11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Chapter 17 Project Management McGraw-Hill/Irwin
Chapter 13 Project Scheduling: PERT/CPM
Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. Use.
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Project Management and scheduling Objectives of project scheduling Network analysis Scheduling techniques.
Operations Management Session 27: Project Management.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
PERT / CPM PERTProgram Evaluation & Review Technique CPMCritical Path Method.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
Tutorial 2 Project Management Activity Charts (PERT Charts)
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
PERT/CPM Models for Project Management
ME 380 Project Planning. Critical Path Method (CPM) Elements: Activities & Events Feature: Precedence relations ActivityDurationPrecedence A4- B5- C3A.
Operations and Supply Chain Management, 8th Edition
BA 333 Operations Management
Project Management. Introduction What – Project Management Where – Where the success or failure of a project will have major consequences for the company.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
ENGM91 ACTIVITY PLANNING Unit 2
Project Management Chapter Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame. Build A A.
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Chapter 17 Project Tracking. Objectives Identify, develop, and use project management tools to track project progress: Schedules Gantt Charts Toll Gate.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6.
Project Management (專案管理)
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
PROJECT MANAGEMENT Approaches
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Prof.Dr. Ahmet R. Özdural – Class Notes_06 - KMU417 Project Planning and Organization – Fall Semester.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Managing the Information Systems Project Cont’d
Chapter 16 – Project Management
Project Management.
PROJECT MANAGEMENT.
Project Management (專案管理)
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Planning & Scheduling
Project Management and scheduling
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
Project Scheduling: networks, duration estimation, and critical path
Chapter 16 – Project Management
Project Management (lecture)
Project Management (lecture)
Presentation transcript:

11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration of each task, subtask,...  Estimate resource requirements for each task, subtask,...(budget, personnel, facilities)  Identify precedence relations among tasks

11/02/09 Chapter 7-Project Planning 2 Benefits of Project Planning  Communications tool  Resource allocation  Benchmarking

11/02/09 Chapter 7-Project Planning 3 Stages of Engineering Design Projects  Enthusiasm  Disillusionment  Panic  Search for the guilty  Punishment for the innocent  Praise and honors for the non- participants

11/02/09 Chapter 7-Project Planning 4 Project Planning Tools  Gantt Chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT)  Variations and combinations of the above  Many available software packages contain these tools

11/02/09 Chapter 7-Project Planning 5 Gantt Chart for Automobile Bumper Project Fig. 7.2

11/02/09 Chapter 7-Project Planning 6 Enhanced Gantt Chart for Automobile Bumper Project Fig. 7.3

11/02/09 Chapter 7-Project Planning 7 Keeping Track of Project Progress on a Gantt Chart Fig. 7.4

11/02/09 Chapter 7-Project Planning 8 Typical Electric Substation Fig. E7.3.1(a)

11/02/09 Chapter 7-Project Planning 9 Tasks for Designing and Building an Electric Substation Table E 7.3.1

11/02/09 Chapter 7-Project Planning 10 Gantt Chart for Substation Design and Construction Fig. E7.3.1(b)

11/02/09 Chapter 7-Project Planning 11 Critical Path Method (CPM)  Uses a network flow diagram to depict the precedence relations among activities (tasks)  Elements of diagram are directed line segments and nodes  Facilitates identification of activities whose timely completion are “critical” to timely completion of the project

11/02/09 Chapter 7-Project Planning 12 CPM Notation and Conventions  An activity is an ongoing effort on a project task (directed line segment).  Every activity has an initiating event and a closing event (nodes).  Events consume no time. Their primary role in CPM diagrams is to separate activities.  Consecutive activities must be separated by events. Fig. 7.6

11/02/09 Chapter 7-Project Planning 13 CPM Notation and Conventions (cont.)  No pair of events can be directly connected by more than one activity with no intervening events. If an activity R must immediately precede S and T, the relationship is depicted as follows Fig. 7.7(a)  If activities R and S must both immediately precede T, the relationship is depicted as follows Fig. 7.7(b)  All networks must begin with a single Start event and end with a single Finish event.

11/02/09 Chapter 7-Project Planning 14 Dummy Activities  Sometimes precedence relationships require the use of a dummy activity (depicted by a dashed line) to indicate the appropriate relationships. Dummy activities do not take up any time.  Dummy activity is needed to correctly depict that P and Q must precede S, and P must precede R.  Dummy activity needed when several activities have same Start and End events. Activities R and S share the same Start and End events. Fig  Dummy activities should be be included only when needed to display the precedence relation.

11/02/09 Chapter 7-Project Planning 15 Precedence Relations for Several Activities of Bumper Project Table 7.2 ActivityPreceded by Design bracket Build bracketDesign bracket Build bumper Drill holes in bumperBuild bumper, Design bracket

11/02/09 Chapter 7-Project Planning 16 Using Dummy Activity for Bumper Project Fig. 7.8

11/02/09 Chapter 7-Project Planning 17 Multiple Dummy Activities  A precedes D  A and B precede E  B and C precede F Fig. 7.9

11/02/09 Chapter 7-Project Planning 18 Project Activities and their Precedence Relations Table 7.1 ActivityDurationPreceded by A3 B3A C4 D1C E3B, D F2A, B, D G2C, F H4G I1C J3E, G K5F, H, I

11/02/09 Chapter 7-Project Planning 19 Constructing a Network Diagram Fig Fig. 7.11

11/02/09 Chapter 7-Project Planning 20 Example of Constructing a Network Diagram Table E7.4.1 Fig. E7.4.1 ActivityPreceded by A B C DA,B EC FA GD, E, F HC IH JD, E KI, J LG ML, K

11/02/09 Chapter 7-Project Planning 21 Another Example of Constructing a Network Diagram*

11/02/09 Chapter 7-Project Planning 22 The Critical Path  The critical path is the path of activities from the start event to the finish event for which delay in any activity along that path will delay the project finish.  For projects with a small number of alternative paths, the critical path can be most efficiently identified by finding the longest of the alternative paths.

11/02/09 Chapter 7-Project Planning 23 Alternative Paths and their Length  For the project depicted in Fig Table 7.3  Thus, A-B-F-G-H-K is the critical path

11/02/09 Chapter 7-Project Planning 24 Critical Path Depicted on Network Diagram Fig. 7.13

11/02/09 Chapter 7-Project Planning 25 Example Problem of Finding the Critical Path*

11/02/09 Chapter 7-Project Planning 26 Alternate Method for Determining Critical Path  This approach is more efficient for larger networks –Use forward sweep to find earliest start (ES) for each activity –Use backward sweep to find latest start (LS) for each activity –Calculate total float (TF) for each activity TF = LS - ES –Critical Path consists of Activities with TF = 0

11/02/09 Chapter 7-Project Planning 27 Earliest Start*  Earliest Start (ES) is the earliest time an activity can start. It is found by tracing forward (from tail to head of each activity arrow) from the project Start event to the tail of the selected activity. When several paths are possible, use the longest path as determined by the sum of the activity durations on that path.  For activity F, ES = 9

11/02/09 Chapter 7-Project Planning 28 Project Duration*  Continue until we have ES for all activities that terminate in the project Finish event. When duration of each of those activities are added to their respective ES times, the largest of the resulting sums is defined as the Project Duration.  For activity H, ES=20  Project Duration =20+4=24

11/02/09 Chapter 7-Project Planning 29 Latest Start*  Latest Start (LS) is the latest time an activity can start and still have the project completed within the Project Duration time.  LS is found by tracing backwards (from head to tail of each activity) from the project Finish event to the tail of selected activity. Make sure you reach the tail of the selected activity via the head of that activity. When several paths are possible, use the longest path as determined by the sum of the activity durations on that path. The Project Duration minus the length of this longest path is the LS for the selected activity.  For activity A, LS=24-24=0

11/02/09 Chapter 7-Project Planning 30 Total Float  Total Float for each activity is the difference between the latest start and the earliest start. TF = LS - ES  The activities for which TF=0 define the critical path.

11/02/09 Chapter 7-Project Planning 31 Summary of Total Float Calculations*  Critical Path consists of A-D-F-G-H

11/02/09 Chapter 7-Project Planning 32 Total Float Calculations Table 7.4  For project shown in Fig. 7.12

11/02/09 Chapter 7-Project Planning 33 Example of Critical Path Determination Fig. E7.4.2(a)

11/02/09 Chapter 7-Project Planning 34 Summary of Example Float Calculations Table E7.4.2

11/02/09 Chapter 7-Project Planning 35 Critical Path for Example Problem Fig. E7.4.2(b)

11/02/09 Chapter 7-Project Planning 36 Program Evaluation and Review Technique (PERT)  Based on Critical Path Method  Replaces single estimate of activity duration by a probability distribution  Allows estimate of probability of completing project by a specified time

11/02/09 Chapter 7-Project Planning 37 Typical Beta Distributions for Activity Durations  t o -optimistic estimate; the shortest time within which this activity can be completed assuming everything goes right. This is the left terminus of the pdf.  t m -the most likely time required to complete the activity. This is the mode of the pdf.  t p - pessimistic estimate; the longest time it will take this activity to be completed assuming everything goes wrong. This is the right terminus of the pdf. Fig. 7.14

11/02/09 Chapter 7-Project Planning 38 Network Diagram for PERT Example Problem Fig. 7.15

11/02/09 Chapter 7-Project Planning 39 PERT Procedure  Calculate the expected duration t e (mean) of each activity  Calculate the variance  2 of each activity  Use t e to determine the expected project duration T e and identify the critical path

11/02/09 Chapter 7-Project Planning 40 Determination of Critical Path for PERT Example Calculation Table 7.5

11/02/09 Chapter 7-Project Planning 41 PERT Critical Path Fig. 7.16

11/02/09 Chapter 7-Project Planning 42 Probability of Completing Project by Specified time T s  Calculate the variance of the project duration as the sum of the variances of the activities on the critical path  Use the standard normal variable z to find the probability of completing the project in a specified time T s  For T s =20  From Table 5.1 Pr (z < -0.57) = 0.285

11/02/09 Chapter 7-Project Planning 43 Space Station PERT Problem Fig. E7.5.1(a) This image is not yet available

11/02/09 Chapter 7-Project Planning 44 Activities for Space Station PERT Problem Table E7.5.1(a)

11/02/09 Chapter 7-Project Planning 45 PERT Diagram for Space Station Project Fig. E7.5.1(b)

11/02/09 Chapter 7-Project Planning 46 Summary of PERT Calculations for Space Station Project Table E7.5.1(b)

11/02/09 Chapter 7-Project Planning 47 Another PERT Example Problem*

11/02/09 Chapter 7-Project Planning 48 Probability of Completing Project by Specified time T s *  Calculate the variance of the project duration as the sum of the variances of the activities on the critical path  Use the standard normal variable z to find the probability of completing the project in a specified time T s  For T s =30  From Table 5.1 Pr (z < 1.48) = 1 - Pr (z < -1.48) = = 0.932

11/02/09 Chapter 7-Project Planning 49 CPM Diagram with Nodes Numbered Fig. 7.17

11/02/09 Chapter 7-Project Planning 50 Calendarized Version of Network Diagram Fig. 7.18

11/02/09 Chapter 7-Project Planning 51 Activity on Node Network Diagram Fig. 7.19

11/02/09 Chapter 7-Project Planning 52 Refined Activity on Node Network Diagram Fig. 7.20