PMG, Aug 03, 2000 Slide 1 Schedule In preparation Done Started Done Started Half done.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
The Intermediate Silicon Layers detector OUTLINE ISL inside CDFII Why the ISL? Conceptual Design Ladders and Spaceframe Rasnik Online Alignment System.
1 Status of the CMS Pixel project Lorenzo Uplegger RD07 Florence 28 June 2007.
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
The DØ Silicon Microstrip Tracker Frank Filthaut University of Nijmegen / NIKHEF NIKHEF, 4 August 2000.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
4/25/2006 Puneeth Kalavase, UC, Santa Barbara On behalf of US Tracker Outer Barrel group Construction and Testing of CMS “Rods”
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
TMDB delay and production plan Augusto. TMDB Prototype Status The prototype boards almost fully assembled should be delivered this week ( May 5 th ) First.
1 Jim Thomas - LBL 4.2 Meters ~ 1 Meter The SSD: March Face to Face Meeting Jim Thomas Lawrence Berkeley Laboratory March 14 th, 2012 The SSD.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
MDC Silicon meeting 24 July 03 1 Run IIb SiliconTemperature Monitoring  The basic philosophy is to build on Run IIa experience and make only minor changes.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 17-Nov-2010.
PMG, June 15, 2000 Slide 1 Schedule Started ! Done Late Done Done(today)
D0 PMG 12/2/99 Fiber Tracker Status  Carbon fiber work u All support cylinders done u Some work remains on band/support pieces + work for Silicon Detector.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
The Inclusive (Measurement ) FVTX aka iFVTX sponsored by LANL-DR in FY ‘06-08 FPIX Chip Module/Hybrid Testcard Pixel Plane Assembly/Integration.
Mikhail Kubantsev - Kansas State University 1 Assembly of a Large Area Microstrip Silicon Tracker Some Experience of Construction of D0 SMT H- disk Silicon.
1 DT critical items status: HVBoards Control and Trigger Boards Assembly in Torino fgasparini june 2004.
Ronald Lipton Layer 0 Status PMG Sep Status of the Layer 0 Project – emphasis on hardware status, preproduction, and preparations for shutdown work.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
Rev of Run IIb, Nov 4-8, 2002, A. Bean 1 Silicon Management  Organization and Management  Schedule  Resources  Conclusions Alice Bean Univ. of Kansas.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
L. Greiner1IPHC-LBNL Phone Conference 05/2012 STAR IPHC-LBNL Phone Conference News and updated ladder testing.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Cost and Schedule.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Jan. 28, 2014W. Bertl, PSI BPIX Cooling Status W. Bertl, PSI.
Pixel Atsushi Taketani RIKEN RIKEN Brookhaven Research Center 1.Overview of Pixel subsystem 2.Test beam 3.Each Components 4.Schedule 5.Summary.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
L. Greiner1IPHC-LBNL Phone Conference 07/10/2012 STAR IPHC-LBNL Phone Conference News and updated ladder testing.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
R. Lipton Vertex ‘98 Santorini, Greece The D0 Silicon Microstrip Tracker (D0SMT) Outline  Design  Detector Studies Coupling capacitors Radiation Damage.
Run2b Silicon Detector Design goals of Run2b Si system Stave design Silicon sensors Schedule K. Hara (U. Tsukuba)
Pixel Pilot system Hardware Status Simon Kwan August 28, 2012 CMS Pixel Upgrade Workshop, Grindelwald1.
D0 PMG, May 04, 2000 Slide 1 Schedule DØ SMT Status Report.
4 May 2006May 06 PMG - Paul R1 AFEII-t Status May 4, 2006 PMG Paul Rubinov.
Status report on the development of a TPC readout system based on the SALTRO-16 chip and some thoughts about the next step Leif Jönsson AIDA Meeting Vienna.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
DOE CD-2/3a Review of the BTeV Project – December 14-16, BTeV Pixel Detector Pixel Module Assembly and Half-Plane Assembly Guilherme Cardoso James.
SiW ECAL: the status before Fermilab Marcel Reinhard LLR – Ecole Polytechnique CALICE caollaboration meeting 18/03/08, Argonne.
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
1 FVTX Quarterly/Monthly Report July 2008 Melynda Brooks, Dave Lee.
Si Sensors for Additional Tracker
Update on the SVD construction
Radiation Laboratory Meeting
RPC FEE The discriminator boards TDC boards Cost schedule.
Presentation transcript:

PMG, Aug 03, 2000 Slide 1 Schedule In preparation Done Started Done Started Half done

PMG, Aug 03, 2000 Slide 2 Action Triggers p Currently:  6 disks complete  3 barrels complete  Produced 2 disks in the months of May, June and July  Wedge production proceeding at significantly faster pace

PMG, Aug 03, 2000 Slide 3 Sensor Delivery p Axial detectors (3-chip):  All sensors in hand p 90 o detectors, DSDM (6-chip):  ~19 sensors still to be delivered  July delivery: 28 sensors  Complete order in August !  Some sensors will be returned but will have no impact on availability of good devices for completion of detector p 2 o detectors (9-chip)  Still to deliver 19 (lyr2) sensors  Delivery should not be a problem  If we need to call into effect fallback: ~10 sensors »Fallback: Accept sensors which have higher R bias, ~50 sensors have been identified p F-Wedge sensors  All sensors (Micron + Eurisys) in hand p H-Wedge sensors  All sensors in hand   ()()

PMG, Aug 03, 2000 Slide 4 High Density Interconnect Status p 3-chip hdi’s  done p 6-chip hdi’s  done (6 hdi’s to Promex for backup) p 9-chip hdi’s  hdi’s processed at Promex  ~12 sent to Promex. Last batch ! p F-wedge hdi’s  18 hdi’s processed at Promex  22 sent to Promex. Last batch ! p H-wedge hdi’s  20 at Silitronics. Last batch ! p Total to be stuffed:  Promex: ~40  Silitronics: ~20

PMG, Aug 03, 2000 Slide 5 Ladder and Wedge Production p Axial detectors (3-chip):  Ladder production continuing; 4-5 more ladders to go p 2 o detectors (9-chip):  Production lagging due to availability of hdi’s »Surface mount at Promex faster than anticipated »First hdi’s from new batch received at Fermilab and burn-in and production started  Hope to make up some of the lag incurred over the course of the last month p 90 o detectors (6-chip):  Paced by Micron delivery, 136 ladders built so far, 107 A/B grade  Enough ladders for barrel 4  Ladder production should proceed adequately p F Wedges (14-chip):  Production proceeding at adequate pace  Sensor and hdi availability not a problem  Testing sensors is cumbersome p H Wedges (6-chip):  192 half wedges produced to date, 115 A/B grade  Half wedge production proceeding adequately  Glued 64 full wedges of which 33 A/B grade  Encapsulation is slow and tedious process  Enough wedges for first two H disks, enough graded for first

PMG, Aug 03, 2000 Slide 6 Production Status and Projection p Projected rates: assumed yieldcapacity  9-chip: >12.0/week 80% 15/wk  6-chip: 6.1/week 85% 10/wk  H-wedge: 6.2 week 85% 10/wk  F-wedge: 3.4/week 90% 15/wk p Slope for end game for 9-chip ladder production getting steeper ! Nominal completion date for ladder production still early September Nov 1, 00 Aug 28, 00 today

PMG, Aug 03, 2000 Slide 7 Production Rate

PMG, Aug 03, 2000 Slide 8 Production Schedule Summary 2 nd half cylinder “short tails” p Barrel assembly going to be driven by availability of 9-chip ladders p Enough 6-chip ladders available for barrel 4; trying to improve overall quality of ladders p 9-chip ladder production should pick up rapidly so no delay will be incurred

PMG, Aug 03, 2000 Slide 9 F Disk Status The Point of No Return p Disks 10 and 12 assembled  Disk 10 first to be dropped in fallback scenarios p Disk 11 is being assembled; All 6 disks for first half cylinder completed p Thus, it is implicit that there is no descoping of the silicon detector! Any remaining fallback is in scheduling

PMG, Aug 03, 2000 Slide 10 Barrel / Disk Assembly and Mounting p Fixturing proceeding for barrel disk mounting and installation  Barrel Removal Fixture, completed  Barrel / Disk mating fixture, completed  Barrel / Disk insertion fixture, behind schedule  End Disk Assembly Insertion Fixture, behind schedule  Silicon Support Cradle, “tumbler”, completed  ……… p All barrels for first half cylinder done, but  refitting of barrel 1 (grounding)  final surveys of barrels p F disks:  Preparation of central ring of end assembly  Radiation Monitors p H disks  CMM programming complete  Ring assembly started. One side of first ring completed and ring flipped over p Support cylinder  ready

PMG, Aug 03, 2000 Slide 11 10% Test p Interface Board design nearly complete  “Acceptable” solution for cross talk still gives glitches »Need to implement ALTERA FPGA »Still to be tested more thoroughly »Design will then be frozen for first 2/15 production boards  termination of bus lines decided  Controls and Monitoring features of board have been verified  Board submitted for bid; vendor visit this Friday p Interlock and Cooling system setup p Disk F14 installed and being exercised:  run coolant at 55 o F  downloading  biasing  readout  L3 and examine p Plan to shake out system with disk F14 and then move to barrel/disk readout

PMG, Aug 03, 2000 Slide 12 Low Mass Cables p Delivery recently slowed down to 35/wk, whereas 56/wk needed, due to vacation and bereavement  Keeping close watch on production p Enough cables available for first half cylinder