Slack Bus Change and Impact to Market Market Analysis, ERCOT QMWG Sep. 4, 2015.

Slides:



Advertisements
Similar presentations
Outage Cost Study Market Analysis and Design Outage Coordination Improvement Task Force 3/23/2015.
Advertisements

SCED Power Balance Penalty Curve
Critique of Proposal to Designate SAPS-Shrew as CRE Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) June 4, 2009.
March 13, 2013 Day-Ahead Market (DAM) Clearing Process follow-up from February WMS Matt Mereness, ERCOT Manager DAM & CRR.
Discussion: Use of RAPs in system operations Kris Dixit 1.
Real-Time Transmission Congestion Management & Market Effects
EE 369 POWER SYSTEM ANALYSIS
Announcements Be reading Chapter 7
February 2012 CMWG Constraints Competitiveness Tests (CCT)
EE 369 POWER SYSTEM ANALYSIS
IMO Market Evolution Program Drew Phillips Market Evolution Program
ERCOT RMR Deployment and Cost Proposals By: Matt Mereness and Ino Gonzalez.
Production Cost Model Fundamentals
1 Dead Bus Pricing Issue/CRR Performance Issue TAC 3 February, 2010.
December 2, 2011 QMWG Summary of Potential Issues with NPRR385 Price Floor ERCOT.
July 30, 2015 TAC Meeting Update to COPS Michelle Trenary August 12, 2015.
Proposed Revision to the Shadow Price Cap and Power Balance Penalties in SCED Same Transmission Element.
April, 2008 Maximum Shadow Price. April, 2008 Protocol Requirement: Transmission Constraint Management (2)ERCOT shall establish a maximum Shadow.
Wholesale Market Subcommittee April 12, 2012 ERCOT Dynamic Ratings Application.
SCED Security Constrained Economic Dispatch Linear vs. Quadratic Programming Model.
Market Evolution Program Day Ahead Market Project How the DSO Calculates Nodal Prices DAMWG October 20, 2003.
Bill Hellinghausen EDF Trading North America
NPRR385, Security Violation Analysis and Reporting and Negative Price Floor WMS Meeting February 15, 2012.
January 21, 2010 Security Constrained Economic Dispatch Resmi Surendran.
ISO Comparison – CAISO Alex Lee (ERCOT)
1 1 Slide © 2005 Thomson/South-Western Simplex-Based Sensitivity Analysis and Duality n Sensitivity Analysis with the Simplex Tableau n Duality.
1 Reliability Deployment Task Force (RDTF Meeting) December 20 th 2011 December 20, 2011.
Nodal MIS Portal Project MIS Functions to Support EDS 3, Release 5 September 11, 2007.
ERCOT, Market Analysis 2013 Annual Constraint Competitiveness Test (CCT) Study Results – Update for 8/27/12 CMWG 8/27/2012 ERCOT Public.
Market Participant Data Access 1 Market Participant Data Access Jan Stephen Kerr.
CMWG Update WMS September 2015 Meeting. CRR Balancing Account Fund Discussion The CRR Balancing Account fund appears to be working as expected The cap.
2% Shift Factor rule and associated price discrepancies Kris Dixit 1.
ECE 476 Power System Analysis Lecture 14: Power Flow Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
Lance Cunningham, Ph.D., PE November Frisco, TX 2.
1 Tests for Reasonable LMPs & Price Validation Tool Overview October 27, 2009 NATF.
Announcements Homework 8 is 11.19, 11.21, 11.26, 11.27, due now
DAM Performance Issues with CRR Offers Steve Reedy Market Design Manager NATF 31 August 2010.
ERCOT Public 1 Real-Time Co-optimization of Energy & Ancillary Services Co-ordination of Power Balance Penalty Curve, VOLL, SWOC for AS Demand Curves.
ECE 476 Power System Analysis Lecture 18: LMP Markets, Symmetrical Faults and Components Prof. Tom Overbye Dept. of Electrical and Computer Engineering.
QSE Managers Working Group November 7 th 2011 NPRR 334 – Additional Analysis.
1 Nodal Stabilization Market Call December 03, :30 PM.
CMWG Update to WMS Report of CMWG Meeting of M. Wagner Edison Mission Marketing & Trading Thanks to ERCOT Staff for Graphics See ERCOT.
August 2012 Wholesale Market Operations Constraints Competitiveness Tests (CCT) – Annual CCT 2013 Study Result with New Approach Market Support and Analysis.
Lead from the front Texas Nodal 1 Reduction of MMS Vendor Effort for TPTF January 8, 2008 Murray Nixon Sai Moorty.
Discussion on FGR Settlement Protocol Language David Maggio CMWG February 17, 2014.
ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Hao Zhu Dept. of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
WMS 1/9/20131 Priority Power Management, LLC Proposed Changes to Holistic Solution WMS January 9, 2013 James Z. Brazell Law Office of James Z. Brazell.
ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Hao Zhu Special thanks to Dr. Kai Van Horn Dept. of Electrical and Computer Engineering.
2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule Kris Dixit 1.
RDTF June 1, Purpose “The effect of the Shadow Price cap for the Power Balance Constraint is to limit the cost calculated by the SCED optimization.
DAM Performance Issues with CRR Offers Steve Reedy Market Design Manager TAC 2 September 2010.
RCWG Update to WMS March 7, Draft NPRR, Caps and Floors for Energy Storage Resources Chair of ETWG gave high level overview ERCOT had questions.
The Wholesale Market Subcommittee Update Prepared for the July 31st TAC meeting.
July 15, 2011 Reliability Deployments Task Force Meeting ERCOT Studies and Proposal on Reliability Energy Pricing John Dumas Director Wholesale Market.
Proposal for Consideration Regarding Holistic Solution to Congestion Irresolvable in SCED Issue:How do you identify when constraint is irresolvable Proposal:Adopt.
Money Transfer Due to Real-Time Irresolvable Constraint Resmi Surendran ERCOT.
Settlement of Ancillary Service Infeasibility ERCOT QMWG April 15, 2016.
CMWG Update to WMS Met 4/24 & 5/11 Continued Work on PRR 801 –Discussed outages as related to TCR Cases –ERCOT evaluates various outage combinations.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Valley Import Constraint Resmi Surendran. Valley Import Constraint Range of SFs – to in valley area – 0.03 to outside valley area Not.
NPRR784 Mitigated Offer Caps for RMR Units Protocol Revision Subcommittee June 16,
Reliability Unit Commitment Discussion with QMWG
Practice: Given the following Sensitivity Analysis Report
CRR Deration and NPRR821 WMS 09/06/2017.
Market Trials Update NATF March 2,
NPRR833 Workshop: Contingency Processing in CRR, DAM and SCED
NPRRs 815NPRR Revise the Limitation of Load Resources Providing Responsive Reserve (RRS) Service.  This Nodal Protocol Revision Request (NPRR) revises.
Review of Abnormal MCPEs
LMP calculations Congestion evaluation
ECEN 460 Power System Operation and Control
Presentation transcript:

Slack Bus Change and Impact to Market Market Analysis, ERCOT QMWG Sep. 4, 2015

2 Market Notice for Mothball MLSES_UNIT 1

3 Change Slack Bus to CPSES_UNIT 1 Current Slack (MLSES_UNIT1) will be mothballed on Jan. 1, 2016 CPSES_UNIT 1 will be the new Slack: –multiple paths to the plant –extremely rare outages –central location of the plant in the ERCOT power system –minimizes issues with VSAT/TSAT NOMCR & market notice planned for Nov. 2015

4 Market Impact of Slack Bus Change CRR – No impact SCED – No impact –SCED shift factors are based on load distributed slack instead of single slack hence no impact to solution or SFs DAM and RUC –No impact to final LMP or awards The changes in energy component (system lambda) and congestion component (sum(shift factor *shadow price)) will cancel out so that the sum of the two components (final LMP) will remain the same –Shift Factor values will be changed

5 DAM/RUC Congestion Component Change Shift Factor values will be changed –The shift factors for DAM and RUC are calculated based on the single slack bus –Historic DAM shift factor would have been different with new slack change –SF of bus A with CPSES slack = SF of bus A with MLSES slack – SF of CPSES with MLSES slack –SF of bus A with MLSES slack = SF of bus A with CPSES slack – SF of MLSES with CPSES slack Congestion component at each bus will be changed –Historic congestion component can be converted to new slack bus by recalculating using new SFs based on above formula No impact to congestion rent –The transmission constraint shadow price and flow will remain the same No impact to PTP price/award

6 Appendix

7 Appendix: Slack Bus Impact for DAM and RUC Define bus o as the original slack bus, n as the new slack bus and j as any bus in the system Define SF(c,j,o) as the shift factor for any bus j w.r.t constraint c with bus o as the single slack. It can be calculated as the flow on constraint c by inject 1 MW at bus j and withdraw 1MW at bus o. Define SF(c,j,n) as the shift factor for any bus j w.r.t constraint c with bus n as the single slack. It can be calculated as the flow on constraint c by inject 1MW at bus j and withdraw at bus n. This is equivalent to the flow on constraint c with the superposition of the following: –inject 1 MW at bus j and withdraw 1MW at bus o (SF(c,j,o)) –inject 1 MW at bus o and withdraw 1MW at bus n (-SF(c,n,o)) so we have SF(c,j,n)=SF(c,j,o)-SF(c,n,o) So for DAM and RUC, the new shift factor SF(c,j,n) will be reduced the same value SF(c,n,o) from the original shift factor SF(c,j,o). However the difference between the two shift factors will remain the same no matter what slack bus is chose, i.e. SF(c,j,n)-SF(c,j,o)=-SF(c,n,o) as consant The DAM/RUC DC Linear Line Flow for any constraint c can be calculated as below(assume j as generator bus and k as load bus) Line Flow (c)=sum[Gen(j)*SF(c,j,n)]+sum[Load(k)*-SF(c,k,n)] =sum[Gen(j)*SF(c,j,o)]-sum[Gen(j)*SF(c,n,o)]+sum[Load(k)*-SF(c,k,o]-sum[Load(k)*-SF(c,n,o)] Because of power balance, we have sum[Gen(j)]=sum[Load(k)], then Line Flow (c)={sum[Gen(j)*SF(c,j,o)] +sum[Load(k)*-SF(c,k,o)]}-SF(c,n,o)*{sum[Gen(j)]- sum[Load(k)]}=sum[Gen(j)*SF(c,j,o)]+sum[Load(k)*-SF(c,k,o)] It is proved that Line Flow will not change no matter what slack bus is chose. Since the DAM/RUC optimization model has the same line flow, the DAM/RUC solution will remain the same.

8 Appendix: Slack Bus Impact for DAM and RUC Define SystemLambda(n) is the shadow price of power balance constraint with bus n as the slack Define ShadowPrice(c) is the shadow price of transmission constraint c. The LMP at any bus j can be calculated as LMP(j)=SystemLambda(n)-Sum[(SF(c,j,n)*ShadowPrice(c)] Where SystemLambda(n) is the energy component and -Sum[(SF(c,j,n)*ShadowPrice(c)] is the congestion component The transmission constraint shadow price will remain the same since the line flow constraint will remain the same The System Lambda may change based on the choice of the slack bus n The LMP will not change but the energy component and congestion component may change but the sum of the two components should remain the same

9 Appendix: Slack Bus Impact for SCED SCED uses the load distributed shift factor from EMS. EMS calculates the shift factor based on the single slack bus first and then transform it to the load distributed shift factor by subtracting the load weighted shift factor center Define the load weighted shift factor center with bus o as single slack as SFC(c,o). It can be calculated as SFC(c,o)=sum[Load(k)*SF(c,k,o)]/sum[Load(k)]; Define SFD(c,j,o) is the load distributed shift factor for bus j w.r.t to constraint c with o as single slack. It can be calculated as SFD(c,j,o)=SF(c,j,o)-SFC(c,o) Define SFD(c,j,n) is the load distributed shift factor for bus j w.r.t constraint c with n as single slack. It can be calculated as SFD(c,j,n)=SF(c,j,n)-SFC(c,n) It has been proved that SF(c,j,n)-SF(c,j,o)= -SF(c,n,o) So we have SFD(c,j,n)- SFD(c,j,o)= SF(c,j,n)-SFC(c,n)-[SF(c,j,o)-SFC(c,o)] = SF(c,j,n)-SF(c,j,o)-[SFC(c,n)- SFC(c,o)] = SF(c,j,n)-SF(c,j,o)-{sum[Load(k)*SF(c,k,n)]/sum[Load(k)]-sum[Load(k)*SF(c,k,o)]/sum[Load(k)]} = SF(c,j,n)-SF(c,j,o)-sum{Load(k)*[SF(c,k,n)]-SF(c,k,o)]}/sum[Load(k)] =-SF(c,n,o)-sum{Load(k)*-SF(c,n,o)}/sum[Load(k)] = -SF(c,n,o)+ SF(c,n,o) =0 It is proved that the load distributed shift factor remain the same no matter what single slack is chose. So the SCED shift factor will remain the same and the SCED solution will not change.