PIP Update Sept. 18 th 2013. Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Pat.

Slides:



Advertisements
Similar presentations
PIP and the Booster Notch Bob Zwaska October 12, 2011 PIP Meeting.
Advertisements

PIP Update Oct Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken Domann.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update July Agenda Summary Update – Budget/RLS – Current Activities – Upcoming Activities/ Changes Update Slides High-Power Ferrite TestingDennis.
PIP Update June 26 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
PIP Update Aug 15 th Agenda Summary Update – Current Activities Dennis Barak / Kiyomi Seiya - High-Power Ferrite Testing Ryan Crawford - Linac and.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
PIP Update Aug 22 th Agenda Summary Update – Current Activities Updates/Talks: – Elmie Peoples-Evans - Schedule Reports – Rene Padilla - Booster.
Proton Improvement Plan (FY13 PMG Q4). William Pellico, Fermilab PMG, Nov PIP FY13 Q4 Summary Task Highlights Budget and Labor Review Summary.
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
Fermilab PIP Booster Accelerator RF Cavity Refurbishment Matt Slabaugh ARW April 2015.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Proton Improvement Plan (FY12 PMG Q4). William Pellico, Fermilab PMG,October FY12 Summary Q4 Task(s) Summary – Highlights RFQ Injector Budget.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Proton Improvement Plan (FY13 PMG Q1). William Pellico, Fermilab PMG, January FY13 Summary Q1 Task Summary – Highlights RFQ Injector Budget.
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
PIP Update Feb 11 th Agenda Summary Update – Current Activities – Updates (Tom Kubicki) – Additional Meetings/Notes.
PIP Update Jan Agenda Summary Update – Current Activities – Updates (Ken, Pat and John) – Additional Meetings/Notes.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Proton Improvement Plan Bob Zwaska July 7, 2014 All-Experimenters Meeting.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
PIP FY14 PMG W. Pellico 7/8/14 7/8/2014PIP PMG. PIP Activities RIL & Linac – 200MHz RF Power System High Level RF Linac Modulator 7835 Procurement – Accelerator.
PIP PMG Project Controls Elmie Evans-Peoples PIP PMG Oct 25, 2012.
Proton Improvement Plan Accelerator Sector Planning and Strategy Oct. 27 and 28 W. Pellico Bob Zwaska, Keith Gollwitzer, Fernanda Garcia Valery Lebedev,
PIP Wednesday April 10 th, /4/12 Agenda Project Update(s) Pellico - PIP Status Talk(s) 1.None –(Review Status Report Effort)
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
PIP Update Oct Agenda Summary Update – Current Activities Updates/Talks: Dave Johnson – Linac Notching (laser)
PIP FY15 PMG W. Pellico PIP PMG March 5 th PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.
Refurbished Booster RF John Reid October 24, 2012.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (Joe Compton - shutdown) – Additional Meetings/Notes.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 07/01/2013.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Proton Improvement Plan Overview Bob Webber July 13, 2011.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Alexander Valishev - Simplified Modeling of Space Charge Losses in Booster.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Proton Improvement Plan William Pellico 44th Fermilab Users' Meeting June 1-2, 2011.
Proton Improvement Plan (FY13 PMG Q3). William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary.
PIP Wednesday March 21, /21/12 Agenda Project Update(s) Pellico - PIP Status Talk(s) 1.Ryan Crawford: Linac Power Distribution - Shutdown 2012 activities.
PIP Update April 10 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Eliana.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Proton Improvement Plan (PIP) William Pellico Fermilab Annual Science and Technology Review September 5-7, 2012.
PIP Update April 3 rd Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
PIP Update Dec 17 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
PAC Meeting, December 12, Prebys 1 The Problem.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update May 28 th Agenda Summary Update – Current Activities/Updates – Ken Domann.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
PIP Update Sept Agenda Summary Update – Current Activities Updates/Talks: Ken Domann - Schedule Update and Statusing Ryan Crawford - Linac MCC/Transformer,
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Presentation transcript:

PIP Update Sept. 18 th 2013

Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Pat Sheahan - Plans for new Ferrite Measurements and Tuner Integration Dan Bollinger - Source Development

Update General Info – PreAcc Beam: RFFQ Driver PA changed – looks much better – Linac Beam: General Tuning – Booster Beam: Tuning – beam for HEP (When source is behaving – ~4E turns -> MI – Studies still underway: Transverse damper studies – not yet started – need to put system back together Cogging software work continues – old system used in operation Booster orbit smoothing – looks fine except for L22 (suspect misalignments) Booster optics software – meeting next week to work out study plan Booster Longitudinal dampers –software effort just starting, new boards? – Booster RF cavity rework Cavity from RF17 reinstalled yesterday – had a vacuum issue Booster RF19 tuner work underway – cavity on lathe getting ready for re-facing of inner flanges RF8 removed last week because of RF leakage (this was the first refurbished) is in test area – There is some evidence of arching on back tuner Spare Cavity Work – brazing plans? – Booster Ferrites (Talk today by Pat on first batch of low mu cores) Were due 2 nd or 3 rd week of July – – Low Mu cores 60 on 8/23 ship 9/11, 60 on 9/6 ship 9/18 and 76 (balance) on 9/27 ship 10/3 – High mu cores – we are preparing a response before the next batch is made – HLRF – PO all signed off – but issues with purchasing agreement CPFF is causing issues!!! Looking into an alternate SBK design Releasing spec to CPI for SBK – looks very promising – Linac Modulator - testing continues (HV probes being purchased to allow for testing) – Booster Shielding – Discussions on how to proceed with beam based measurements and MARS – Short Kickers under test (Hardware of kicker PS is progressing – maybe a status talk?)

Recent PIP Budget/News Supplemental Funding – approved and nearly spent Several items still in bidding process - Budget Issues – Submitted FY14 labor and Budget – Labor plan is in place – entirely expect it to change – PIP 11 M FY14 budget uploaded – New director has not given any signal to PIP to slow down or change course (setting up meeting for Nigel tour of PS) Labor Issues – We have not had the expected labor on a few parts of PIP – Cavity refurbishment is the most glaring shortfall MSD techs are supposedly available – waiting upon Matt for guidance Looking into other options to move this process along -Please use the E-Log to put general work in progress updates/photos – weekly would be nice – if progress is being made in task -Need to post

Upcoming Talks Sept 18: Dan Bollinger - Source Development Future Meetings to be Scheduled: Kiyomi – Booster cogging plans Eddy – Booster damper plans Bill Pellico - Loss Scans and Shielding Assessment Jon Reid - Solid State Installation - Final Report Tan – RFQ Summary (after install of corrector and source B operating)