Tom Beebe Project Manager Application of Reservoir Characterization and Advanced Technology to Improve Recovery and Economics in a Lower Quality Shallow Shelf Carbonate Reservoir Class II Project DE-FC22-94BC14990 Tom Beebe Project Manager
Project Location
Welch Field Map
West Welch Unit History 1939 Discovery 1955 Pilot water flood began 1960 Unitized & initiate water flood 1966 Develop to 40 acre 5 spots 1971 Complete 40 acre 5 spots 1982 Initiate 10 acre well spacing line drive 1991 Complete 10 acre well spacing line drive 1994 Shut-in Prod / Inj Wells over the next 5 years 1997 CO2 pilot w/DOE 6 wells 2000 Drill first horizontal well 2001 Drill 4 horizontal wells
Comparison of Fields
Technologies Demonstrated Cross well seismic 3D seismic interpretation Petrophysical flow description Reservoir simulation Cyclic CO2 stimulation Hydraulic fracture stimulation
DOE Project History
WWU DOE Project Area – Actual Performance
WWU DOE Focus Area – Actual Performance
Pattern Tertiary Performance Green – Tertiary Oil Recovery Magenta – HCPV CO2 Injected Red – Annual Throughput (Processing Rate)
Producer Well Response & CO2 Injection Cumulative CO2 Injection Dark Red Peak Incremental BOPD/BWPD/MCFPD Magenta – Cum CO2 Injected, MMCF
Producer Well Response
Activities Since 2000 Emphasize on Optimizing Reservoir Processing Rate Injection Wells Step Rate Tests Dip-Ins Injection Profiles Producing Wells Workovers Horizontal Well Observation Well Logging Cross Wellbore Tomography
West Welch Unit #4853 Horizontal Lateral
WWU #4853 Horizontal Simulation Surveillance West Welch Unit #4853 (12/07/00) West Welch Unit #4853 (02/01/01)
WWU #4853 Horizontal Well Results
2001 Workover Results in the Focus Area Spent $450M on 15 workovers (14 PRD & 1 CO2INJ) Average 10 BOPD Incremental after 30 days Payout ~6 Months @ $21/BO and constant BOPD 50 BOPD incremental after ~1 year of production (1/3 of 30 day incremental)
Observation Well Logging Last Column represents CO2 migration through reservoir Comparison of Neutron log ran in 1994 to 2001 measure porosity change. N M1 M3 M5 Z6
Focus Area Forecasted Tertiary Performance Not from model forecast, but prototype curve
Economic Summary
Simulation Historical & Forecasted Rates From SPE 39808 West Welch CO2 Flood Simulation with an Equation of State and Mixed Wettability (1998) Initial update of rate cards with model dataset (2002)
Simulation Historical & Forecasted Cumulative Initial update of rate cards with model dataset (2002)
Cross Wellbore Tomography www.advancedreservoir.com Advanced Reservoir Technologies, Inc. P.O. Box 985 Addison, TX 75001-0985 Ph. 972-418-0992 FAX 972-418-2064
Summary WWU & the DOE Area are both low productivity and low reservoir processing rate. Last 2 years have focused on the demonstration phase with emphasize at optimizing the reservoir processing rate. The exception of wellbore tomography work done by Advanced Reservoir Technology. Response observed from CO2 injection: Reduction in water production, increase gas production and flattening and incline in oil production. Low HCPV CO2 injected, however greater volume of CO2 injected into focus area than original DOE area. Successfully drilled horizontal lateral, however did not improve reservoir processing rate and application of the SURGI tool did not address fluid loss to previously open fracture. Workover program did result in incremental oil, but results varied and appears to have a high decline rate. Qualitatively measured CO2 migration through the main pay intervals, however some CO2 migration below pay. Economics though positive ROR, would not be able to support capital investment and high injection withdraw ratio (IWR) deteriorates the return. Original forecast from the simulation work does not match due to different CO2 injection scheme and performance.
Conclusions CO2 Pilot flood to improve recovery appears not economics. Tertiary response occurred more often in the closet producer either north or south of the supporting CO2 injection well. Efforts to improve the processing rate varied. (stimulations, injection tests and the horizontal well) The successful reservoir process rate improvements were not enough to improve flood performance. Decision to move to the focus area helped improve potential response versus spreading out CO2 injection throughout the project. The horizontal lateral either connected up existing fractures and / or the stimulation went into the same location. Some of the well stimulation work appeared to have been needed prior to implementing the CO2 flood. More attention needed to be addressed to out of zone injection. High IWR is problem during the water flood (evident during the modeling effort) as well as indication of out of zone CO2 injection in the observation well.