Bulding 245 schedule update LIU Booster Meeting 07-11-2013 Fulvio Boattini TE-EPC TEEPC.

Slides:



Advertisements
Similar presentations
Substation L1/ MCC L1 Update March 21 st, Current Location.
Advertisements

For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
PSB Main Power Supply Serge Pittet Jean-Paul Burnet, Karsten Kahle, Fulvio Boattini, Max Chamiot-Clerc TE-EPC Serge PITTET LIU-2011 Event, 25/11/2011.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Peter Sharp CERN CMS Electronics CMS LV Power System Peter Sharp 7 April 2003.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Power converters implications for Booster Energy Upgrade Jean-Paul Burnet, Serge Pittet LIU day, TEEPC.
PSB MPS Building 245 CV Status EN-CV-PJMichel OBRECHT – Frédéric TEIXEIRA
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
Progress with POPS Jean-Paul Burnet TE/EPC IEFC workshop, Feb 2010.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
IT-4082 Design, Supply, Installation and Commissioning of the ventilation of the BAF3 building Alexandre Broche EN-CV-PJ.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
17/6/2002Ivan Hruska,Francisca Calheiros,Bruno Allongue 1 TILECAL brick development Projected parameters design should fit the volume 160 x 40 x 50mm to.
AD/ELENA (B193) Hall Extension F. Butin. Status The need of a new building for AD was already discussed in 2010, First pre-study shown to GTPE 1st Sept.
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
Thermosiphon project management and quality assurance EN/CV/DC Presentation done by Elena Perez Rodriguez For further information contact
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
ISOLDE: Status report building th ISCC meeting CERN, 24 June 2014 Erwin Siesling, Magda Kowalska.
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 17 th December 2013.
Serge Pittet (Work-Package holder) Konstantinos Papastergiou (Work-unit: Sirius converters) CERN Technology Department | Electrical Power Converters 12.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
PSB Reference Magnet (for the 2.0 GeV upgrade) A.Newborough 16 th October 2014.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
ELENA installation progress F. Butin / ELENA collaboration.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
S A Griffiths CM42 June 2015 Electrical & Control.
POPS-B Project Update 07 June 2016 POPS-B: Project update and Feedback from POPS Experience LIU-PSB Meeting June 2016 Fulvio Boattini TE/EPC 2.
East Area Renovation Project Planning activities Quentin Bouirek / EN-EA, East Hall under construction
Update on the PSB Cooling and Ventilation Systems
YETS & LS2 Works EN-EL / Power distribution
MEDICIS Safety Alarms Systems
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
East Area Renovation Project Team meeting # 2 – EDMS News
CBETA Technical Review
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
EHN1 Extension planning
Collaboration meeting 26 to 28 June 2017
CMS Area Working Group Meeting
Budget specification EHN1 Extension: Infrastructure (WG2)
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
B245 Modifications & Cabling Update
SPS activities during LS2 TE-EPC (Power Converter Group)
YETS & LS2 Works EN-EL / Power distribution
Accelerator Module Test Facility
East Hall under construction
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
5th Review Committee October 4th, 2004 Facilities and Schedule C
Buildings Entrance Tunnel. 5th Review Committee October 4th, 2004 Buildings, Facilities and Schedule C. Sanelli.
East Hall under construction
LINAC 3 Meeting ICL machines Injectors
East Area Renovation Supply of control rooms b.157
Presentation transcript:

Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini TE-EPC TEEPC

Building 245 Position 07/11/2013TE-EPC - Fulvio Boattini2 TEEPC France-Swiss border Limit for edification France Switzerland

Building /11/2013TE-EPC - Fulvio Boattini3 TEEPC Converter1 A (19t) Converter1 B (8t) Trim1 (2t) Converter2 A (19t) Converter2 B (8t) Trim2 (2t) Converter3 A (19t) Converter3 B (8t) Trim3 (2t) ACDC1 DCDC1 QPS1 DummyLoad 1 DummyLoad 2DummyLoad 3 CAPS ROOM CONVERTER HALL MAGNET TEST AREA HVAC HALL CAPS ROOM 2 CAPS ROOM 3 ACDC2 DCDC2 QPS2 ACDC3 DCDC3 QPS3 Stai rs Original DesignWith Booster CV integration

Building /11/2013TE-EPC - Fulvio Boattini4 TEEPC Original DesignWith Booster CV integration Need to find another place for Booster2GeV MPS transformers

Building /11/2013TE-EPC - Fulvio Boattini5 TEEPC ACDC1 DCDC1 QPS1 DummyLoad 1 DummyLoad 2DummyLoad 3 CAPS ROOM CONVERT ER HALL MAGNET TEST AREA HVAC HALL CAPS ROOM 2CAPS ROOM 3 ACDC2 DCDC2 QPS2 ACDC3 DCDC3 QPS3 StairsStairs Booster2GeV transformers. Proposed position Transformer MVCB station ~60mt

physicsLS1physicsLS2physics May 2016 Building Ready No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction Power converter Design & specification Market Survey & Call for tender Power converter Design (supplier) Power converter construction Power converter Installation and cold commissioning October 2013 March 2014 March 2015 FC August 2016June 2014 FC April 2017 Start Commissioning on dummy load Power converter commissioning on test magnets 2 weeks System pre-commissioning on PSB magnets 2months System final-commissioning on PSB magnets Power converter commissioning on test magnets TEEPC MPSB Time Schedule Switching cabinets and cabling installation

physicsLS1physicsLS2physics May 2016 Building Ready No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction October 2013 March 2014 March 2015 FC April 2017 Start Commissioning on dummy load TEEPC MPSB Time Schedule Switching cabinets and cabling installation 3D building model ready by the end of next week EPC & CV generated a document for HSE feedback on safety issues for the building EDMS EPC & CV & EL are working on a electrical requirements EPC working on the switching cabinets and cabling installation EDMS

physicsLS1physicsLS2physics May 2016 Building Ready Building construction Cooling installati on Air conditioning and cooling pipes installation LV cabinets installation. Lights and other services 18kV cabinets installation Cooling and Conditioning operating Lights and electrical cabinets installed Overhead Crane installed Fire alarm system installation April 2017 Start Commissioning on dummy load Old to new MPS switching cabinet installation TEEPC MPSB Time Schedule

physicsLS1physicsLS2physics May 2016 Building Ready No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction Cooling installati on Air conditioning and cooling pipes installation October 2013 March 2014 March 2015 FC LV cabinets installation. Lights and other services 18kV cabinets installation Cooling and Conditioning operating Lights and electrical cabinets installed Overhead Crane installed Fire alarm system installation April 2017 Start Commissioning on dummy load Old to new MPS switching cabinet installation TEEPC MPSB Time Schedule

TE-EPC - Serge Pittet, Fulvio Boattini10 THANKS FOR THE ATTENTION QUESTIONS? Bulding 245 schedule update TEEPC 13/09/2012