© Property of ERCOT 2001 ERCOT Limit Calculation Process John Adams Operations Engineer.

Slides:



Advertisements
Similar presentations
Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Advertisements

Goshen Area Bus Reconfiguration
2004 Congestion Costs. 2 Transmission Congestion Occurs when analysis shows a given outage of a transmission element (contingency) will result in the.
CSC/CRE Technical Review 6 October Outline  Review the process used in calculating Power Transfer Distribution Factors (PTDFs).  Information.
Discussion: Use of RAPs in system operations Kris Dixit 1.
Recent ERCOT Events Lessons Learned
Announcements Be reading Chapter 6, also Chapter 2.4 (Network Equations). HW 5 is 2.38, 6.9, 6.18, 6.30, 6.34, 6.38; do by October 6 but does not need.
Real-Time Transmission Congestion Management & Market Effects
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
System Operations Staffing Request Presented to the ERCOT Board Of Directors By Sam Jones, COO November 16, 2004.
9/14/2015 IEEE Presentation Time-Based Management of Large Scale Network Models John Moseley P.E. Lead Network Model Engineer.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
March 2003 Operations Summary Bill Blevins Manager Operations Engineering.
NSRS deployment April John Adams ROS – May 12, 2005.
Peak RCCo Performance Metrics Draft –November 2013.
Monthly TCR Calculation DRAFT 3 James J. Teixeira 05/11/02 Also review ERCOT Protocols Section 7 for more details and additional data.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Public Meeting on ERCOT’s Proposed 2004 Budget September 3, 2003 Preliminary - Subject to ERCOT Board Approval.
Reliability Requirements Bill Blevins Manager of Operations Support ERCOT.
Lead from the front Texas Nodal 1 External Web Services Update Nodal Implementation Team Presentation July 7, 2009.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
April, 2008 Maximum Shadow Price. April, 2008 Protocol Requirement: Transmission Constraint Management (2)ERCOT shall establish a maximum Shadow.
Lead from the front Texas Nodal 1 Texas Nodal Energy Management System Requirement Documents December 5, 2006 Jay Dondeti EMS Project.
SO – CART Project Status Protocol Revision Subcommittee Update 2/23/06.
EDS 2 Early Delivery Systems Review and Request for Approval May 2007 John Webb.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
AFC METHODOLOGY EMS USER GROUP SEP 12, 2004 AFC – New Developments EMS USER GROUP Sep
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
East Texas Export Limit ERCOT Operations Planning ERCOT Market Presentation
Transmission Outage Process April Purpose In compliance with the Protocols and the Electric Reliability Council of Texas (ERCOT) Operating Guides,
8/22/2006 TPTF MIS Update Kate Horne Pat Harris. TPTF8/22/2006 Agenda Review proposed site map Discuss role of MIS task force Obtain clarification on.
© Property of ERCOT /17/20041 RTCA, CAM, and SFT Presented by: John Adams November 17, 2004.
Page 1 TAC Program and Projects Update March 6, 2003.
December 2, 2004 Congestion Causes and Effects Presented to WMS January 14, 2005 Beth Garza.
Information Technology Report Dave Pagliai Manager, IT Support Services October 2015 ERCOT Public.
Managing of Limits during Loss of Analysis Tools/ EMS April 23, 2014.
2010 CSC & Zone Selection: 6 Lines W-N & 4 Zones (WN2_SN0-4Z) Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) August 19,
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Severe Winter Weather Resource Outage Analysis Chad Thompson Operations Working Group September
Stability Limit Management Chad Thompson Manager, Operations Support Planning Working Group Meeting ERCOT Public January 20, 2016.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
MISUG TAC Update Jackie Ashbaugh ERCOT 3/7/ TAC3/7/ /22/2011 Meeting Focus on the high priority items from MISUG: Review task list prioritization.
HDL Overrides ERCOT January 7, Pre-posture for a planned outages Unsolved Contingencies Conflict between voltage support and thermal post-contingency.
© Property of ERCOT EMMS Improvements Operations Review Group 11/17/04.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Regional Operations Review Group Activities Status Report to TAC April 8, 2004.
Joint PLWG/CMWG Assignment Update to ROS September 15, 2011.
A new Nomogram Development POM- based tool - Application results in the Idaho Power System. Orlando Ciniglio, IPC Marianna Vaiman, V&R Energy WECC TSS.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
09/20/20061 RTCA, CAM, and SFT Presented by: John Dumas September 20, 2006.
ISO Confidential Overview of California’s Current Drought and its Effects on the Energy System Dede Subakti, P. E. Director, Operations Engineering Services.
Day-Ahead Market Discussion/Clarification TPTF April 24, 2006.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
What Is Firefox? __________ is a Web ___________ that you use to search for and view Web pages, save pages for use in the future, and maintain a list.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
MISUG Meeting Materials ERCOT 7/26/ MISUG Agenda 1.Antitrust AdmonitionJ. Lavas9:30 a.m. 2.IntroductionsJ. Lavas9:30 a.m. 3.Market Data Transparency.
WMS UPDATE CMWG n CMWG has completed their data collection and evaluation of congestion n Based on this evaluation WMS recommends that the same CSCs with.
Information Needed By All Market Participants To Facilitate Transmission Congestion Studies In ERCOT Presented to the ERCOT ROS by Shannon Caraway, P.E.
Southern Cross Directives Planning Items
Review of Abnormal MCPEs
Path Operator Implementation Task Force
Grid Integration of Intermittent Resources
ECEN 460 Power System Operation and Control
Western Electricity Coordinating Council
ISO New England System R&D Needs
ECEN 460 Power System Operation and Control
Time-Based Management of Large Scale Network Models
Presentation transcript:

© Property of ERCOT 2001 ERCOT Limit Calculation Process John Adams Operations Engineer

© Property of ERCOT 2001 Philosophy  Prevent ERCOT from entering a state in which a single contingency leads to cascading outages or instability

© Property of ERCOT 2001 Process  Review Outage Coordinator notes.  Model most severe expected conditions next day using a power flow case describing resource plan & outage schedule conditions.  Perform contingency analysis and analyze most severe consequences of forced outages on planned operations.  For each contingency leading to post contingency loading over 110% rating: Review to determine if cascading

© Property of ERCOT 2001 Process  If post contingency overloading appears to be both real, and cascading: prepare an operational limit  Prepare daily limits sheet and provide to operations desk

© Property of ERCOT 2001 Review CSC Limits  Operation Engineer reviews limits on CSC’s for next day. Sandow-temple – performs a power flow and contingency analysis describing this particular interface; Increasing the loading until post contingency loading of 110% of the thermally adjusted rating is reached.

© Property of ERCOT 2001 Review CSC Limits  Operations Engineer reviews limits on CSC’s for next day. STP-WAP – review with a power flow study ~once/week. Apply temperature de-rating daily.

© Property of ERCOT 2001 Review CSC Limits  West-north – review with power flow once/week. Review stability limits from file studies daily in light of units online. If necessary apply a reduced limit  North-west – review with power flow once/week.

© Property of ERCOT 2001 Outage Coordinator Studies  On many occasions, the outage coordinator studies have alerted operations to a security limit which has been studied by the TDSP or the outage coordinators. These limits are provided to operations via the outage notes. Generally, outage coordinators ask operations engineering to review all such limits.

© Property of ERCOT 2001 Distribution of Limits Sheets  Limits sheets are faxed to transmission operators monitoring the CSC interfaces.

© Property of ERCOT 2001 Enforcement  Operator enters CSC limits on “real time transmission constraints limits.”  These limits are automatically posted on the “actual system demand” page of the ERCOT web site.  Transmission & security operator monitors these limits, and adjusts the OC1 constraints to hold actual flows below the physical limit.

© Property of ERCOT 2001 Enforcement  On operational congestion limits, the operator normally asks the operations engineer to calculate shift factors for units in the area, and create an OC2 constraint to control this limit.  To create these shift factors, the operations engineer normally performs a MUST study.