FACILITY NEW BUILD/UPGRADE LONG LEAD ITEMS Craig Lavender - HMNII
TAG (T/AST/077) Covers: CONSTRUCTION, MANUFACTURE, REPAIR, REPLACEMENT, MODIFICATIONS NEW BUILD
LC 17 REQUIRES ADEQUATE QA SYSTEMS WHICH INCLUDES PROCUREMENT + AUDIT OF ARRANGEMENTS
CUSTOMER - SUPPLIER WHERE LICENSEE IS IN PLACE WHERE THERE IS NO LICENSEE YET.
WHAT NII EXPECTS ALL ORGANISATIONS IN SUPPLY CHAIN HAVE ADEQUATE QA ARRANGEMENTS. SUPPLIER SELECTION TECHNICAL SPECIFICATIONS QUALITY PLANS CONTRACT VARIATION CONTROL COMPETENCE IN THE SUPPLY CHAIN DEVIATIONS (NON CONFORMANCE) RECORDS INSPECTION & SURVEILLANCE ACTIVITIES
DIFFICULT REQUIREMENTS FOR LONG LEAD ITEMS TECHNICAL SPECIFICATIONS COMPETENCE IN THE SUPPLY CHAIN
NII INVOLVEMENT ASSESSMENT OF TECHNICAL SPECIFICATION (DESIGN) ASSESSMENT OF CONTRACT ARRANGEMENTS INSPECTION OF CONSTRUCTION/MANUFACTURE WITNESS TESTING ENTRY ONTO Q PLANS