David Lee, FVTX Review Nov 2008 1 Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader.

Slides:



Advertisements
Similar presentations
FVTX Transition to Operations PHENIX FVTX Close Out April 23, 2012 BNL 1 FVTX Close Out Review Ed OBrien April 23, 2012.
Advertisements

L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
3 Oct Cost and Schedule Update Craig Ogilvie, Iowa State University Analysis of system risks Update schedule  Critical path.
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
L. Greiner1PXL Sensor and RDO review – 06/23/2010 STAR PXL Detector Project Status.
FVTX Wedge Assembly WBS to David Winter Columbia University FVTX Wedge Manager.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
TIPP Conference, June 10, Mechanics and Assembly of the Silicon Vertex Detector for PHENIX Walter Sondheim - LANL Mechanical Project Engineer; VTX.
David L. Winter for the PHENIX Collaboration PHENIX Silicon Detector Upgrades RHIC & AGS Annual Users' Meeting Workshop 3 RHIC Future: New Physics Through.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
HvH, DNP Oct The FVTX detector in PHENIX Hubert van Hecke, Los Alamos National Laboratory for the PHENIX collaboration Vtx (Mannel) Fvtx (HvH) RPC.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
U N C L A S S I F I E D FVTX Detector Readout Concept S. Butsyk For LANL P-25 group.
Gerd J. Kunde - LANL1 The FVTX Technology  Outline Overall Picture Silicon Detector –Geometry, Layout, Process Readout Chip –FNAL Chips, New Chip PHX.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 DAQ for FVTX detector Implementation Mark Prokop Los Alamos National Laboratory.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
FVTX Review Nov FVTX Review Homeworks. FVTX Review Nov When is Project Complete; how will it be determined?
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
U N C L A S S I F I E D 7 Feb 2005 Los Alamos RHIC Program David M. Lee Heavy Ion and Medium Energy 7 February 2005.
HFT face-2-face F.Videbaek Brookhaven National Lab.
TOF Project Construction Project Plan
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 17-Nov-2010.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
M. Brooks, LANL 1 02/19/07 Review Schedule The FVTX upgrade project Melynda Brooks Silicon Sensor, Chip, ReadoutJon Kapustinsky Mechanics Walt Sondheim.
03/12/07 Jon S Kapustinsky LANL Jon S Kapustinsky, LANL Forward Vertex Detector Collaboration Meeting UNM, March 12, 2007 Outline: FVTX Overall Description.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
The PHENIX Forward Silicon Vertex Tracker Eric J. Mannel IEEE NSS/MIC October 29, 2013.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
FVTX Review, November 17th, FVTX Mechanical Status: WBS 1.6 Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
Axel Drees, Stony Brook University BNL review of RHIC detector upgrades, March 14 th 2006 Overview of PHENIX upgrades Goals of PHENIX upgrades program.
FVTX Wedge Assembly WBS , , , , , David Winter Columbia University FVTX Wedge Manager.
Aug 2003 Craig Ogilvie 1 Landscape/Goals for R&D  Goal: Barrel+structure ready Summer/Fall 06 (run07)  Goal: Endcaps ready Summer/Fall 07 (run08)  RIKEN.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
Robert Pak, FVTX Annual Review Nov Mechanical Integration WBS Robert Pak Brookhaven National Laboratory.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Cost and Schedule.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Overview Technical Design Overview Design status.
Melynda Brooks, FVTX Closeout Review, April FVTX Project Overview Cost & Schedule Deliverables Melynda Brooks Los Alamos National Laboratory FVTX.
PHENIX Timetable FY 2002 FY 2003 Prepare S  S  with Au-Au beams May 2001 March 2002 Jan 2001 June 2002 Sept st  physics (J/  suppression &
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
Columbia University IN THE CITY OF NEW YORK FVTX Electronics Oversight and Integration Eric J. Mannel Columbia University.
Robert Pak VTX Meeting June 3, Robert Pak 1 VTX Meeting June 3, 2005 General Progress Started general integration meetings for detector upgrades.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Status: R&D: Scientific and Technical Resources Technical Design Overview Design status R&D Cost and.
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
1 HBD: Responsibilities, Cost and Schedule Itzhak Tserruya EC/DC Meeting, BNL, March 9, 2005.
Silicon strip detector R&D issues –readout chip decision –interface with PHENIX –ladder Technical options –SVX4 or MVD-TGV+AMU/ADC recut –other sensors.
B => J/     Gerd J. Kunde PHENIX Silicon Endcap  Mini-strips (50um*2mm – 50um*11mm)  Will not use ALICE chip  Instead custom design based on.
David M. Lee Los Alamos National Laboratory DOE Review of the Heavy Ion Program Agenda Introduction – Joel Moss 1. David M. Lee – KB02 program.
1 FVTX Quarterly/Monthly Report July 2008 Melynda Brooks, Dave Lee.
Melynda Brooks, FVTX Annual Review, November FVTX Project Overview Cost & Schedule Melynda Brooks Los Alamos National Laboratory FVTX Project Manager.
WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.
Page Headline Project Management Cost & Schedule Review Rob Michnoff.
Evidence for Strongly Interacting Opaque Plasma
Conventional Facilities
Presentation transcript:

David Lee, FVTX Review Nov Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader

David Lee, FVTX Review Nov Forward Vertex Detector Cost & Schedule Participating Institutions Organizational plan Changes since Nov 2007 Cost Schedule Talk Outline

3 Los Alamos National Laboratory LANL coordinate work to procure the silicon sensors, work with FNAL on the development of the PHX chip, on development of the interface to PHENIX DAQ, and on the simulation effort with NMSU. Los Alamos is currently leading the mechanical engineering and the integration effort for the barrel detector, VTX, and will continue those efforts for the FVTX. Bhabha Atomic Research Centre Involvment still under discussion Brookhaven National Laboratory Brookhaven manages the integration and ancillary systems for the VTX and will do the same for the FVTX. They might also participate in software and the assembly of the disks and cages. Charles University, Czech Technical University, Institute of Physics, Academy of Sciences, Prague The Czech groups will participate in sensor testing Columbia University Columbia University has major responsibility with the complete wedge assembly and testing. They are also have co- responsibility for the FPHX chip and are active in the software simulations. Iowa State University Iowa State University is currently working on management details with the barrel detector and working on an (funded) SBIR effort for the level one trigger capabilities of the FVTX. New Mexico State University NMSU will be responsible for the FVTX detector assembly, as well as managing and working on comprehensive simulations for the FVTX effort and working on the sensor testing. Saclay Saclay will work on software. Participating and Interested Institutions

David Lee, FVTX Review Nov University of Jyvaskyla Involvment still under discussion. Have indicated that they will contribute students in the assembly and testing University of New Mexico UNM has experience in testing, Q/A and a laboratory for characterization of sensors. They will participate in sensor testing They may also work on the HDI and flex cables. Yonsei University, Seoul, Korea Involvment still under discussion Participating and Interested Institutions

David Lee, FVTX Review Nov DOE Office of Nuclear Physics Helmut Marsiske Federal Program Manager BNL Program Manager Tom Ludlam BNL PHENIX FVTX Project Office Project Manager: M. Brooks (LANL) Deputy Project Manager: D. Lee (LANL) Electronics Project Engineer: E. Mannel (Columbia) Mechanical Project Engineer: W. Sondheim (LANL) PHENIX Management Spokesperson B. Jacak Operation Manager E. O’Brien Upgrade Manager A. Drees Offline Hugo Pereira Software vanHecke,X. Wang LANL,NMSU Simulation X. Wang NMSU,LANL, Saclay Database D. Winter ROC M. Prokop LANL FEM M. Prokop LANL QA S. Butsyk LANL DAQ M. Brooks LANL Sensor J. Kapustinsky/ LANL Sensor Design J. Kapustinsky LANL, Columbia, Czech Sensor QA D. Winter/TBD Columbia, UNM, Czech FPHX J. Kapustinsky/ D. Winter LANL/Columbia FPHX Design R. Yarema FNAL,LANL, Columbia FPHX QA R. Yarema FNAL, LANL Cabling D. Fields UNM Flex Cable D. Fields UNM HDI M. Hoferkamp UNM, Columbia Fibers D. Fields UNM Wedge D. Winter Columbia Wedge Assembly D. Winter/TBD Columbia, NMSU, UNM Wire Bond D. Winter/TBD Columbia Wedge QA D. Winter/TBD Columbia, NMSU UNM Metrology D. Winter/TBD Columbia Integration Mechanics R. Pak BNL Mech Structures D. Lee LANL Assembly Installation S. Pate NMSU Disk Assembly S. Pate/PD NMSU Disk Metrology S. Pate/PD NMSU Ancillary Service R. Pak BNL Cage Assembly S. Pate/PD NMSU Organizational Chart

David Lee, FVTX Review Nov FVTX Cost Estimate

David Lee, FVTX Review Nov WBSitem Base Cost Actual Cost Quoted Cost sensor mask set $51.8k $67k sensor prototype $25.9k $36.9k production sensor $439.2k $381.5k ,2 first FPHX prototype $0 $174k HDI prototype $10.4 $30k 1.6 Final design drawings $67k $67k production wedge backplane $146.8k $63k cage tooling jig $10.7k $7.8k total $751.8 $374.9 $452.3($75.4) Updated Costs in At Year dollars *Costs include burden and taxes

David Lee, FVTX Review Nov Funding and Spending Profiles

David Lee, FVTX Review Nov Project Manpower Fractional Cost 63% 37% 63% Integrated over project

David Lee, FVTX Review Nov Estimated Manpower From Workforce Spreadsheets- covers all scientists, and training for postdocs and students. U.S participants only. From FVTX Project File, does not include contract personnel Ave Tech = $100k Ave Engineer = $200k

David Lee, FVTX Review Nov On Project Workforce Includes contract personnel

David Lee, FVTX Review Nov On Project M&S Costs

David Lee, FVTX Review Nov Risk Mitigation Sensors - “standard” p-n diode, decades old technology - Mini-strips, minimize channel count, control occupancy - uses standard wire bonding techniques HDI - not state-of-the-art, conforms to industry standards more complicated than previously expected, added electrical engineer, simulations FPHX - based on previous successful chips - low power, simplifies mechanical designs, cooling system 1 st prototype very successful DAQ - not state-of-the-art, commercial components, easily integrates into PHENIX DAQ - ROC board is more complex, added expert ECAD designer, simulations Mechanical – room temperature, low power, experienced team Wedge - simple design due to low power, no chips on sensor Cage and Disk - modular designs, not dependent on VTX - simplifies integration

David Lee, FVTX Review Nov FVTX Cost and Schedule Changes Construction start – January 1, 2008 ( 2 st QTR FY08) – Started April 1 DOE Funding – FY2008 FY2009 FY2010 Apr08 $500k $2400k $2000k Added 4 ½ months float on critical path 1 st FPHX MOSIS delayed to June – FNAL designers needed more time Delayed ROC/FEM start to FY2009 – due to funding Sensor prototype start Jun08 – small changes and change in procurement HDI prototype delays – designer availability

David Lee, FVTX Review Nov FVTX Cost &Schedule Issues and concerns HDI prototype delays milestones for system tests and test with FPHX chip HDI prototype is now on critical path 4 week delay in FY2009 for funding start FPHX engineer availability at FNAL

David Lee, FVTX Review Nov FVTX Schedule Calender years NOTE: Includes R&D Schedule Float 4 ½ months

David Lee, FVTX Review Nov FVTX Schedule delay Delayed by funding

David Lee, FVTX Review Nov FVTX Schedule Delay by funding

David Lee, FVTX Review Nov FVTX Schedule

David Lee, FVTX Review Nov FVTX Schedule

David Lee, FVTX Review Nov Current year Funding and Spending Profile

David Lee, FVTX Review Nov Current year Funding and Spending Profile

David Lee, FVTX Review Nov FVTX Component Production Start Dates Sensor2/11/0911 months float* FPHX12/17/094 1/2 months float (on critical path) HDI prototype 1/2/09 4 1/2 months float (on critical path) ROC10/1/096 months float* FEM10/1/093 months float* Cage6/1/099 months float* Wedge2/2/0911 months float* Disk2/2/099 months float* * Float to critical path

David Lee, FVTX Review Nov FVTX Milestones WBS 1.1 DOE construction funds receivedQ3 FY08 WBS Review and approve wedge, disk, cage designQ3 FY08 WBS HDI testedQ3 FY08 Q1 FY09 WBS Sensor prototype testedQ1 FY09 WBS First prototype wedge assembly completeQ1 FY09 WBS PHENIX system test completeQ1 FY09 WBS Review and approve FEM and ROCQ3 FY09 WBS Sensor Procurement completeQ3 FY09 WBS Wedge assembly test completeQ4 FY09 WBS FPHX engineering run completeQ1 FY10 WBS ROC and FEM production completeQ2 FY10 WBS Start endcap assemblyQ3 FY10 WBS Ancillary electronics installedQ4 FY10 WBS Start installation into cage enclosureQ4 FY10 WBS Place wedges on cooling plate completeQ1 FY11 WBS ½ Cage assembly complete Q2 FY11 WBS Install cages into VTX enclosure completeQ2 FY11 WBS Verify functional requirements and Project CompleteQ3 FY11

David Lee, FVTX Review Nov Cost Basis and Status as of October 2008

David Lee, FVTX Review Nov Summary Mechanical 90% design complete FPHX chip 1 st prototype complete and successful ROC FVTX board pre production prototype in design FEM FVTX board pre production prototype in design HDI prototype now critical issue Cost Basis is in good shape Construction and testing complete Nov 2011 Construction Schedule points to FY 2012 as data run

David Lee, FVTX Review Nov Summary WBS No Cost and Schedule Cost$4.88M at year $ R&D neededFPHX, HDI, DAQ Cost Basisvendor quotes and Eng. Est. Cost Contingency28% Schedule Start and Complete 04/01/2008 – 6/29/11 Schedule Contingencyrisk based Risklow (FPHX and HDI moderate)