Internal review of superconductor and magnet laboratories1 Status of LHC-TB Power Converters Hugues Thiesen TE-EPC.

Slides:



Advertisements
Similar presentations
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Advertisements

Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)
MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
BHEL – Electronics Division, Bangalore
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
CERN 29 Jan 2008 Power Converters for Linac 4 - Carlos A. Martins1 Power Converters for Linac 4 2 Hz) Carlos A. MARTINS Accelerators and Beams (AB)
1 / 19 M. Gateau CERN – Geneva – CH 14th International Magnetic Measurement Workshop September 2005, Geneva, Switzerland.
Strategy for SPS 200 MHz LLRF upgrade (1)  Each of the four cavities (2x 5 sections, 2x 4 sections):  1-T Feedback (loop around cavity and amplifier)
Powering the main linac implications Daniel Siemaszko, Serge Pittet OUTLINE : Cost impact of power converters, power consumption and powering.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
JPV, TB of Nov.15 th, ‘Rack Status‘ Jean-Pierre Vanuxem, PH-AIS.
17.March.2005 C. A. Martins, CERN AB/PO 1 Power converter for the TT2 mercury target project by Carlos DE ALMEIDA MARTINS (AB/PO)
The CNGS Horns Electrical Systems The CNGS Horns Electrical Systems 4th workshop on Neutrino Beams and Instrumentation 7 – 11 November 2003 at KEK Gilles.Maire.
Measurement Control and DAQ for Superconductors and Magnet labs SCLabs Adriaan Rijllart1 Adriaan Rijllart, for the EN-ICE-MTA section.
CSFL upgrade – status report. Purchased parts/ spares Red and white heat shrinks, Kapton tape, flat cable, spare diodes.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
Instrumentation for Magnetic Measurements” Review of Superconductors and Magnet Laboratories, May 2009 Page 1/7 Superconducting.
Electrical & Control Power Supplies Trevor Hartnett.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Bock_DE_Session1_Block1_Question3 Barcelona May 2003 Nexans SuperConductors Dr. Joachim Bock Nexans SuperConductors D Huerth
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 CSCM-7TeV Powering Implementation and ELQA Third LHC Splice Review November 2012 M. Bajko, M. Bernardini, B. Bordini, k. Brodzinski, J. Casas-Cubillos,
Fk. Bordry AB/PO Academic Training - 27th March 2003 Technological Challenges for the LHC Power converters for the LHC Frédérick BORDRY AB-PO ? I(A) t.
A.L.F. Enterprise n Electrical Parameters Measurement Component (EPMC) n Boris Fradkin ©A.L.F.Enterprise Boris Fradkin.
TE-EPC Activities during LS2 V. Montabonnet on behalf of TE-EPC group.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
Review of superconductors and magnet laboratories Summary of measurements and instrumentation issues
Power Quality Karsten KAHLE Electric Power Converter Group (TE-EPC) High Power Converter Section Review of CERN’s Electrical Power Network October.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Actual Circuit Total inductance:15.4 H (154x0.1H) Total resistance:1 m  RB output current:13 kA RB output voltage:190 V Main Power Converter RB circuit.
HTS for Upgrades: overview of test requirements Amalia Ballarino, CERN Review of superconductors and magnet laboratories, A. Ballarino.
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
Technology Department CERN-GREECE INDUSTRY DAY Monday, 31 March 2014 TECHNOLOGY DEPARTENT 2 In the frame of the Accelerators & Technology Sector at CERN,
Review of Sector th of February Tunnel Access During Powering Tests Hugues Thiesen, AB-PO.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Essential Consolidation Items for LIU-PSB Collection from LIU-PSB WP holders.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
28/01/2013 Gerrit Jan Focker, BE/BI/PM 1 Isolde SGIU Beam Instrumentation Remarks on status and possible development.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 T. Mohite and H. Welker LINAC and Operation/ Electric Power Systems GSI Darmstadt Power Converters for the Magnets of Collector Ring in FAIR
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CONS and HL-LHC day Analysis of needs from TE-EPC
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
HL-LHC IT STRING and Series test of SC link
Power converters and circuits
AD consolidation activities in LS2
Experience: past events and accidents
EN 4946 – Refurbishment of Electrical Substations
Powering the LHC Magnets
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
the CERN Electrical network protection system
SPS activities during LS2 TE-EPC (Power Converter Group)
EN-ICE Technical Committee SM18 activities & projects
POPS Strategy for Restarting & Repairing
3 issues identified in review
TEST PLANS for HL LHC IT STRING
Status of RF at HZB: BESSY II, MLS, bERLinPro and BESSY VSR
Review Bloc 4 and SM18 facilities and upgrade
Presentation transcript:

Internal review of superconductor and magnet laboratories1 Status of LHC-TB Power Converters Hugues Thiesen TE-EPC

2 Contents  Inventory of power converters  Status of power converters  AC and CV infrastructures  Client requests  Conclusions and recommendations Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters

3 Inventory of power converters  Power converters have been designed for LHC applications High current (up to 15 kA) and Low voltage (6V to 16V) Main PCs are unipolar in current and Corrector PCs are limited to 600A  40 power converters in 8 different laboratories 4 in Block-4 for diode packs and special magnets  1 x [15kA/25V] thyristor power converter (20kA)  2 x [±600A/±12V] switch mode power converters (CIRTEM)  1 x [±2kA/±10V] modified LEP type D power converter 5 in building 163 for superconducting cables  3 x [16kA/6V] switch mode power converters (Danfysik)  1 x [4kA/8V] switch mode power converter (Kempower)  1 x 1Q with mechanical polarity switch (ISR power converter) 1 in building 180 for Atlas (Out of Service since 2006)  1 x [24kA/6V] switch mode power converters (Danfysik) 1 in building 281 for 600A HTS current leads  1 x [±600A/±12V] switch mode power converters (Transtechnik) Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters

4 Inventory of power converters  40 power converters in 8 different laboratories (cont.) 1 in SM-18 for RF cavities  1 x [100kV/40A] LEP RF power converter 2 in SM-18 for calibration of magnetic instrumentation  1 x [200A/300V] LEP type B power converter  1 x [±600A/±12V] switch mode power converter (Transtechnik) 1 in SM-18 for 13 kA current leads (Out of Service since 2004)  1 x [15kA/16V] switch mode power converters (Transtechnik) 26 in SM-18 for MQ and MB magnets  1 x [15kA/±70V] thyristor power converter (20kA)  5 x [15kA/±16V] thyristor power converter  6 x [±600A/±12V] switch mode power converter (Transtechnik)  6 x [±600A/±12V] switch mode power converter (CIRTEM)  4 x [±60A/±8V] switch mode power converter (LHC prototype)  2 x [±60A/±8V] switch mode power converter (LHC series)  2 x [±120A/±10V] switch mode power converters (LHC series) Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters

5 Status of power converters  Status of power converters 14 different types of power converters Between 10 and 20 years old Prototype PCs or modified PCs  Main issues Number of spare parts is limited  No spare parts for the [±2kA/±10V] power converter in Block-4  No spare parts for the 18kV transformer (special transformer with 2 outputs) used for the [15kA/±70V] power converter in SM-18 (cluster A) Obsolescence of the components  Power semiconductors  Digital electronics End of the lifetime for several devices  MCB for the [15kA/±16V] power converters (MTB in SM18) Difficulties to modify the power converters  It is not possible to modify the internal software for several PCs (LEP)  It is difficult to modify the software of the MTB PCs Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters

6 AC and Water infrastructures  AC infrastructure No problem with the existing AC infrastructures if no additional power converters are requested  The AC infrastructures have been designed for the initial requests only 1 x (2MVA, 400V) switch-board free in SM-18 (String II)  Possibility to install the Block-4 power converters in SM-18  Cooling infrastructure In general, no problem with the existing cooling infrastructures if no additional power converters are requested Limited capacity in SM-18  No possibility of using the 6 MTBs at the same time (max. 3)  Water cooling problem if the Block-4 power converters are installed in SM-18 Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters

7 Analysis of client requests  LHC spares and stock No major problem (limited activity) Main issues  The diode packs can be tested only in Block-4 with the [15kA-25V] power converter (special test bench)  The 15kA power converter of the CL test bench is not operational  LHC operation support No major problem (limited activity)  LHC upgrade phase I Main issues  For this moment the corrector power converters are limited to 600A ([±600A/±12V])  The needs for the string test must be defined  Development requests The requests must be clearly defined  Specifications (maximum current and voltage, accuracy, etc…)  Types of power converters (1Q, 2Q, etc…) Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters

8 Conclusions and recommendations  Conclusions and recommendations The LHC TB power converters have been designed for LHC (max. current is 15 kA). 20kA can be reached in SM-18 (Cluster A) but new DCCTs must be bought. The [24kA/6V] power converter in building 180 and the [15kA/16V] power converter in SM-18 are not operational. The 24kA can be restart but the 15kA must be replaced. The [±2kA/±10V] power converter in Block-4 is at the end of its lifetime and must be replaced. The ISR power converter in building 163 is obsolete and must be replaced. 4 of the 6 [±60A/±8V] power converters in SM-18 are prototype power converters. The replacement of these 4 power converters by LHC power converters (750 in operation) is strongly recommended. All software modifications are difficult or impossible. The replacement of the control electronics (FGC-1) of the SM-18 power converters by LHC control electronics (FGC-2) is strongly recommended. No problem to support a limited activity. If the activity must increase, a PC consolidation must be planed (e.g. MCB of the main PC of the MTB in SM-18) Internal review of superconductor and magnet laboratories - Status of LHC-TB Power Converters