Environment, Safety and Health

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Transition to Operations Erik D. Johnson, Deputy ALD for Programs Science Advisory Committee April 4, 2011.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beneficial Occupancy Readiness Evaluation Plan Update Brian Heneveld, P.E., CIH NSLS-II BORE Coordinator Conventional.
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction Engineer Convention Facilities Advisory Committee Review.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Authorization Basis Steve Hoey, NSLS-II ESH Manager Project Advisory Committee February 8-9, 2011.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project LCLS NEH ARR John Arthur LCLS Experimental Facilities Division August 11, 2009 Welcome.
1 Roger Erickson 1 Coordination with Accelerator Systems NEH Accelerator Readiness Review Coordination with Accelerator Systems.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project The Instrument Readiness Review Process John Arthur LCLS Experimental Facilities Division.
1 Michael Scharfenstein 1 Environment, Safety and Health CXI Final Instrument Design Review, June Mike Scharfenstein ES&H.
SLAC ES&H Overview Craig Ferguson March Operating Model ES&H Mission Critical Issues Challenges Path forward Topics October 2008.
Mike Scharfenstein FAC Review - November 11, 2008 SLAC National Accelerator Laboratory 1 Environment Safety & Health Status.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Operations Erik D. Johnson, Deputy ALD for Programs NSLS-II Project Advisory Committee February 8-9, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Safety W. R. Casey NSLS-II ESH Manager CFAC 5/8/08.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Readiness Stephen Sawch, Assistant Director for Construction Management Conventional Facilities.
M. Scharfenstein - ES&H Coordinator 8 June 2009
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
DOE-HSS Review of LBNL Science Divisions 10/23/08.
Safety & Project Management by NABEEH JUM’AH. Eye on Safety  Proactive  Reactive.
1 Lawrence Berkeley National Laboratory Integrated Safety Management Systems Review August 8-9, 2006 B erkeley Lab Safety Committee Presentation Paul Blodgett.
LSST Camera Performance and Safety Assurance Plan and Safety Overview Joe Kenny Camera Safety Manager LSST Safety Council Review 18 August 2015.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Role in NSLS-II Operations Marty Fallier Conventional Facilities Advisory Committee Review October 5-6, 2009.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
Environmental Restoration Projects Methods for Safety Culture Realization November 30, 2007.
NuMI DoE Review of the NuMI Project May 2004 ESH, SA, SAD N. Grossman Page 1 ESH, Shielding Assessment (SA) & SAD: Outline SB&O Construction Phase ESH.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement Anthony Guadagni Procurement Manager NSLS-II Project Advisory Committee Meeting December 10.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
1.  Mission: Improve and operate accelerators, support the experimental program, and design and construct new accelerator facilities in an environmentally.
Using ISMS Principles and Functions in Developing an ARRA Readiness Review Process Presented by Linda K. Rogers Assessments & Readiness Programs Manager.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Redundancy Requirements for Critical Devices R. Casey August 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
Why Do We Need The ASO? E. Lessard Collider-Accelerator Department (C-AD) Brookhaven National Laboratory DOE Accelerator Safety Workshop to
Collider-Accelerator Department EBIS Commissioning Accelerator Readiness Review (ARR) Conduct of Operations Administrative Controls Ray Karol May 2010.
January 4, 2007 RHIC II Project Internal Cost Review Ed Lessard ESH D R A F T Project Overview.
1 BROOKHAVEN SCIENCE ASSOCIATES 2009 DOE Accelerator Safety Workshop BNL S-band LINAC Fire Safety Concerns August 19, 2009 A. Ackerman.
James C. Liu 1 and Lawrence S. Walker 2 1. SLAC National Accelerator Laboratory, CA, USA 2. Brookhaven National Laboratory, NY, USA 1. Introduction ANSI.
Independent Oversight Status Report on Workplace Exposure Monitoring ISM Workshop 2007.
1 David Schultz 1 SLAC Self-Assessment Programs meeting ASO Requirements David Schultz LCLS Program Division Director SLAC National.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
Mike Scharfenstein LUSI DOE Review August 19, 2008 ES&H Overview p. 1 LCLS Ultrafast Science Instruments (LUSI) M. Scharfenstein.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
Audits & DOE Walkthroughs ISO and OHSAS surveillance audits August 18 th – 20 th –CD, ESH&Q, and FESS organizations to be audited Software.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
Safety Management Systems Session Four Safety Promotion APTA Webinar June 9, 2016.
Overview of FESHCom Subcommittees Don Cossairt, Radiation Protection Manager, ESH&Q Section October 1, 2013.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Planning for Succession
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
M. Scharfenstein - ES&H Coordinator 14 May 2009
Ian Evans SSRL Safety Office
Integrated Safety and Environmental Management
Environment, Safety and Health
Richard Hislop Construction Safety Coordinator
DOE Review of the LCLS Project October 2006
PROJECT SAFETY Richard Hislop.
Presentation transcript:

Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting February 8-9 2011

Outline Progress since December 2009 Baseline Risks Scope, Staffing Progress since December 2009 Design/Radiation safety, Operations, Authorization Basis, Construction Risks Project Safety Record Recommendation Status Look Ahead FY11 Goals Issues Conclusions

ESH Scope ESH Support for: Design Operations Construction Conventional Facilities Accelerator Systems Experimental Systems Operations Experimental Facilities Experimental Reviews Construction Ring Building LOB’s Authorization Basis Safety Assessment Documents Accelerator Safety Envelopes BORE, Equipment Readiness Reviews, ARR’s

ESH Program Responsibilities Experiment safety review Work planning support Emergency planning Environmental management Hazardous waste management Industrial hygiene Industrial safety Radiation safety ESH Facility & Equipment Design Safety system configuration control Self-assessment Risk assessment Interlock testing (radiation and laser) Tier I inspections Compliance audits Training development Document control Readiness Reviews Construction Safety

Environment, Safety and Health Organization Manager – S. Hoey Deputy – A. Ackerman Construction Safety Lead K. Krasner ESH Design & Commissioning Lead S. Hoey ESH Operations Manager A. Ackerman Laboratory Support Radiation Control F. Zafonte F. Flannigan Industrial Hygiene C. Weilandics Environmental Compliance D. Bauer Construction T. Conrad Readiness Review R. Travis ESH Coordinator L. Stiegler G. Wilson EWH T. Anschutz Radiation Physics P. K. Job Torcon K. Krasner Health Physics W. R. Casey ESH Engineer K. Klaus Readiness Evaluation B. Heneveld Safety Officer B. Chmiel Authorization Basis N. Gmur Safety Engineer T. McDonald COMMITTEES ALARA Committee Beam line Review Committee EMS/OHSAS Committee ES&H Committee ES&H Improvement Committee Interlock Working Group Review Committee PS Directorate Safety Committee ESH Assurance M. Buckley C. Nielson

Institutional ESH Related Support Resources from the Lab ESH and Support Organizations are needed to support the following phases; Ongoing “design review” activities Ongoing operations & construction support (NSLS and NSLS-II) BORE’s Equipment/instrument readiness reviews Authorization Basis documentation development & review ARR’s Commissioning Beam line development & commissioning NSLS-II operations Decommissioning - 725 Transition to Ops

Progress - Radiation Safety Workshop June 22-23, 2010 (third workshop) Participants – ALS, APS, SSRL, ESRF Chaired by Paul Berkvens Outcome: Followed up on recommendations made at previous workshops (3/07 & 4/08) all prior recommendations closed, (15 from this workshop) Provided feedback and lessons learned on workshop topical areas, beam line installation and accelerator commissioning Received Committee’s concurrence that strategies for radiation safety for NSLS-II are sound and moving in the right direction “The committee is highly impressed with the progress that has been made to-date in working and resolving radiation safety issues for design and commissioning of NSLS-II since the last workshop”

Progress - Area Monitors Locations for area monitors have been planned for Linac, Booster, Storage Ring and beam enclosures (~60 units) Area monitors will provide warnings locally and in control room and be interlocked to injection through PPS for high alarms Monitors from 3 prospective vendors have been purchased, installed and tested at NSLS for. Testing included: Comparison between units Determine response to short pulse length radiation during injection Evaluate long term stability of detector and reliability of unit Permit better specification of units for final procurement Two phase procurement: 3 units procured Fall 2010 for Linac commissioning Additional 52 units procured Spring 2011 for Booster and Storage Ring commissioning (award April 2011) Mirion, Apantec, HPI

Progress - ESH Operations NSLS ESH Operations and NSLS-II Operations are now combined Includes significant footprint increase (research and development, assembly areas) 725 – NSLS – 162,156 ft2 (Exp floor = 123,644 ft2) 726 – NSLS - Mechanical Tech Support 3519 ft2 727 – NSLS – Mech/Magnet Measurement 3519 ft2 729 - NSLS Source Development Lab – 8018 ft2 902/905 – Magnet test and assembly, vacuum – 22,690 ft2 703 – Experimental Facilities Division, 9 new labs – 7,360 ft2 945 – Vacuum lab – 4,068 ft2 832 – RF development, magnetic measurement – 7,895 ft2 820 – Front Ends Diagnostics – 5,700 ft2 Risk well understood & Controlled – lab work, mechanical Assembly, chemicals, haz waste etc. Work processes covered by 24 Project Safety Review Forms (PSRF’s) fully implemented

Progress - Construction Safety Contractor performing better than industry average Many programmatic enhancements & best practices; Increased use and detail of PHA’s Increased communications – daily ESH planning mtgs; weekly ESH Mgmt mtgs; monthly ESH group mtgs, schedule and coordination mtgs with ESH. Modified Safety Incentive – workers receive 90% On site medical provider – NYS trained EMT’s Drug screening, pre-employment and post-incident/cause Construction safety assessment – contractor and NSLS-II

Progress-Transition from Construction Laboratory Beneficial Occupancy Readiness Review process will be used Officially turns over sections of facility to allow machine installation Specific NSLS-II BORE Plan in place that; Defines scope Establishes schedule Identifies resources Baseline BORE’s start Feb 2011 and go through June 2012 total of 10 BORES to match construction phases Pre-BORE’s started Nov 1, 2010 (phase walk downs)

Risk Analysis & Management Category Description Risk Ranking Management ESH Construction Minor or major injury or mishap, conventional construction, R&D Ops through technical equipment installation, Prime contractor coordination Medium ESH Construction Plan (HASP); Contractor Pre-qualification; Safety Incentive; Dedicated CSE’s, contractor qualification; work planning & control; communications ESH Design Major change driven by ESH design Oversight or changing regulation (ring bldg and tech equipment) Low (Reduced from Medium) Formal Design Reviews; SME input; Extensive use of Lessons Learned ESH Site Prep-excavation Legacy contamination identified during excavation, protected species impacting construction Retired Extensive site evaluation; Monitoring of protected species Authorization Basis Impacts Possibility of DOE Order 420.2B “Safety of Accelerator Facilities” being rescinded and replaced by more stringent nuclear stds Active participation in ASO working group and gap analysis The ESH risks from the NSLS-II risk registry are all binned into three categories. Design risk is open through commissioning (major after 100% complete), >500k 2-3 months Site prep – complete when all site work and excavation is complete, then retired (20-30k/cleanup overall cost impact 250-500k and 1-2 months Construction is highest risk includes technical equipment installation and gets retired when that is complete, 3-4 million (fatality) 3-4 months

Injury Summary Operations: 3/10/09 Recordable – Technician infection from splinter Construction: 7/16/09 Recordable – sub-contractor moving conduit chipped tooth 9/30/09 DART – sub-contractor broken leg from rebar impact 2/22/10 Recordable – sub-contractor fractured finger tip 4/22/10 Recordable – sub-contractor cut leg with hammer claw 7/26/10 DART – sub-contractor cut palms moving decking 10/21/10 DART – sub-contactor pulled back muscle

Project Safety Record (through December 2010) Hours Worked Recordable Cases Recordable Rate Recordable TARGET DOE (Gen Ind) DART Cases Dart Rate DART TARGET DOE (Gen Ind) NSLS-II Staff pre FY09 341,100 .65 .25 NSLS-II Staff FY09 320,396 1 .62 NSLS-II Staff FY10 432,272 NSLS-II Staff FY11 to date 107,800 NSLS-II Staff Cumulative 1,201,568 .17 Contractors FY 09 60,208 2 6.64 1.8 (4.7) 3.32 .6 (2.5) Contractors FY10 331,424 3 1.81 .60 Contractors FY11 to date 112,411 1.8 Contractors Cumulative 504,042 6 2.38 1.19 Total Project to Date Cumulative 1,705,610 7 .82 .35 DART’s also count as TRC’s for rate calculations

Recommendation Status Continue to evaluate and improve oversight of contractors and subcontractors and their contractor and subcontractor ES&H programs. Closed The project should begin planning now for the required safety readiness reviews (internal) for beam line commissioning. Closed (will cover in later presentation) The renegotiation of the safety incentive on the ring building should be completed. Closed New safety incentive should be included in the LOB procurement. Closed

FY11 Goals Development of the Linac and Booster Commissioning SAD’s, ASE’s and supporting documentation Coordinate the BORE’s for transition to construction and manage findings Develop acceptance and readiness processes for equipment installation Provide ESH support for the radiological safety design of beam lines; design of the supplementary shielding; Personal Protection and Equipment Protection systems Finalize area monitor testing/selection and initiate procurement Maintain improving trend in construction contractor(s) performance and quickly bring the new prime up to a best in class level

Issues Increase in number of beam lines (and BL reviews) Coordination of prime construction contractors (Torcon & EWH) will need consistency of ESH implementation Laboratory resources to support Transition to Operations will need to be managed Increase in number of beam lines (and BL reviews)

Summary ESH Program is well defined and documented ESH Staff is well qualified and in place Performance metrics are trending positively Early deficiencies in construction safety program implementation have been addressed and processes are in place to move forward safely with minimum risk On track with authorization basis process including BORE, SAD’s and ASE’s Program is continually improving & incorporating Lessons Learned