director, FSIO May 8, 2007.
SunGuide® Software Development Project Release 4.3 Express Lanes Enhancements Design Review December 15, 2009 December 15, 20091R4.3 Design Review.
Enhanced 511: Beyond the Basics Jerry Woods Florida DOT – District 5 iFlorida - Automated Message Generation Based on Travel Times.
July 14, 2010SunGuide SMD Kickoff Meeting1 BDQ69 SunGuide Support, Maintenance and Development Enhancement Contract July 14, 2010 Kickoff Meeting.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting August 27, 2007.
Statewide Transportation Management Center Software Library System (SunGuide SM ) TIM & SunGuide SM Coordination Meeting October 21, 2004 Orlando, Florida.
Research & Technology Implementation TxDOT RTI OFFICE.
Statewide Transportation Management Center Software Library System Software Requirements Review (SRR) and Status Meeting January 8, 2004.
SunGuide SM Software: Development Status Robert W. Heller, Ph.D. July 14, 2004.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
SunGuide TM Software Development Project Release 4.2 FHP/CAD + AVL/RR Design Review January 8, 2009 Jan 8, 20091R4.2 Design Review.
SunGuide SM Software Development Project Status Meeting December 7, 2004.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.
Ajh January 2007 CCSDS “Books” Adrian J. Hooke CMC Meeting, Colorado Springs 26 January 2007.
Florida Traffic Incident Management Performance Measures Paul Clark – Florida DOT Traffic Incident Management and Road Ranger Program Manager.
SunGuide SM Software Development Project Status Meeting July 13, 2004.
SunGuide SM Software Development Project Status Meeting May 10, 2005 CDRL
SunGuide SM Software Development Project Administrator Training CDRL
1 TOWER CONSTRUCTION NOTIFICATION SYSTEM ENHANCEMENTS March 30, :00 PM Room 6-B516 of the Portals II Building 445 Twelfth Street, SW Washington,
NWPP Multiple-Award Technical Support Contract (eff. 08/2005) Unit 8 Unit 8 “Managing the Task Order”
SunGuide TM 4.0 Functionality Data Fusion: How Data is Managed June 24, 2008.
PMO Update to PRS Troy Anderson ERCOT Program Management Office December 17, 2009.
SunGuide TM Software Development Project Release 4.0 Kick-off Meeting October 15, 2007.
Clay Packard, PE ITS GC Software Project Manager Florida Department of Transportation WAZE – FDOT Integration.
SunGuide SM Software Development Project Status Meeting April 29, 2004.
DHHS COE Meeting Agenda May 19, 2011 Welcome Introductions Contract Compliance Reporting Questions and Answers DHHS Open Windows Update.
Commission on Teacher Credentialing Ensuring Educator Excellence 1 Program Assessment Technical Assistance Meetings December 2009.
SunGuide SM Software Development Project Status Meeting October 13, 2004.
PMO Update to PRS Troy Anderson ERCOT Program Management Office January 21, 2010.
Grants and Contracts Jim Butterfield and Kathy Blackwood October 5, 2004.
December 16, :00 – 2:45. MPM Team Agenda 1.Review of MPM Program and Team 2.Consensus items document 3. Upcoming activities 4. Discussion.
SunGuide SM Software Development Project End of the Year ITS Working Group Meeting December 7, 2005.
State of Georgia Release Management Training
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting November 27, 2007.
April 29, 2004 Project Status Meeting Liang Y. Hsia, P.E. ITS Engineer Administrator Florida Department of Transportation.
DHHS COE Meeting Agenda February 16, 2011 Welcome Introductions Contract Compliance Reporting Questions and Answers DHHS Open Windows Update Group Exercise.
PDS4 Project Report PDS MC F2F University of Maryland Dan Crichton March 27,
TMCs – The Next Generation ITS Tennessee Annual Meeting / October 8, 2009 Dr. Robert Edelstein, PE, PTOE.
SunGuide SM Software Development Project Software Design Review May 12, 2004.
SunGuide SM Incident Management Concepts Robert Heller October 21, 2004.
Florida Department of TRANSPORTATION FLORIDA DEPARTMENT OF TRANSPORTATION Crash Cushion and Guardrail Approach Terminal In-Service Performance Evaluation.
Agenda Time Item Lead 8:30 – 8:35 Introductions Liang Hsia 8:35 – 8:50
SunGuideSM Software: Development Status Steven W. Dellenback, Ph. D
Agenda Time Item Lead 10:00 – 10:05 Introductions Liang Hsia
Agenda Time Item Lead 8:30 – 8:35 Introductions Liang Hsia 8:35 – 8:45
SunGuideSM Software Development Project Status Meeting and Demonstration April 5-6, 2005 CDRL
NM Department of Homeland Security and Emergency Management
Presentation transcript:

SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 2 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 3 Introductions

November 9, 2004SunGuide Status Meeting 4 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 5 License Updates SwRI / FDOT Sublicense –License executed on August 29, 2003 before the contract started. –License updated on September 5, 2003 covering distribution source code to other Florida governmental entities. –TxDOT informed SwRI on January 22, 2004 that TransGuide software was on “hold”. –License amended on April 12, 2004 (to support District 2 and name change)

November 9, 2004SunGuide Status Meeting 6 License Updates For a FDOT / TxDOT partnership to occur two things are needed: –MOU and License: FDOT provided TxDOT with comments and legal opinion on March 2, 2004 TxDOT provided FDOT with draft MOU and License on March 16, 2004 FDOT forwarded draft MOU & License to TxDOT on October 18, 2004 –TxDOT Software License (solves TransGuide license issue) TxDOT provided FDOT with a license on June 30, 2004 (included previous FDOT requests for content). FDOT signed license on August 10, TxDOT acknowledged the receiving of the FDOT signed license on August 23, TxDOT signed license on August 30, 2004 and sent to FDOT on September 20, FDOT Requested TransGuide software on October 4, FDOT Received TransGuide software on October 19, 2004.

November 9, 2004SunGuide Status Meeting 7 License Updates - continued FDOT / WSDOT Term of Use (TOU): –WSDOT provided FDOT with standard TOU on February 11, –FDOT provided recommendation on to WSDOT on March 13, –FDOT provided comments to the WSDOT’s Office of General Counsel’s August 21, –WSDOT began working on FDOT’s comments on August 26, –FDOT requested status on September 14, 2004, October 7, 2004 and November 5, 2004.

November 9, 2004SunGuide Status Meeting 8 License Updates - continued FDOT / MDX Joint Program Agreement (JPA) –FDOT provided MDX with preliminary JPA on December 3, –MDX provided FDOT with draft final JPA on June 23, –FDOT worked on Locally Funded Agreement and MDX JPA. –FDOT forwarded updated JPA and sublicense to MDX on October 26, 2004

November 9, 2004SunGuide Status Meeting 9 License Updates - continued SwRI / FDOT / Lee County Sublicense –Lee County provided FDOT with official letter for participation on July 27, 2004 –FDOT and SwRI started documentation preparation on July 30, 2004 –SwRI provided FDOT with draft language on September 10, 2004 –FDOT forwarded sublicense to Lee County on October 26, 2004 FDOT issued iFlorida Data Collection Process (DCP) notice to proceed on September 8, GDT License: –System Planning Office and Office of Information Systems are finalizing the license agreement on September 14, –Kevin Thibault approved the $130,000 GDT Procurement on October 19, 2004

November 9, 2004SunGuide Status Meeting 10 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 11 Reports by Deployment and Possible Integration Schedule District 4 District 6 MDX District 7 District 1 District 2 District 5 District 3 Turnpike Enterprise

November 9, 2004SunGuide Status Meeting 12 District 4 Schedule September 2004 District 4 moves equipment to new TMC October 12, 2004 SunGuide SM Software Team performs Milestone Demonstration December 2004 SunGuide SM Software Team provides TMC operators with software training January 2005SunGuide SM Software Team sets up the District 4 software

November 9, 2004SunGuide Status Meeting 13 District 4 Milestone Demonstration

November 9, 2004SunGuide Status Meeting 14 District 4 Schedule December 2004 I95/I595 Video Monitoring Project Starts. January 2005 District 4 TMC Grand Opening. January 2005 Complete I 95/I 595 Video Monitoring and Detector System

November 9, 2004SunGuide Status Meeting 15 District 6 RTMC

November 9, 2004SunGuide Status Meeting 16 District 6 Schedule June 25, 2004New TMC Grand Opening April 2005Ramp metering subsystem to be installed and tested June 2005SunGuide SM Software Release 2 deployment includes Ramp metering system July 2005I-95 Package B project completion

November 9, 2004SunGuide Status Meeting 17 MDX Schedule April 7, 2003MDX sent letter to ITS Office about participating in SunGuide SM Project April 25, 2003FDOT Responded, Welcoming MDX’s participation December 3, 2003FDOT provided MDX with a draft Joint Program Agreement June 2005 SunGuide SM Software Release 2 deployment at MDX October 2005 MDX TMC Operational

November 9, 2004SunGuide Status Meeting 18 District 7 RTMC November 2005Building Construction Finish SunGuide April 2006SunGuide SM Software Deployment

November 9, 2004SunGuide Status Meeting 19 District 2 RTMC FY 2004I-95 N ITS Improvement FY 2006SunGuide Deployment (Tentative) FY 2004I-95 N ITS Improvement FY 2006SunGuide SM Deployment (Tentative)

November 9, 2004SunGuide Status Meeting 20 District 5 RTMC FY 2004 Orlando RTMC retrofit and upgrade September 8, iFlorida Data Collection Process December 2005 FY iFlorida C2C between Districts 2 and 5

November 9, 2004SunGuide Status Meeting 21 Turnpike RTMC

November 9, 2004SunGuide Status Meeting 22 Turnpike Schedule March 2004SunNav 1.1 Test April 2004SunNav 1.2 Development June 2005 Observe D 4, D 6, & MDX C2C Deployment

November 9, 2004SunGuide Status Meeting 23 District 1 May 2005 I-75 Safety Barrier System upgrade December 2006 SunGuide Deployment at Ft. Myers RTMC FY 2011 (2005) Sarasota RTMC December 2006 SunGuide SM Deployment at Ft. Myers RTMC FY 2011 (2005) Sarasota RTMC

November 9, 2004SunGuide Status Meeting 24 District 3 FY 2007 Pensacola RTMC FY 2008 Tallahassee RTMC

November 9, 2004SunGuide Status Meeting 25 Lee County Bridge Incident Management July 27, 2004 Lee County Public Works will participate in SunGuide Software

November 9, 2004SunGuide Status Meeting 26 C2C Schedule February 16, 2004SunGuide SM and C2C Project Team completed Interface Control Document (ICD) February 20, 2004SunGuide SM and C2C Project Coordination Teleconference March 9, 2004SunGuide SM & C2C Project Coordination Meeting June, 2005C2C deployment among Districts 4, 6, and MDX

November 9, 2004SunGuide Status Meeting 27 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 28 Project Web Site

November 9, 2004SunGuide Status Meeting 29 Release-Oriented Development Approach

November 9, 2004SunGuide Status Meeting 30 Status of Release 1 Activities Project Management: –PM / Meetings / Reviews –Process documents –Interface Control Documents (ICDs) Core software framework: –Database –User administration –Executive handler –Status logger –User interface –Map –Data Bus DMS: –General Subsystem –NTCIP Florida MIB driver –Mark IV version 2.5 driver

November 9, 2004SunGuide Status Meeting 31 Status of Release 1 Activities - continued CCTV Control: –General Subsystem –NTCIP 1205 driver Video Switching –General Subsystem –IP Video switching driver Video Wall –General Subsystem –Barco/Argus video wall driver Traffic Detection, driver for: –General Subsystem –Bitrans B238-I4 driver –RTMS (EIS and Wavetronix) driver

November 9, 2004SunGuide Status Meeting 32 Status of Release 1 Activities - continued Incident Management: –GUI –Subsystem –TIM coordination Training: –Training Plan –Classes being adjusted –Material being developed Testing –Integration testing –Document development Documents: –Software User’s Manual (SUM –Version Description Document (VDD) –Software Design Document (SDD)

November 9, 2004SunGuide Status Meeting 33 Status of Release 2 Activities Ramp Metering: –Design activities initiated –Initial GUI design completed –High level design completed Emergency Evacuation: –Requirements refined and provided to FDOT –Design initiated Data Archive –Requirements refined –Design initiated Web Server –Requirements refined –Design initiated HAR –Requirements refined –Design initiated Center-to-Center –Requirements refined –Design initiated RWIS –Requirements refined –Design initiated Inventory and Maintenance –Requirements to be refined Optional Service: –iFlorida Data Collection Process (DCP)

November 9, 2004SunGuide Status Meeting 34 Development Activity Software development for Release 1 is complete Current Release 1 activities: –Integration Testing –System Testing –Endurance Testing –Documentation (ICDs and SDD) Release 2 activities: –Design –Prototyping (preview in the December meeting) –Coding to start soon

November 9, 2004SunGuide Status Meeting 35 Development Schedule For the last 12 months: –Factory Acceptance Testing in San Antonio on November 17-19, 2004 –Deployment in District 4 on December 2, 2004 Recent developments: –District 4 ready to deploy late January, early February 2005 –Additional review time for testing documents –FDOT’s request to add District 4 DMS Message rules to the Incident Management Subsystem PRIOR to Release 1 testing New Schedule: –Factory Acceptance Testing in San Antonio on January , 2005 –Deployment in District 4 on January 24, 2004

November 9, 2004SunGuide Status Meeting 36 Deliverable Status SwRI waiting for FDOT comments: –Concept of Operations –Version Description Document Future documents to be provided by SwRI: –Software Integration Case Procedures (final version) –Software User’s Manual (draft and final version) –Software Design Document (final version) –District 4 Deployment Plan (draft and final version) All documents delivered to FDOT are available on the project web site.

November 9, 2004SunGuide Status Meeting 37 Cost Status Release 1: –Budget amount: $3,863,374 –As of 9/24/04, ~$3,257,000 has been expended Release 2: –Budget amount: $2,568,339 –As of 9/24/04, ~$254,000 has been expended Adjustments: –Reductions (funds back to FDOT): Eliminating DTS Efforts: $75, Combining 2a and 2b: $66, (this includes a “training adjustment” to add classes) –Additions: iFlorida DCP Task: $64, Distinct 4 Message Rules: $30,854.32

November 9, 2004SunGuide Status Meeting 38 Spending Curve

November 9, 2004SunGuide Status Meeting 39 Schedule Status Current areas of concern: –Documents: None –Software: None

November 9, 2004SunGuide Status Meeting 40 Schedule Status – continued Last Reporting Period

November 9, 2004SunGuide Status Meeting 41 Schedule Status - continued Current Reporting Period

November 9, 2004SunGuide Status Meeting 42 Functional Threads

November 9, 2004SunGuide Status Meeting 43 Schedule Status - continued Integration/Testing: –Proceeding well –Continuing long term “endurance” testing “Factory” Acceptance Testing: –Tentatively January in San Antonio Future status meetings that need to be scheduled: –December 8, 2004 (“short” meeting in Jacksonville) Future reviews that need to be scheduled: –Release 2 Software Design Review: sometime early 2005, will be held once other Release 1 and Release 2 enhancement requests are complete

November 9, 2004SunGuide Status Meeting 44 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 45 TIM Coordination Meeting Meeting: –Held: Thursday, October 22, 2004 –Where: Orlando RTMC Attendees: –Mike Akridge, FDOT –Elizabeth McCrary, FDOT –Liang Hsia, FDOT –Dong Chen, FDOT –Steve Corbin, FDOT –Denny Pedrick, FDOT –James Bitting, FDOT –Kendra Blackforce, TPK –Ranzy Whiticker, TPK –Mike Meincke, TPK –Mike Washburn, TPK –Nelson Figueroa, FDOT –Larry Rivera, FDOT –Paul Dixon, FHP –Mark Roberts, FDOT –Brenda Young, FDOT –Jennifer Heller, FDOT –Robert Heller, SwRI –Bret Sadler, SwRI –Walt Townsend, ITS-Siemens –Charles Wallace, PBF

November 9, 2004SunGuide Status Meeting 46 TIM Coordination Meeting: Capability for Consideration Link to Computer Aided Dispatch (CAD) system, which is a standard, statewide system. SunGuide SM has a C2C capability through which CAD data could be transmitted but logic would need to be added when received in SunGuide SM. Some districts have adopted three levels of incidents based on both severity (length) of the incident and lane closures. This was not in the IM requirements per se (there are three “levels”: Minor, Moderate and Severe that are functions of user-defined percentages of lanes blocked). The new MUTCD uses three levels based on time (which are similar to Florida’s time-based criteria. The conclusion was that the definition of incident severity (and their labels) should be user configurable, and that the history of an incident’s evolution should be fully reproducible. (Note: there must be some commonalities in order to report and measure performance at a statewide level.) District 4 has proposed a standard template for DMS messages that is being implemented in SunGuide SM.

November 9, 2004SunGuide Status Meeting 47 TIM Coordination Meeting: Capability for Consideration – con’t The software should associate a lane configuration with each TSS link on the map. When the operator clicks on a link to create an incident, automatically pre-select the lane configuration associated with that link. (Currently, when an operator creates an incident, they must manually choose a lane configuration for the location associated with the incident.) In the message sign control GUI, add a way to bring up a camera that can see the sign, in order to confirm message activation. When logging incident data, include TSS data so that “end of congestion” time can be tracked as well as closure of incidents. The TIM group suggested identifying incident data by region (rural and urban), route, number of accidents, time to clear and recover from incidents, vehicle types, and highest location of incidents. The TIM Group needs to refine these requirements, including explicit reporting requirements.

November 9, 2004SunGuide Status Meeting 48 TIM Coordination Meeting: Capability for Consideration – con’t It was suggested that incidents should identify types of vehicles involved in the incident (CV/auto, auto/auto, CV/CV, multiple vehicles of all types, etc.). SunGuide SM needs to include the statewide TIM performance measures currently being researched. SunGuide SM ‘s geo-location system is based entirely on lat-long. It will be important to add mile marker locations, particularly in view of a possible deployment of location reference markers extensively throughout the state. This process needs to be automated. Also, freeway cross streets are common reference points, so a quicker way for operators to locate them is desirable. Similarly, it needs to be determined whether it is necessary to include the link-node system. SunGuide SM has a flag to indicate that a hazardous material is involved in the incident, but the type of material is not captured. A set of HAZMAT categories at least, or actual chemicals at most, should be added.

November 9, 2004SunGuide Status Meeting 49 TIM Coordination Meeting: Capability for Consideration – con’t It is further suggested that other data, such as ambient lighting, be added. The TIM Program will need to specify all such data that are not currently being captured. The contacts list currently has to be created for each incident. The capability to have contact groups should be added, and incidents should be able to have pre-designated groups to notify, by severity level and perhaps even other criteria. (Note: these pre-designated groups would be a minimum given the incident.) Dispatching of Road Rangers should be automated in the software. The use of PDAs for Road Ranger logging needs to be recognized and the ability to upload these data be added. Consider changing the DMS editor to allow selecting multiple signs to update with the same message, dragging one sign into another to copy text, etc. Also, when adding a sign to an incident response plan midstream, allow its proposed message to be populated automatically. Add Incident Management reporting capabilities. Districts are to submit examples of their desired reports.

November 9, 2004SunGuide Status Meeting 50 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 51 Hands-On Training On November 5, 2004 SwRI received the following comment: –Section – Page 6: It states that this is not a hands on Training Course. This needs to be so the operators will get a feel and fully understand how to operate the system. SwRI’s Position: –SwRI received request for hands-on training. –SwRI had planned on having a laptop version of the software for the instructor to use. –Happy to alter the training for hands-on. –Problem is hardware. Will the Districts have a test environment with field equipment to support training? Discussion?

November 9, 2004SunGuide Status Meeting 52 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 53 Canoga Loop Background Limitations of older 3M devices: must poll the device often (essentially every vehicle): –C822/C824 –C922/C924 (new version of the above) 3M has a newer product: –"Traffic Monitoring Card" (numbered as 942/944) –Works in conjunction with the C922/C924 –Provides the capability to establish a monitoring interval in the range of 1 second to 15 minutes –Driver can then poll at this interval, the device will provide average speed, occupancy, volume for the specified interval –The device can be polled for the last 300 intervals (i.e. it keeps a history of 300 intervals) or you can request the data for the last 500 vehicles (i.e. it keeps a history of the last 500 vehicle reads) Same protocol is used for all above devices (some additional messages to support the Traffic Management Card

November 9, 2004SunGuide Status Meeting 54 Canoga Loop Issues: Discussion Topics Use of 170 controllers –SwRI would recommend using SunGuide SM application servers rather than 170s if the communications infrastructure supports the protocol bandwidth Price of Canoga units –How do they compare to RTMS or other devices? Installation costs –How do they compare to other devices? Does FDOT want a Canoga driver for SunGuide SM ?

November 9, 2004SunGuide Status Meeting 55 Agenda TimeItem Lead 10:00 – 10:05Introductions Liang Hsia 10:05 – 10:10License Updates: - TxDOT and FDOT - MDX JPA - TransGuide - GDT - WSDOT TOU - SwRI/FDOT Modification Liang Hsia 10:10 – 10:20TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDX Turnpike Enterprise 10:20 – 10:50Project Status Report Steve Dellenback 10:50 – 11:00SunGuide SM and TIM Coordination Meeting Briefing Liang Hsia 11:00 – 11:10SunGuide SM Training Steve Dellenback 11:10 – 11:20Canoga Micro Loops Steve Dellenback 11:20 – 11:35SunGuide SM Demonstration and/or Screen Review Robert Heller 11:35– 11:40Open Discussion / Action Item Summary All

November 9, 2004SunGuide Status Meeting 56 See Other Presentation

November 9, 2004SunGuide Status Meeting 57 Action Item Recap NumberPersonAction