3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.

Slides:



Advertisements
Similar presentations
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Advertisements

WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
LSU 07/24/2004Defining Project Tasks1 Defining the Project Tasks Project Management Unit, Lecture 4.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
Chapter 9. Intro  What is Project Management?  Project Manager  Project Failures & Successes Managing Projects  PMBOK  SDLC Core Process 1 – Project.
RF Cavity / Coupling Coil Module
1 CAPACITY BUILDING AND TRAINING ON PROCUREMENT Session 9 – The World Bank Procedures for IT Procurement September 21, 2005 by Arif Hassan.
Server Virtualization: Navy Network Operations Centers
Andy Stefanik 1July 2006 Mechanical Overview WBS 1.5 Opto-Mechanical System Andy Stefanik - Fermilab.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Project Tracking. Questions... Why should we track a project that is underway? What aspects of a project need tracking?
Soft Tech Development Inc. 1 Software Project Tracking A CMM Level 2 Key Process Area Soft Tech Development Inc.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
Lecture 11 Managing Project Execution. Project Execution The phase of a project in which work towards direct achievement of the project’s objectives and.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
3.1 Optomechanical systems (1) Scientific and engineering resources are available to carry out the optomechanical work on DECam. The highly distributed.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Risk Management 1. Risks and Risk Management Risks are potential events that have negative impacts on safety or project technical performance, cost or.
Oct 17, 2001SALT PFIS Preliminary Design Review1 PFIS/ IMPALAS Issues Outside Reviewer's Comments Post-PDR tasks Valuation Issues.
TOF Project Construction Project Plan
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
U.S. Department of Energy’s Office of Science Dark Energy Survey (DES) Project Stephen Tkaczyk, Chair DOE/SC Review Committee September 10, 2008
Federal Aviation Administration By: Giles Strickler, UCS Program Manager Procurement Policy (AJA-A11) Date:September 22, 2010 Unified Contracting System.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Copyright 2010, The World Bank Group. All Rights Reserved. Statistical Project Monitoring Section A 1.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
Lesson 1: Examining Professional Project Management Topic 1A: Identify Project Management Processes.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
XLIX Engineering Design Firm © 2010 ENGR/ETGR Definition of Project 1 A project is “…a combination of human and non-human resources pulled together.
Brenna Flaugher October 30, 2007 Preliminary Directors Review 1 Outline This talk will describe progress on DECam since the joint NSF/DOE CD-1 review in.
System Performance Metrics and Current Performance Status George Angeli.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Advanced Project Management Project Planning Phase Ghazala Amin.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
DES Review CCD Focal Plane and Camera Roger Smith George Ricker.
UCLA - March 8, 2006 US TBM Cost Estimate Status March 8, 2006 Tom Mann.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
OUTAGE MANAGEMENT. OUTAGE APPROACH/PHILOSOPHY A) Time based / machine operating hours based concept related to OEM recommendations - More expensive than.
Apr 29, 2003SSWG - CDR Comments1 PFIS Critical Design Review Comments Detailed response available in document SALT- 3100BP0011 (PFIS web site) Responses.
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Oct 17, 2001SALT PFIS Preliminary Design Review Management, Schedule, & Budget 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Management,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Proton Plan PMG 7/27/06 J. Sims 1 Proton Plan Cost and Schedule Report Jeff Sims.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Camera PDR/CD1 Planning 19 September 2008
Jim Fast Pacific Northwest National Laboratory
ENGR 281 Engineering Scholars Program Project Management Life Cycle Overview K. F. Reinschmidt J. L. Frank / Marathon Ashland Petroleum LLC Chair in.
2K CB FDR Overview:  Agenda, Charge, Review Process
Budget Budget Contingency/ Cost Risks Descope Options
Management Breakout: MREFC Budget Summary Victor L
Lockheed Martin Canada’s SMB Mentoring Program
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Systems Engineering for Mission-Driven Modeling
Presentation transcript:

3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver

3.1.1 Optics, Optical Corrector, Mechanical Systems (1) Findings & comments:  WBS tasks for the optical and opto-mechanical assemblies are complete with resource loading and documented cost estimates. The estimates appear to be conservative and contingency allowances take risk into account.  A review of the costs associated with telescope simulator testing at FNAL and on-site integration at CTIO is advisable.  No schedule problems were identified at this time. Progress is tracked through regularly spaced milestones, EV analysis, plus other metrics. Slack time is not explicitly added in the WBS.  Six of nine recommendations from the May 2007 joint DOE/NSF DES review have been fully addressed. Pending items include a stray light analysis, the design of the C1 lens cover, and finite element modal analysis of the combined DECam/telescope structure.

3.1.1 Optics, Optical Corrector, Mechanical Systems (2)  System engineering has improved within the DECam project with the hiring of a project scientist. System engineering documentation (requirements and interface documents) and configuration control are being implemented. These are critical for the success of the distributed opto- mechanical effort.  A FE modal analysis of DECam mounted in the telescope top ring is needed to validate the design of the cage, vanes and hexapod. The analysis may reveal potential problems in the design that result in lower modal performance and need to be addressed. It also provides the basis for specifying stiffness requirements for the hexapod assembly.  The plan for manufacturing and assembling the DECam optics is deemed adequate. Careful attention must be paid to fabrication and assembly tolerances to insure that optical performance meets error budget specifications.

3.1.1 Optics, Optical Corrector, Mechanical Systems (3)  The filter changer and shutter assemblies are being provided by U. Michigan. The assemblies will be purchased from Bonn and are based on scaled up versions of existing designs. The technical and schedule risk for these items is deemed to be low.  The Project will use a hexapod for positioning DECam within the cage assembly. The project has received engineering and fabrication cost estimates from a number of vendors. Hexapod development is on the critical path and the Project is requesting CD3A approval to go forward with early procurement. Hexapod stiffness requirements should be determined from the finite element modal analysis. The hexapod is ready for CD3A development pending the results of the FE modal analysis.

3.1.1 Optics, Optical Corrector, Mechanical Systems (4)  Advancing filter procurement one year will significantly reduce the risk of schedule slip. The procurement of filters is currently on the critical path.  The DECam project should evaluate the programmatic impact of the loss of a filter due to breakage and obtain a quote for the cost of providing spares.  The effect on image quality of a temperature differential between the DECam cage and ambient air should be analyzed and the specification and/or the thermal design of the assembly revised if necessary to comply with the image error budget. Current specifications allow the DECam cage assembly to be at a temperature up to 2° C different from ambient.

3.1.1 Optics, Optical Corrector, Mechanical Systems (5) Recommendations: 1.Continue to develop the systems engineering controls prior to CD3B. 2.Complete the pending recommendations from the May review prior to CD3B. 3.Review the costs for DECam assembly & integration at FLAL and CTIO and provide a generous contingency to the budget and schedule for these activities. (Prior to CD2 baseling) 4.Perform an FE modal analysis of DECam in the telescope structure within 6 months. 5.Analyze the effect of a hot air plume caused by the cage assembly being at a temperature 2 degrees above ambient prior to CD3.

3.1.1 Optics, Optical Corrector, Mechanical Systems (6) Recommendations: 6.Investigate the cost to provide a set of spare filters prior to CD3. 7.Develop a strategy to control the hexapod positioner in the required 5 degrees of freedom prior to CD3. 8.Proceed to CD2 with Opto-mechanical systems. 9.Proceed with CD3A procurement of the hexapod assembly pending the results from the FE modal analysis.