Rocky Mountain Area Transmission Study Steering Committee Meeting January 13, 2003 RAWG proposed Alternatives.

Slides:



Advertisements
Similar presentations
Lessons from the 2015 SSG-Wi Reference Case Mary Johannis, SSG-WI Generation Subgroup Lead Tom Carr, WIEB Seams Steering Group of the Western Interconnection.
Advertisements

1 Data Work Group WECC - TEPPC Technical Advisory Subcommittee Meeting San Francisco, CA November 28, 2007 Jamie Austin PacifiCorp Progress Report: 2007.
BAL-002-WECC-1 Contingency Reserves
Brookfield Renewable Energy Group. Focusing on Renewable Power Generation and Transmission Conceptual discussion how to integrate renewable resources under.
Rocky Mountain Area Transmission Study RMATS Economics Economic Comparisons Preliminary: Distribution of Gains and Losses RMATS Steering Committee July.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
New England’s Regional Renewable Resource Development Efforts New England States Committee on Electricity November 3, 2011.
Concentrating Solar Deployment Systems (CSDS) A New Model for Estimating U.S. Concentrating Solar Power Market Potential Nate Blair, Walter Short, Mark.
WESTERN ENERGY INFRASTRUCTURE ASSESSMENT Energy Infrastructure Policy Group Office of Energy Projects Docket No. AD Item A-3 July 23, 2003.
Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission Study Presentation to National Wind Coordinating Committee June 22, 2005 W Grivna, PE.
1 WGA Clean and Diversified Energy Advisory Committee Briefing Brian Horii Energy and Environmental Economics, Inc
WECC PCC Meeting Salt Lake City, UT July 16, 2014.
Hybrid System Performance Evaluation Henrik Bindner, Tom Cronin, Per Lundsager, Oliver Gehrke Risø National Laboratory, Roskilde, Denmark.
2001 & 2002 Energy Preparedness Tucson Electric Power February 16, 2001 Michael Flores, Manager Control Area Operations David Hutchens, Manager Wholesale.
Preliminary Analysis of the SEE Future Infrastructure Development Plan and REM Benefits.
WGG Coal Retirement Case Transmission Repurposed for Renewables.
Utah Schedule 37 Update June 25, Schedule 37 Background Schedule 37 – Published rates for standard power purchase agreements with qualifying facilities.
Energy Business Solutions Michigan IRP Working Group Meeting June 10, 2005.
Rocky Mountain Area Transmission Study RMATS Economics Reference Cases Economic Comparisons Distribution of Economic Gains and Losses RMATS Steering Committee.
Rocky Mountain Area Transmission Study Transmission Projects Recommendations to RMATS Steering Committee June 9, 2004.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
SPP.org 1. SPP: Demand Response and Advanced Metering in Arkansas.
2013 Alternative Transmission Development Robert H. Easton March 17, 2004 RMATS Stakeholder Meeting.
Approach to the Wind Resource Assessment for the Sixth Power Plan Northwest Power & Conservation Council Generating Resources Advisory Committee August.
Variable Generation Subcommittee Paul Arnold and Michelle Mizumori Northwest Wind Integration Forum Technical Work Group October 29, 2009.
Past Studies and Resource Diversity Western Renewable Energy Zones, a joint initiative of the Western Governor’s Association and the U.S. Department.
NGEIR Technical Conference Presentation May 16, 2006.
1 Wind Integration Study Team (WIST) Report to the Northwest Wind Integration Forum Steering Committee January 6, 2010 Jeff Miller - ColumbiaGrid Rich.
Base Case Draft – For Comment Rocky Mountain States Sub-Regional Transmission Study December 9, 2003.
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable.
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
Net Metering Technical Conference Docket No PacifiCorp Avoided Costs October 21, 2008 Presented by Becky Wilson Executive Staff Director Utah.
A Resource Adequacy Standard for the Pacific Northwest Resource Adequacy Technical Committee January 17, 2008 Portland Airport.
Sixth Northwest Conservation & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Northwest Power and Conservation Council Generating.
Proposed Generation Expansion Process For Review and Discussion March 1, 2011.
Resource Adequacy Steering Committee Meeting October 4, 2011.
Kevin Hanson Doug Murray Jenell Katheiser Long Term Study Scenarios and Generation Expansion Update April, 2012.
City of Port Angeles Strategic Planning Workshop for Power Supply June 7, 2011 Scott Corwin Executive Director Public Power Council.
“DRAFT” RMATS 2008 Base Case (To be presented at the RMATS Stakeholders Meeting) March 17, 2004.
Guidance for Utility Adequacy Assessments Steering Committee Meeting January 29, 2010.
Forming a Cost Assignment/ Cost Recovery Team RMATS Steering Committee January 13, 2004.
1 Recommendations Now that 40 GbE has been adopted as part of the 802.3ba Task Force, there is a need to consider inter-switch links applications at 40.
Proposed Analytical Approach - Modeling Phase 3 - Formation of new team December 9, 2003 Steering Committee Presentation.
Rocky Mountain Area Transmission Study Steering Committee Meeting 2013 Case Alt 1 & 2 - Iteration 2 – Test Transmission Solutions Alt 3 & 4 – Iteration.
1 PNW Regional Contingency Resources Resource Adequacy Technical Committee April 6 th, 2011.
Eastern Wind Integration and Transmission Study David Corbus - Project Manager Matt Schuerger (Consultant) National Wind Technology Center NREL Golden,
Rocky Mountain States Sub-Regional Transmission Study December 9, 2003 Generation Additions Strawman.
Base Case Rocky Mountain Area Transmission Study Presentation to Steering Committee February 5, 2004.
Multi-objective Optimization
C A L I F O R N I A E N E R G Y C O M M I S S I O N Integrated Energy Policy Report Workshop Landscape-Scale Environmental Evaluations for Energy Infrastructure.
TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects — The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
Northwest Wind Integration Forum Technical Work Group Meeting October 29, 2009.
Rocky Mountain Area Transmission Study Overall Economics of Alternatives Steering Committee Meeting April 29, SLC.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
2006 Report on the Capacity, Demand, & Resources for the ERCOT Region Technical Advisory Committee June 1, 2006 Kenneth A. Donohoo. P.E. Manager, Transmission.
Regional System Operator Issues Analysis Ron Lehr Western Clean Energy Advocates January 7, 2016.
Respect for the Individual · Humility · Innovation · Excellence · Teamwork · Integrity System Strength/Short Circuit Current Minimum Requirement June 5,
DISTRIBUTED GENERATION ISSUES Technical Issues Non-Technical Issues.
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
2010 Northwest Regional Forecast Resource Adequacy Technical Committee April 22, 2010.
CREPC/WIRAB Meeting April 27, 2016 Salt Lake City, UT Thomas Carr Western Interstate Energy Board Evolution of Grid Planning in the West.
Understanding the Integrated Resource Plan (IRP 2010 Rev 2)
4/23/2018 Steering Committee Meeting 2013 Case Alt 1 & 2 - Iteration 2 – Test Transmission Solutions Alt 3 & 4 – Iteration 1 - Define Congestion.
2017 Integrated Resource Plan
Western Wind and Solar Integration Study Phase 1
Vetting the GENESYS Model
Economic Adequacy Standard
Steering Committee Webinar March 25, 2016
Base on maximum operating wind capacity at end of planning period
Presentation transcript:

Rocky Mountain Area Transmission Study Steering Committee Meeting January 13, 2003 RAWG proposed Alternatives

RMATS 2  Applicable to resource alternatives for 2013 studies  Each new generation project should be modeled in at least one- generation alternative, either as an individual project or as part of a coherent group Generation may be aggregated into coherent groups by fuel type that is within a geographic area. If it becomes necessary to prorate generation capacity, it would be reduced as a group and no individual project would be required to withdraw from the alternative  Wind generation contributes toward capacity as 20% of the nameplate rating (may modify based on NREL study results)  Total capacity within an alternative generation group would be generally equal to the multiple of the load increase (from 2008 to 2013) plus 15% planning margin  A 2013 base or preferred case will not be created, but all the alternatives will reflect a 2013 time frame and will be compared to the 2008 base case RAWG Criteria for Building Alternatives

RMATS 3 Serving Load RMATS load growth (3,900 MW) Generation equal to one times the RMATS load growth from 2008 to 2013, plus reserves. Generation additions based on available IRPs of Rocky Mountain area utilities and balanced with load growth in each state. This alternative is intended to represent minimal transmission. Serving Load RMATS load growth (3,900 MW) Export 2X (7,800 MW) Export 3X (11,700 MW) Generation equal to one times the RMATS load growth from 2008 to 2013, plus reserves. This alternative will be based on generic low fuel cost resources located in the Powder River area and on the RM open range (wind), both from the RMATS new generation list, and may require more transmission. Generation equal to two times the RMATS Load Growth from 2008 to 2013, plus reserves. Generation additions will be based on the RMATS new generation list and judgments by the RAWG. Generation equal to three times the RMATS Load Growth from 2008 to 2013 plus reserves. Generation additions will be based on the RMATS new generation list and judgments by the RAWG. DSM, High Wind RAWG recommended addressing high DSM in 2013 and High Wind in 2008 in the sensitivity analysis. Generation Alternatives for 2013 runs Proposed by RAWG Committee

RMATS 4 Generation Alternatives for 2013 runs 20% of wind nameplate applies toward capacity Designed Alternative 1 based RMATS load growth, IRPs and minimum new transmission; configured incremental resource additions in each state to meet projected load growth plus reserves in that state; major wind in CO-E and SW Wyoming close to load centers. Designed Alternative 2 based on RMATS load growth with a focus on Powder River coal and open range wind (cheaper resource cost) and may require more transmission in the region. Designed Alternative 3 as an export case (incremental resources equal to 2 times RMATS load growth) with additional Powder River (and Utah) coal and open range wind necessitating more transmission for export. Designed Alternative 4 as a larger export case (3 times RMATS load growth) Powder River (and Utah) coal and open range wind necessitating more transmission for export.

RMATS 5  Collaborative, iterative process between RAWG, Transmission Additions, and Modeling Team to formulate alternatives for further, in-depth modeling  Coordination with wind resource advocates on modeling  Determining the level of DSM in the 2013 sensitivities  Determining the technical feasibility of adding 10,440 MW of wind Pending Issues