TS4 preparatory meeting 11-12-2012. TS4 – weeks 51-52-1 Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

André Augustinus 16 June 2003 DCS Workshop Safety.
EMCal DCS and related Issues with Shutdown/Installation B. S. Nilsen M. Cherney J. Fujita.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
Dimuon Forward Spectrometer May 2008 Cosmic Run Day by Day report Interesting runs.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
winter shutdown preparatory meeting A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
J.Pothier CERN EP/CMIC.Schäfer CERN EP/L3D. J.Pothier CERN EP/CMIC.Schäfer CERN EP/L3D SAFETY J.Pothier (GLIMOS) C.Schäfer (deputy GLIMOS) DISMANTLING.
DCS T0 DCS Answers to DCS Commissioning and Installation related questions ALICE week T.Karavicheva and the T0 team T0 DCS Answers to.
LS1 reference slides LS1 plans Detector’s plans Services and central systems availability 8/2/13LS1 planning meeting - A.Tauro1.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
Active gas system status. S.Konovalov, K.Zhukov. Active gas system operation. S.Konovalov "Active gas system..."TRT Overview  Good design.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
Claudio Bortolin 03/09/2012. SPD (RP analyses required) 1) Pump 17b replacement and leak test 2)Pressure test on the old inlet lines (technicians coming.
EN-CV interventions during YETS
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Muon Tracking Meeting SOR issue First priority Diagnostic: MCH DetectorScriptError Arriving at the initialization stage: the whole or part.
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
TC meeting P2 planning wks 9&10 A.Tauro
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
1 Onsite Status Itaru Nakagawa RIKEN/RBRC. 2 Schedule.
24/03/2010ALICE TOF General Meeting March TOF hardware and data taking 2010 Andrea Alici Museo Storico della Fisica e Centro Studi e Ricerche “Enrico.
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
winter shutdown planning A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
E Ethernet C CAN bus P Profibus HV HV cables LV LV cables (+busbar) S Serial (RS232) Signal cable Other/Unknown Liquid or Gas Cable and/or Bus PCI-XYZ.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
Claudio Bortolin. pump: replaced outlet filter: replaced demineralized cartridge: replaced mechanic filter on air control: replaced SSD chilled water.
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
André Augustinus P2 events & perturbations 07 May 2010 ALICE Technical Coordination Meeting.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
ALICE 5 o’clock meeting Wk 51.
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
LS1 planning meeting
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
LHCb & EYETS
ALICE 5 o’clock meeting Wk
Power cut 18kV cable for EMD404/E9 is heating
November technical stop activities:
Presentation transcript:

TS4 preparatory meeting

TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start the RP search at 8:30 Access in weeks 52 & 1 will be restricted (only critical activities) No access in these periods: –Lift maintenance  20 th Dec 7:00 AM to 9:00 AM –Evacuation test  28 th Dec (whole day) –Lift conformity  3 rd Jan (whole day) Magnets will stay off –Ramp down on Monday 17 th at 6:00 or 8:00, depending on LHC program (SL action) DAQ-DCS-HLT available at all times 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro2

TS4 – detector’s activities 1/5 11/12/12 TC meeting DetectorActivity SPDPressure test on the old inlet lines. -Nitrogen bottle connected with a manifold that feeds the 10 inlet connections at the plant while the other side of the pipe (PP4) will be closed with 10 caps. The pressure (10b) will be kept for several hours in order to identify possible leaks checking the leak rate with a digital pressure manometer. Cleaning of filters in PP3 of sectors 0, 1, 2, 3 and 8. -Start on Monday morning. Cleaning by vacuum pump. Need to access PP4 several times every day. -If on Friday morning (21 st Dec) the cleaning process is not satisfactory  will leave the cleaning machine on until Friday 4 th Jan when will disconnect it and restart the cooling loops. Drilling of the filter in PP3 of sector 3 (tbc). -Access to PP4 and PP1 to install the manometers and equipment necessary for the PP3 filter's drilling of sector 3. Filters replacement in PP4. Replacement of the compressor "B” and of the pump “A”. TS4 preparatory meeting - A.Tauro3

TS4 – detector’s activities 2/5 11/12/12 TC meeting DetectorActivity SSDReplace 7 CAEN LV boards with modified ones TPCWk 51: install TPC upgrade prototype (IROC + drift box) in the miniframe. Wk 52-1: intervene in the cavern if needed, in particular for gas leaks, if any. -The prototype is an aluminum box (typical dimension 50 cm) flushed with the TPC gas and instrumented with HV and 1-2 readout channels (with LV). -HV, LV and a scope will be installed in one rack (A15 or so) -The cables are already pulled. Laser: the work will be done in the laser hut with or without the L3 magnet on. Time needed: 2 times 1/2 day of access. Wednesday 19th: -Laser2: repair hardware error: replace flash lamp or top up secondary cooling water -Laser1: improve the energy output by replacing some mirrors. Modify the HV distribution to OROC A05 and C06. TS4 preparatory meeting - A.Tauro4

TS4 – detector’s activities 3/5 11/12/12 TC meeting DetectorActivity TRDMon: check of the LV connections on the C side of the TRD supermodules (IR camera, voltage measurements). Depending on the outcome of the survey: -tightening of problematic LV connections. -adding of patch cables for problematic connections. Tue or Wed (1h): check connector for the LV supplies in rack I26 Tue (few hours): help EN-CV to leak tests on the TRD cooling system. Tue (2h): connect the GTU DCS boards to ethernet multiplexer setup in rack C19 install backup trigger fiber from pretrigger (bottom of L3) to sectors 02 and 03 (C-side). The current fibers of the BACKUP trigger system for sectors 02 and 03 seem to be broken. TS4 preparatory meeting - A.Tauro5

TS4 – detector’s activities 4/5 11/12/12 TC meeting DetectorActivity TOFReplacement of faulty DCDC converter in SR2C Replacement of 2 faulty Detector Readout Modules (DRM) in sector 6 side A and sector 7 side A (access from miniframe): -the upper part of these TOF crates is completely blocked by pipes (gas and cooling) and cables. -the safest way to replace this boards is to unplug all the TDCs and to extract the DRMs from the bottom (estimated time to unplug/replug one crate is ½ day). HMPReplacement of CAEN LV power supply PMDRepair FE chains (need to move the detector to parking position) (tbc) Repair the CROCUS modules. Few days after 30 th Dec. T0Inspection of T0 trigger electronics: check the thresholds of OTVX signal. -Access to O18-O19 racks -Standalone run with calibration trigger Reset the calibration laser system. -Access to O18-O19 racks TS4 preparatory meeting - A.Tauro6

TS4 – detector’s activities 5/5 11/12/12 TC meeting DetectorActivity MTKFPGA software update ST3-4-5 (need nacelle). Replacements/rearrangements of readout cards in FASS and outside. MTGNo activity on detector. Electronics: -Spare DARC & Regional boards test in situ, crucial for p-A -Need DAQ control. It takes ~2 days of activity. Need to access to the MTR global crate in C-side of level 0 and the gangways C-side. TS4 preparatory meeting - A.Tauro7

Wk 51: L3-MNF activities MonTueWedThuFri 8:00 – 12:00 SPD-TPCTOF, TRD 13:00 – 17:00 TRDTOF, TRD 14/9/12TS preparatory meeting - A.Tauro8 SPD has to access L3 every day for short periods

TS4 – other activities TE-VSC: installation and test of the GIS table (crane needed – remove green fences) –Start Monday at 14:00 – will close the central valve PH-DT (gas group): replace pump of TRD gas system. 2 pumps are currently working in parallel (9’500h and 8’000h of work – limit is 10’000h) Tue 18 th Dec.’12 (tbc)  swap one pump EN-CV: –Maintenance drainage pump (‘pompe de relevage’) (UX25) –Maintenance P2 chillers (19-21 Dec) EN-HE: put UX25 crane in operation (reinstall electronics) EN-HE (Réel-Altéad): installation of anti collision system between PR709 (SX2) and PR774 (UX25) 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro9

TS4 – Diesel and SVC tests 1/2 Diesel test planned on Wednesday 19/12 from 7:00 AM to 7:05 AM A ~5 minutes cut of: –all offices, meeting rooms, wall outlets, light, coffee machine –all SXL2 –Working Rooms in the ACR –the non UPS part of the detector cooling plants (interlocks triggered) –the gas systems (PLCs stopped, interlocks triggered) –the circulation of iced and mixed water, ventilation Are NOT affected at P2: –all equipment on UPS –all racks in CR and UX For info: this is CERN-wide, this affects also all offices and labs in Meyrin 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro10 All gas systems stopped on Wed before 7:00 What about Detector Cooling?

TS4 – Diesel and SVC tests 2/2 18kV compensator (‘filter’) test, planned on Wednesday 19/12 starting at 09:30 AM –Possible perturbations on all networks, including rack power. Only exception: UPS power –Advise to ramp down all HV and if possible LV (possible trips of CAEN and ISEG) Central systems availability during these two tests: DAQ: –Will shutdown consoles in WRs and majority of CR1 on Tuesday evening (t.b.c by RC) HLT: –Might shutdown part of CR2 (t.b.c. if and when) DCS, safety systems: –Not affected (but DCS maintenance in the shadow) 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro11

TS4 – DCS Bottom line: don’t touch! –But please make your backups Monday 17/12 (morning) –‘Usual’ DataBase updates, normally transparent –Possible DB shutdown for repowering Wednesday 19/12 (morning) –In the shadow of the 18kV filter tests –Reboot of DCS cluster –Make sure you save your work (latest Wed. 19 at 09:00) 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro12

TS4 – End-Of-Year closure Weeks 52 & 1 Different from last years –ALICE remains ‘powered’ –24/24 shift coverage (DCS and DAQ) –Re-enforced on-call for online systems Immediate actions are possible by shifters – Make sure you provide clear and precise instructions! As other years: daily inspection tours in CRs and UX –To spot the obvious –‘Usual suspects’ will be contacted soon 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro13

TS4 – status of gas & cooling systems Gas systemCooling system SPD -Run SDD-SSD -Run TPC Run TRD Run TOF Run EMC -Run PHO Run (N 2 )Run (both plants) HMP Ar instead of CH4 (stop Mon, restart 7 Jan) C6F14 in stagnant mode Run PMD Run- MCH Run- MTG Purge (no SF6)- 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro14 CV and Gas piquet services available at all times

Lifts AS703 (UX25) – stopped on Jan.3 rd AS715 (CRs) – stopped on Jan 4 th 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro15

Visits VIP visit by The Research Council of Norway on Tuesday 8 th Jan 2013 –15:10 Transport to LHC Point 2, building 2285 –15:25 Visit ALICE surface permanent exhibition (P. Giubellino and Norwegian Colleagues) –15:50 Walk to building 2255 –15:55 Don helmets at the entrance to the PM25 lift and descend –16:00 Opportunity to view the tunnel at Point 2, UJ26 (P. Giubellino and Norwegian colleagues) –16:15 Visit ALICE underground experimental area (P. Giubellino and Norwegian colleagues) –16:35 Back to surface 11/12/12 TC meetingTS4 preparatory meeting - A.Tauro16