November 15, 2003Bill Wisniewski1 Introduction Brief Status of LST project QA Review Mechanical, Schedule and Cost Review.

Slides:



Advertisements
Similar presentations
Module Assembly Update Ohio State University and Princeton University are presently preparing facilities for module assembly. Both universities are fabricating.
Advertisements

Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
1. 2 RE Case Study What was the Project Objective? When did it all Start? What was the Plan? How did Negotiations take place? What were the Benefits of.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Limited Streamer Tubes for the IFR Barrel Installation Review SLAC, Oct 21, 2003 Stewart Smith INFN: Ferrara, Frascati, Genova, Padova, Roma, Torino US:
IFR-LST status report G. Cibinetto INFN Ferrara Babar Collaboration Meeting, Feb. 21, 2004 Milestones LST production status 1 st module assembled Princeton.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2005 IR-2 Installation Discussion H.J. Krebs October 22, 2003.
BaBar: The Detector Richard F Boyce 21 October 2003.
May 5, 2004H.J. Krebs LST Installation Readiness Review 2004 IR-2 Installation Schedule H.J. Krebs May 5, 2004.
March 23, 2009H.J. Krebs1 BaBar D&D Schedule & Budget Overview H. James Krebs March 23, 2009.
May 4, 2004Bill Wisniewski1 Installation Review. May 4, 2004Bill Wisniewski2 Charge ( W. Althouse, G. Bowden, W. Innes(chair), J.Weisend, (D. Nelson))
October 22, 2003H.J. Krebs1 LST Mechanical Design Review Mechanical Installation Preparation H. James Krebs October 21, 2003.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2004 IR-2 Installation Schedule H.J. Krebs October 22, 2003.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
Release & Deployment ITIL Version 3
IFR End Door Enhancement Mechanical Engineering Status & Installation Issues H. James Krebs June 23, 2001.
From Research Prototype to Production
October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and Fabrication Status H.J. Krebs October 10, 2003.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Page 1 BaBar IFR Mechanical, Schedule Cost Review Outbriefing (1) Excellent job on preparing and presenting review Overall, the Committee feels that the.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
LST SAFETY INSTALLATION READINESS REVIEW 5/5/2004 FRANK O’NEILL (SLAC)
LST Upgrade LST Upgrade Readiness Review William Sands, Princeton University,
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
Tracker SSD Ladder Preproduction Review Actions and Changes Since Last Week September 16, 2002 Alessandro Brez Robert Johnson.
9 September 2004The Straw Tube Chamber1 The CDC Curtis A. Meyer Carnegie Mellon University Physics Requirements and Specifications Prototype Construction.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Management’s preliminary comments to the ERC Report FINANCE COMMITTEE June 19, 2002.
Proposal for LST-based IFR barrel upgrade Roberto Calabrese Ferrara University Workshop on IFR replacement, SLAC, 11/14/2002.
CLAS12 Drift Chamber Prototyping
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
Quality Control QC is taken very serious QC Document for Tube Production QC Document for Module Assembly QC Document for Installation.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
Continual Service Improvement Methods & Techniques.
1 R&D status report of LST technology (2) Changguo Lu Princeton University BaBar IFR Workshop SLAC, December 8, 2002.
LARP Review, June 12-14, 2006 Prebys, Todesco, Zisman 1 Accelerator Systems Eric Prebys Ezio Todesco Mike Zisman.
LSTs in the IFR gaps Workshop on IFR replacement SLAC November 14, 2002 L. Piemontese INFN Ferrara.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
May 31, 2010Bill Wisniewski1 Mechanical Integration Issues.
Integration Prototype1 BaBar Integration as a Prototype for SuperB Bill Wisniewski SuperB Workshop at LNF 6 April 2011.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
Comments on Services Elba Comments on Services & … Bill Wisniewski SLAC.
Director’s Progress Review Closeout Meeting
DNP Initiative ENG-003 Standard Design Process Overview Configuration Management Benchmarking Group June 12, 2017.
Introduction BaBar Components The Problem IFR Upgrade: 2004 & 2005
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
BaBar LST Upgrade Mark Convery SLAC 13 Jun 07.
Bill Wisniewski SuperB Frascati Meeting September 30, 2010
Renovation of the 45-year old PS magnets
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
LST Module Installation
Director’s Progress Review Closeout Meeting
RPC and LST at High Luminosity
Limited Streamer Tube Project Summary
as a prototype for Super c-tau factory
DOE Review of the LCLS Project October 2006
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Presentation transcript:

November 15, 2003Bill Wisniewski1 Introduction Brief Status of LST project QA Review Mechanical, Schedule and Cost Review

November 15, 2003Bill Wisniewski2 Single-layer large cell (15x17 mm) Read out φ with wires, z with strips Test Tube in BaBar shows wires give better φ resolution, lower multiplicity than φ strips Negligible capacitor failure rate Graphite- Coated PVC LST Design

November 15, 2003Bill Wisniewski3 Test Tubes in BaBar These have been extremely useful in defining the final readout configuration Front-end HV circuit Obtained geometrical efficiency: 5600 V

November 15, 2003Bill Wisniewski4 Readout Configuration (I) Location of HV bypass capacitors is important, as they form part of the circuit for terminating the signals on the wires to ground. Tests in BaBar show that the circuit should be located close to the tubes Improved coupling to the wire-strip transmission line. Isolation of the HV cable (10-20 conductor) Reduction of the effective capacitance of the cable/power supply Capacitors are reliable enough: less than.2 failures per year expected (.02% of whole detector)

November 15, 2003Bill Wisniewski5 Readout Configuration (II) Placing the capacitors on the detector makes it possible to read out the wires. Advantages: Larger-amplitude signals Lower multiplicity Elimination of phi strips (some cost saving) Allows using lower-resistivity graphite, which should translate into better reliability.  Modifications to existing spec’d hardware very minor. Wire readout adopted.

November 15, 2003Bill Wisniewski6 LST Production (I) Extrusions: Tests in September. Specs met after 2 weeks work. Full production now complete, all tubes at LST assembler’s factory (PHT). Tube components (endcaps, wire holders, etc): preproduction samples obtained three weeks ago. Changes made. Production started this week. Enough parts on hand 11/17 for LST stringing to begin.

November 15, 2003Bill Wisniewski7 LST Production (II) Facilities at PHT: clean areas readied; tooling adapted for BaBar cell size (includes machines for cleaning and painting extrusions, wiring). Painting of extrusions has begun. LST team develops in-house strip production facility, eliminating a potentially unreliable commercial operation. New technique gives better performance, removes concerns about schedule and Q/C associated with the vendor.

November 15, 2003Bill Wisniewski8 Dec BaBar chooses LST for IFR Upgrade June EPAC Review Approves LST Proposal June Cost/Schedule/WBS prepared June INFN Gruppo Uno Evaluation (Resources!) June BaBar IFC Approves Project (Resources!) June Large/Small Cell Decision July Electronics Design Review (pass) Aug 1 -- Place Orders for Tubes & Small parts Aug Q/A Review Sept 3 -- Fire safety approval for materials (tubes, strips, cables) Aug Install Test Module into BaBar Oct 1 -- Decide to read out Phi via wire signals instead of strips Oct 1 -- Final design for “small parts” Oct Mechanical, Schedule (Installation) & Budget Review Nov 5 -- Module Design Complete Nov Tube Production begins! Begin fab of shipping boxes Nov Orders placed for components: electronics, crates, HV system, signal cables, HV cables Milestones successfully passed

November 15, 2003Bill Wisniewski9 Dec 1 Z-strip production begins Dec 18 First shipment (~5%) of tubes to Princeton/OSU All materials for module assembly in Princeton/OSU Jan 6 ’04 Q/C systems operational at OSU, Princeton Module assembly begins. Feb 1 HV system shipped to Princeton Feb 15 Tubes for 2 sextants shipped to Princeton/OSU Mar 1 Crates complete Mar 1 Electronics tests begin Mar 15 5% of modules shipped to SLAC Mar 15 Q/C system operational at SLAC Apr 1 Installation tooling complete: Installation Readiness Review Apr 1 Electronics complete Apr 1 Production, Q/C complete at PHT; Apr 1 Gas system assembled, under test at SLAC Apr 15 Electronics, crates, HV shipped to SLAC May 1 All tubes shipped to OSU/Princeton May 1 Ship Modules for 2 sextants to SLAC May 15 Q/C begins at SL:AC July 20 Modules for last 4 sextants assembled at OSU, Princeton July 31 LST system construction complete Aug 1 Installation of 2 sextants begins July 2005 Install remaining 4 sextants (ready earlier) Remaining Milestones

November 15, 2003Bill Wisniewski10 Absolutely crucial to get this right! Q/C procedures at Pol.Hi.Tech. (PHT) Test equipment supplied by INFN in place at PHT. Tube acceptance criteria agreed upon – Stated in PO. Q/C and long term test procedures at US sites has been designed. Team and procedures in place – 3 Q/C shifters/day. C. Lu and two Princeton students at PHT to become expert, and then work on Q/C at Princeton and OSU during module assembly. Quality Control

November 15, 2003Bill Wisniewski11 Barcode labeling Inspection of profiles Mechanical Graphite coating Resistivity Measurement Inspection of jackets, endcaps, circuit cards Gas tightness (leak test) Wire check Wire-cathode distance measurement HV conditioning and plateau measurement Long range tests Scope of Q/C Activities at PHT

November 15, 2003Bill Wisniewski12 QA Review Reviewers: Jaroslav Va’vra (chair); Giorgio Maggi; Darren Marsh Limitation: working to a tight schedule during late July & August: vacations, closed departments, etc. versus need to have the QA plan in place by September Are you satisfied that the LST team has a credible QA Plan? Process: LST team completes QA plan and distributes it to reviewers Aug 6 (17pages) Reviewers read plan, submit comments for changes, questions for clarification LST team amend plan by Aug 18 Caucus for second round of comments, questions if needed Teleconference with presentations, etc., if needed, last week August Comments from committee follow.

November 15, 2003Bill Wisniewski13 QA Q & A The reviewers had ~30 questions requiring detailed responses. These were concerned with, among others: Appoint a QA czar? Level of clean room required? Wire cleaning? Wire tension test? Extrusion straightness test? Material coupons for paint? Damage from probes for resistivity measure? Radioactive source test? Aging & amplifiers? Avoid changes from past experiments… PVC extrusion company experience? Preproduction issues? Czar? Gloves? Why so many resistivity measurements? Gas tightness? Shipping box details? Transportation damage checks issue. Post clean room requirements. Problem resolution? Stringing. PCB soldering check? Strip rejection? Spec values rather than ‘small or zero’. Control of glues and epoxies. Decide to proceed ?

November 15, 2003Bill Wisniewski14 QA Reviewer Signoff Opinion of three reviewers that the QA plan plus the Q&A satisfied them that QA was adequate : “…the answers provided show that the questions were taken seriously…These people are very experienced.” “ I have reviewed the responses to our comments and questions and believe the LST Manufacturing Team has a good handle on the process controls needed to ensure requirements are met.” “As far as I am concerned, I am quite satisfied…I have learned that ….the company involved has great experience. That there is a person named to be in charge of production and QC…That the production rate will be low initially and there is a plan to QC the tubes produced and review the results early…’clean room practice’ … is accepted.”

November 15, 2003Bill Wisniewski15 Mechanical, Schedule & Budget Review BaBar Barrel IFR Upgrade Mechanical, Schedule and Cost Review Charge to the Committee (W. Althouse, G. Bowden, G. Deis (chair), F. Raffaelli, J. Weisend) The BaBar Instrumented Flux Return (IFR) system consists of the return yoke of the superconducting solenoid magnet along with instrumentation used to detect the passage of particles (μ’s, π’s and long-lived neutral kaons). The steel is arrayed in sextants consisting of 18 layers of steel with thickness increasing radially outward. Resistive Plate Chambers (RPCs) constitute the sensors located in the slots between the steel layers. The performance of the RPCs has been decaying since the start of the experiment. The performance in the barrel has now decreased sufficiently that the sensor elements must be replaced. The problems that have been found with the ‘monolithic’ RPCs have led BaBar to choose a better understood and more robust sensor technology, Limited Streamer Tubes (LSTs), to replace them. It is expected that this more modular technology will last reliably through the balance of the decade. The barrel RPC system has 19 layers of sensor. The outermost of these layers can not be accessed. In order to more than compensate for the loss of the last layer of steel absorber, six of the gaps between the steel plates will be filled with brass.

November 15, 2003Bill Wisniewski16 Charge (cont’d) Access to the RPCs is limited by the array of steel that covers the ends of the barrel and provides a connection path from the barrel to the endcap for the magnetic field. In order to remove the RPCs, these parts of the barrel structure which have been in place since the construction of the experiment will need to be removed. Engineering studies have been conducted to understand the stability of the barrel structure under the increased load from the brass while the structure is partially disassembled. Four of eight magnet vessel restraints will be disconnected during the first phase of the installation, when the top and bottom sextants will be upgraded. The four supports for the barrel calorimeter are attached to the steel corner blocks. Two of these blocks will be removed during the second phase of the upgrade, requiring a transfer of the calorimeter load. Please evaluate the adequacy of the engineering studies performed thus far. Are they moving in the right direction in cases where they are not yet complete? Can we put the detector together again? Tooling and platforms will be needed for removal and restoration of the steel, for insertion of the brass absorber, and for the installation of the LSTs. Please comment on the status of the design of these items, as well as mechanical design of the LST modules. The sensor elements will require services: gas, readout cables, high voltage system. Is the plan for integration of these services on the BaBar detector adequate? Are safety considerations receiving sufficient attention?

November 15, 2003Bill Wisniewski17 Charge (cont’d) The installation of the LSTs, brass and services is expected to be a complicated task. Installation plans have been developed. Manpower estimates have been made based on schedules which aim to minimize downtime, since BaBar is engaged in competition with another experiment. The schedule for summer 2004, when the first phase of installation will occur, is driven by the desire to match as closely as possible the normal two month machine shutdown. In 2005 the second phase of barrel upgrade will take place, as well as repairs to the Silicon Vertex Detector and upgrade of beam line elements also contained with it in the support tube. Due to the complexity of this multi-system upgrade, it is expected that it will take significantly longer. The 2005 schedule is less mature than that of Please comment on the installation plan. Does the manpower estimated appear adequate? Is there enough float in the 2004 schedule, or is it a very success oriented schedule? Is the time estimated to be needed in 2005 adequate? Finally, please consider the cost estimates and WBS for this upgrade. Please comment on their maturity and adequacy. Please provide your preliminary feedback via a closeout session on the afternoon of the second day of this review, with a written report to follow.

November 15, 2003Bill Wisniewski18 Project Review Agenda Introduction & Charge Mech/Elect Engineering & Design Manpower & Org Chart Overview of BaBar Steel Design Brass Absorber Design Earthquake Analysis Mechanical Engineering Analysis LST Schedule & Milestones LST Design Handling & Installation Fixture Status EMC Load Transfer Fixture Installation Platforms & Positioners S.C. Solenoid Issues LST Gas System Utility Routing, Cableways & Crate Locations LST Storage and Testing Hazard Analysis & Safety Oversight WBS & Cost Estimate Mechanical Installation Preparation 2004 Brass Absorber Installation LST Installation, Connection & Checkout IR-2 Installation Manpower & Org Chart 2004 IR-2 Installation Schedule 2005 IR-2 Installation Discussion

November 15, 2003Bill Wisniewski19 Committee Report (I) We now have a draft report from the committee. The format of the report is General Comments, Response to Specific Questions in the Charge, and a Summary of Specific Recommendations. Extracts of the General Comments follow: The Committee would like to thank the project staff for their efforts in preparing and presenting this review, and commend them for their excellent work in the project thus far. The BaBar Barrel IFR Upgrade presents some unique engineering challenges, and the team has done a very good job of identifying and addressing them. Overall, the committee feels that that a great deal of good work has been done, that the project is on track, and that it will be successfully completed. From a technical standpoint, the project is solid, and there are no technical show-stoppers. All of the major technical risks are identified. For the 2004 installation, all of the major technical risks are resolved, and the team is making good progress in hammering out the remaining details. For the 2005 installation, some technical risks remain, particularly the method of transferring the EMC load onto temporary supports. There is adequate time to resolve these remaining issues and to incorporate the lessons learned in the 2004 installation.

November 15, 2003Bill Wisniewski20 Committee Report (II) The overall schedule for the project appears sound. The schedule for the 2004 installation is very well-done for this stage of the project, with an excellent level of detail. However, the 2.5 month duration for the 2004 installation is extremely success-oriented. Some of the assumptions the schedule is based upon are quite uncertain. Nevertheless, the committee feels that it is a reasonable aggressive planning goal that will help focus the attention of both the project and SLAC management on the schedule risks. Continued discussion between the project and SLAC management, and proactive decision- making by both, will be necessary to properly prioritize shutdown activities to avoid significant slips beyond this goal. The WBS and cost estimate are also very well-developed, and appear to be reasonable and without padding... There are three key areas which the Project should focus on, in order to reduce the overall project risk as it moves forward:

November 15, 2003Bill Wisniewski21 Committee Report (III) First, project leaders should place more emphasis on technical and programmatic coordination across the entire project, including LST production and installation… Second, project leaders should work closely with SLAC management, and clarify the key schedule risks and tradeoffs… There are also several key tradeoffs that can be made (such as the tradeoff of number of sextants upgraded in 2004 vs. the downtime required for the upgrade)…. Third is the need for more formal safety planning. The circumstances of the installations in 2004 and 2005 present a significant risk of accident. Early, detailed, safety planning is needed to ensure adequate personnel training and full-time coverage by safety officers on all shifts for the duration of the installation….