Monday 21.3. 06h00: End of fill #1640: 3.7 pb -1. 06h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
LHC status Wednesday 15 th July 2015 Coordination: Wolfgang Hofle, Mike Lamont.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday September 14th
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Saturday 30th June - Sunday: Rocky !
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Summary of Week 11: 14 – 21 March
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Lost at 12:05 to power converter (RTQX2.R1) problem
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Tuesday Loss maps in the night:
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
Yesterday’s morning’s controls issues
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Thursday Fill 1364 (24 bunch) dumped at 07h
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Tue/Wed 12/ :00 Probe beam back again
Thursday – Morning Energy matching at injection with H CODs
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Thursday 22 September 2011.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Saturday 26th March 9:15 Problem with RB78 temporarily solved. It's running on one Thyristor bridge only and without the active filter LHCb polarity change.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Saturday 26 November 2011.
HI2011 Commissioning Status
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost for both RBs... Piquet called again. 09h18: Ramp down of LHCb and ALICE dipoles and compensators. Ramp down of ALICE solenoid. 09h27: Recovered from RB trips. Prepare for injection while magnets ramp down. 09h50: Problems in PS. Mains down in SPS. 10h30: Total voltage INTLK reduced to 3.5 MV (P. Baudrenghien). 10h33: Injection. 11h49: Start ramp. Beams dumped from false collimator interlock. LHC 8:30 meeting 22/03/2011

Total voltage INTLK reduced to 3.5 MV The RF interlock on the local cavity voltage has been reduced to 3.5 MV (both rings). It was set to ~1.5 MV before. That threshold is constant through the cycle. Tested by Philippe: reduced the total voltage to 3.4 MV. Triggered the beam dump. LHC 8:30 meeting 22/03/2011 P. Baudrenghien

Monday h34: Release of the new FGC software to fix the RF trip problem of two days ago (S. Page). Deploy fix for low level collimator controls software (A. Masi). 13h08: Problem with the ADT: the check for the injection settings is failing. W. Hoefle verifying. 13h18: Injection 136b. Large oscillations at the injection of SPS (PS not stable): larger emittances ( murad-m) with respect to nominal. 14h38: Start ramp. 15h13: Stable beams. 15h13: LHC fast BCT phase tuning done (J.J. Gras). 21h45: Beam dumped by EIC. 21h49: Ramping up LHCb and ALICE magnets. LHC 8:30 meeting 22/03/2011

Collimator Software Issue Worked since last Friday to understand problem that appeared last Thursday: postmortem data, review of the PRS (Position Readout and Survey system) code. Possible source of problem: rare software state with duration 1us during which, if the trigger is received, the first interpolation of the limit functions is wrong providing limits much stricter with a consequent beam dump. Probability estimated to about 10^-4. Higher in reality? Workaround to avoid this case. New software version has been running all weekend on collimator test bench executing successfully a thousand of short profiles (i.e. no dump as soon the trigger were received). After new Monday case: decided to deploy this. LHC 8:30 meeting 22/03/2011 A. Masi

LHC fast BCT phase tuning Reduced significantly the effect of bunch length on measurement (image shows we stay within +/1 % now). Fast BCT cross-calibrated with DC values after ramp. LHC 8:30 meeting 22/03/2011 J.J. Gras

Monday LHC 8:30 meeting 22/03/2011

Luminosity LHC 8:30 meeting 22/03/2011

ALICE luminosity and background LHC 8:30 meeting 22/03/2011

Higher IR2 Vacuum Pressure Magnets Off LHC 8:30 meeting 22/03/2011 IR2 pressure

Monday – Tuesday, 21 – h39: Injection.  injecting difficult: PM from losses at pt 8, up to 94% of dump level.  context missing for XPOC b2 (verified with next dump ok)  the MKI waveforms b2 were not correct once  inj oscillations looked good, asked injectors to decrease intensity/emittance,SPS to increase scraping and verify blow up.  Not verified yet with 24 bunch trains 23h19: SIS/controls problem  No SIS injection permits (IQC, XPOC, PM, vent.doors permits missing)  JMS (Java Message Server)  Experts: connection between the public JMS broker (JMS-PUBLIC- PRO) and the operational JMS broker for TN (JMS-CO-PRO1 & 2)  Still ongoing after intermittent fixes 05h05: BPM controls problem  Trips of BPM crates. Still ongoing. LHC 8:30 meeting 22/03/2011

Ahead Tu am:Fix controls issues. Last 136b fill. Tu pm: Go to 200 bunches. Tu – Wed:Perform 2 fills with 200 bunches. End of fill test of IR8 separation (tbc). Wed pm: Complete commissioning 1.38 TeV. Wed pm – Fri:Stable beams at 1.38 TeV. 80b. Sat am:Switch back to 3.5 TeV Test ramp nominal bunch. Third fill with 200b. Weekend:Commissioning (3h for TL tests, 8h injection test with 96b,...) Intensity step to 250b if time left Monday 6am:Beam stop for TS LHC 8:30 meeting 22/03/2011

Outstanding Injection of 96 bunches (  weekend) Timing distribution (  technical stop) FGC firmware update Collimation system controls fix 1.38 TeV setting-up (  Wednesday onwards)  Crossing angle all zero: OK  TCTs to set up & loss maps Interlock tests for the roman pot (  parasitic or TS) RF voltage limit interlock Longitudinal blow-up (  if needed) Wire scanners Abort gap cleaning (  with high intensity injection) Injection gap cleaning (  with high intensity injection) LHC 8:30 meeting 22/03/2011