Supervisor Briefing. There was a LV Cable Strike o/s of 5 Eastcote Rd, Pinner on Friday 10/10/14 at approx. 14:56. The original Excavation was excavated.

Slides:



Advertisements
Similar presentations
EFCOG Electrical Improvement Project Electrical Hazards Awareness Briefing Excavation and Trenching Module 5.
Advertisements

Greater Chicago Damage Prevention Council REQUESTING PERMITS Excavator Responsibilities (Contractual and Municipal) A permit is required for any excavation.
Excavation Lesson 3 M. S. Martin Sept De - Watering The removal of ground water and / or accumulated rainwater from within excavations or earthworks.
Scales Floor Plans Scaling drawings allow us to draw exceptionally large objects such as houses on any size of paper available to us. To enable this to.
CONTRACTOR KILLED IN FALL FROM ROOF WORKING AT HEIGHT Work at height is work in any place at, above or below, ground level, where a person could be injured,
Call Before you dig Safe digging is no accident. Alberta Damage Prevention Council.
Various services have to be connected. Here the sewer is being connected and pipes laid for storm water removal.
NETS Network Upgrade!.  304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed.  255,000 Feet of CAT6A copper.
MINI BOX. STANDARD BOX MAGNUM BOX SPINDLE ASSEMBLY.
Carnell. IEMA, Ireland Regional Event Are SUDS the Answer for Drainage? Dublin, 12th Dec 2007 “Filter Drains as a SuDS System” presented by Andrew Todd,
Hargrave Street Pumpstation – Site Preparation July 2014.
GROUNDWATER CONTROL.
Copyright  Business & Legal Reports, Inc.
1 Armour Ranch Road Bridge Emergency Repairs SB County Project Number 01STRM R015 Storm Damage caused during March 5 th 2001 storm.
Excavation Hazards & Controls. Hazards Collapse of sides zType of soil structure is an important factor zWhat might appear to be a safe soil structure.
Foundation Systems.
Set out masonry structures
1. 2 Safety work-stoppage PDO & its contractors have suffered THREE high potential incidents involving cold cutting in the last TWO months.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
Chapter 18 Foundations.
11kv Cable Strike Case Study
Excavation Instructional Goal: through class participation and discussion, the participant will identify the issues and hazards related to trenching and.
The Investigative Skills Assessment This is a unit of your GCSE done in class which counts for 25% of your final mark. You will carry out a practical investigation.
Outcome 6 Safety requirements for working safely in excavations and confined spaces Unit 201: Health and safety in building services engineering.
Safety in the numbers Working Safely Around Pipelines Dig Safe BC! Workshop: March 2010.
Guide to the TDM online system
Ms. Potter Career Goals September 8, th Block Project Example.
FIRE PREVENTION. Fire Of the many hazards on site or at work, fires are the worst kind. They do a great deal of damage every year.  All fires, however.
Rethinking maintenance SUDSnet International Conference 2012 Multiple Benefits from Surface Water Management 4 th & 5 th September 2012, Coventry University.
The Natural Pool To advance to the next slide, click your mouse button. To end the show, close the window.
1 Direct burial cable, up to 24 individual fibers, reinforced.
Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES This work.
MELBOURNE CRICKET GROUND RECONSTRUCTION Written by Gary Thomas.
Introduction to Spring Development
1 THE LACLEDE GROUP Damage Prevention … a shared responsibility PRESENTER NAME.
Ecosystem Etiquette. Safety You should never work with your back to the water One group should always remain on watch of the sea You should never work.
A Chamber Installations Process Improvement M60 J8 & M62 J19 £228,763 saved Katie Jones, MSM Jonathan Derrick, Mway.
Health, Safety and Environmental Update November 2015 Purpose: The intention of this briefing is to pull together and share both Optimise and other contractor.
Installing Guttering and Rainwater Systems
Site Safety, Health & Environmental Induction. Management Commitment to H&S Operate in accordance with Health & Safety best practice Develop and maintain.
Confined Spaces. Definition: Are large enough that an employee can bodily enter them Are not designed for continuous occupancy. Have limited or restricted.
There was a Problem when making up coupling. Could not properly engage the pipe thread. When struggled to undo the rig tongs, fingers got into wrong place.
Ms. Hobart Career Goals March 19, th Block Project Template.
Gasunie is one of the biggest gas infrastructure companies in Europe. Within the company, we give safety the highest priority; it forms the basis of our.
Working Safely Near Power Lines NOVA SCOTIA ASPHALT USER PRODUCER ASSOCIATION.
Best 20 jobs jobs sites.
Death of Victim Struck by Crane Handling Jig Grave Accident Case in Manufacturing Sector 교육미디어
Excavation & Trenching Awareness Plus
Student name: ………………………………………….…. Course of study: (Please tick)  Subsidiary Diploma(pt)  Extended Diploma(ft)  Diploma (ft Yr 2) Unit 51 Civil Engineering.
Excavation and lifting Excavator: Power driven digging machine Types 1. Hydraulic excavator 2. Cable operated excavator 3. Shovel 4. Draglines 5. Hoes.
Excavation Hazards & Controls.
In Too Deep A CDM Perspective – Acting BEFORE Construction Begins.
TRENCHLESS TECHNOLOGY
Services Campaign In Too Deep.
NORTH TRUNK SEWER REPLACEMENT PROJECT
Leica Detection UK Detecting and Avoiding Buring Services for
The 5S numbers game. 1 1.
The 5S numbers game..
Learning bulletin KCD Thames Valley
Strip Foundations The foundation runs under all the loadbearing walls.
Pier Foundations Piers Suspended floor Ground beam Next slide.
Ensure to use the right tools and equipment for the activity
PDO Second Alert Date: Incident title: LTI What happened?
The 5S numbers game..
Learning bulletin KCD Thames Valley
Cat.
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
Effective communication prevents incidents
Always use a banksman with reversing
How Excavation Companies Help You In Construction Projects In Ooltewah, TN.
Presentation transcript:

Supervisor Briefing

There was a LV Cable Strike o/s of 5 Eastcote Rd, Pinner on Friday 10/10/14 at approx. 14:56. The original Excavation was excavated by another team. The Lanes team on site required the excavation the be extended to allow them room to insert a lining into a storm drain. A second team was sent to carry out this extra works.

The team discovered a 150mm Gully pipe running into the Storm drain with concrete around it.

In the process of removing the concrete from around the Gully Pipe, with an FL22, they struck the LV cable below. LV Cable

What Went Wrong The Team did not carryout a site survey using the CAT4 & Genny because the LV cable had been “Marked Up” by the previous team who excavated the trench.

The Team did not use the use the CAT4 to trace out below the Cable TV Ducts. The Team did not Hand dig to Locate the LV Cable before trying to remove the concrete.

Lessons Learn’t Always use the CAT4 & Genny to survey the site when taking over a Job, started by others Never rely on other peoples Marking Up. When excavating Always Scan below Exposed Cables/Plant. Before knocking out concrete in the ground, Always hand dig 500mm around the concrete to ensure that there are no cables/plant in the immediate Supervisors are to ensure there is a suitable and sufficient handover and exchange of information on site where the gangs change