Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 MQXFA Functional Requirements Ruben Carcagno May 13, 2015 1.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

Cryogenic Experts Meeting (19 ~ ) Heat transfer in SIS 300 dipole MT/FAIR – Cryogenics Y. Xiang, M. Kauschke.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LQS01 Test Preparation and Test Plan LARP Collaboration Meeting 12 LBNL - April 8-10, 2009.
HL-LHC/LARP, QXF Test Facility Workshop– R. Carcagno QXF Test Requirements Ruben Carcagno BNL Workshop December 17, 2013.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
Superconducting IR Magnets CHEN, Fusan May 11, 2007.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
HL-LHC Annual Meeting, November 2013HQ Planning – G. Sabbi 1 HQ Status and Plans G. Sabbi High Luminosity LHC Annual Meeting Daresbury, UK, November 11-14,
Review of Quench Limits FermilabAccelerator Physics Center Nikolai Mokhov Fermilab 1 st HiLumi LHC / LARP Collaboration Meeting CERN November 16-18, 2011.
General Considerations for the Upgrade of the LHC Insertion Magnets
TD Designs for mu2e Solenoid Magnets Michael Lamm for the Mu2e Collaboration and TD/Magnet Systems Dept. All Experimenters’ Meeting January 25, 2010.
CLIC Workshop th -17 th October 2008 Thomas Zickler AT/MCS/MNC 1 CLIC Main Linac Quadrupoles Preliminary design of a quadrupole for the stabilization.
Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 MQXFA Functional Requirements Ruben Carcagno October 30,
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
Cold powering test results of MBHSP102 Gerard Willering, TE-MSC-TF With thanks to Jerome and Vincent and all others from TF for their contribution.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
Q4 MAGNETS FOR HL-LHC J.M. Rifflet, M. Segreti, E. Todesco WP3 - Q4 magnets for HL-LHC 5th Joint HiLumi LHC-LARP Annual meeting Research supported.
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Philip Schwarz TE-MSC-MNC 1 Engineering Specifications for ELENA ring and TL magnets Philip Schwarz on behalf of WP 2.2 ELENA IIC meeting 5 th December.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
MQXF Workshop on Structure, Alignment, and Electrical QA – Feb 2-4, 2016 Requirements and feedback form LARP structure review Ruben Carcagno February 2,
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Super Fragment Separator (Super-FRS) Machine and Magnets H. Leibrock, GSI Darmstadt Review on Cryogenics, February 27th, 2012, GSI Darmstadt.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
First Q4 cold mass engineering follow up meeting 16/03/2016 Q4 Status update H. Felice, M. Segreti, D. Simon and JM. Rifflet.
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Answers to committee questions - magnets.
Ranko Ostojic AT/MEL 1.Beam heat loads 2.Magnet design issues related to heat loads.
Jim Kerby Fermilab With many thanks to Vladimir Kashikhin, the FNAL, KEK, and Toshiba teams. SCRF BTR Split Quadrupole ILC ML & SCRF Baseline Technical.
CERN, 11th November 2011 Hi-lumi meeting
CBM Dipole Conceptional Design Review
SIS 100 Vacuum chamber Recooler String system Components
Status of the PANDA Solenoid Magnet Production in BINP
CBM magnet overview of the BINP work
MQXC Nb-Ti 120mm 120T/m 2m models
Hervé Allain, R. van Weelderen (CERN)
Hervé Allain, R. van Weelderen (CERN)
SLHC –PP WP6 LHC IR Upgrade - Phase I.
11T Magnet Test Plan Guram Chlachidze
HO correctors update Massimo Sorbi and Marco Statera
The HL-LHC Circuits: Global View and Open Questions
Hervé Allain, R. van Weelderen (CERN)
HO Corrector Magnets: decapole test and future plans
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
Status of the PANDA Solenoid Magnet Production in BINP
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
PROPOSAL OF APERTURE FOR THE INNER TRIPLET
Updated concept of the CBM dipole magnet
as a prototype for Super c-tau factory
Review of Quench Limits
Beam Screens Cooling Update (1st Oktober 2014)
Hi-pot results summary
Electrical integrity of magnets and coils
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 MQXFA Functional Requirements Ruben Carcagno May 13,

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Functional Requirements A clear specification of functional requirements for U.S. deliverables is needed to support the DOE Order 413.3B project management process for the US-HiLumi project These requirements should not be embedded in other documents (e.g., design reports) or mixed with requirements for other systems – Functional requirements for the U.S. project deliverables should be documented in a stand-alone document – These requirements should be such that their verification means that the project deliverable(s) are fit for the intended use They do not include design parameters, only the functions that the deliverable must satisfy – Functional Requirements must be reviewed and approved by the end user (CERN), well in advance of the project baseline establishment for the CD-2 DOE review A signed document should be finalized in less than a year from now 2

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Main Project Planning Documents 3 Project Execution Plan (PEP) Project Management Plan (PMP) Risk Management Plan (RMP) Quality Assurance Plan (QAP) Change Control Management Plan Procurement Management Plan Manufacturing: Manufacturing Plan (MP), Procedures, etc. Risk Registry (RR), Risk Analysis Performance Baseline (PB) Cost Baseline Scope Baseline Schedule Baseline Acquisition Strategy (AS) Mission Need Statement (MNS) Integrated Safety Management Plan KPPs, WBS, WBS Dictionary Key Assumptions, KPPs, Baseline, Funding Profile, PM Strategy BOEs, Time- Phased, Escalation, Contingency BOEs, RLS, Milestones, Constraints, Contingency Design: Reports (CDR, PDR, FDR) Drawings, Specifications, etc. Functional Requirements Specification (FRS) OBS, RAM, CAMs Alternatives and Risk Analysis Value Engineering Cost and Schedule Range, Key Milestones Procurement: Procurement Plan (PP), etc.

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Scope This presentation is for the MQXFA functional requirements for Q1 and Q3 only: The MQXFA magnets for Q1 and Q3 are assumed to be identical A separate, similar functional requirements document is also needed for the Q1, Q3 Cold Mass Assembly (LMQXFA/B) 4 SS vessel not part of MQXFA

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Previous Example: MQXB FRS Example of a previous FRS for the present Inner Triple Quadrupole MQXB for Q2 Some parameters for MQXFA FRS were taken from the MQXB FRS, but they need to be confirmed by CERN 5

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 MQXFA FRS Draft prepared as a US- HiLumi project document to start discussions Attempts to collect all the functions that the MQXFA magnet must satisfy – A total of 38 functional requirements were identified Several parameters need definition and confirmation by CERN 6

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 MQXFA FRS Table 7 Parameters in black are more certain. Parameters in red less certain or still under discussion

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 MQXFA Physical Requirements 150 mm aperture, ≤ 5.0 m long, ≤ 614 mm diameter, ≤ 1 mrad/5m twist, ≤ 100 um/5m straightness 8

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Magnetic Field Requirements Magnetic length is 4.2 m, nominal gradient T/m, ultimate gradient 140 T/m (5% above nominal) in superfluid helium at 1.9K, fringe field < 50 mT Field Quality Targets (tables need to be updated): CERN will provide b14 correctors if the target b14 value cannot be met 9 Systematic Random

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Cryogenic Cooling System 10

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Cryogenic Requirements Superfluid helium bath at 1.3 bar and K, 40% of coil inner surface free of polyamide, coil peak power 2.5 mW/cm 3, maximum heat load 20 W/m (assumes CERN-provided beam screen with tungsten absorber) Minimum cooling channel diameter is 77mm to accommodate two 74mm O.D. copper heat exchanger tubes, provisions for cooling passages (8mm pole holes every 50 mm, etc.) 20 bar peak pressure Maximum rate of temperature change +/- TBD K/hr 11

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Power System 12

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Electrical Requirements Feeding current < 20 kA (expected nominal is kA), ramp rate of 10 A/s with < 2 volts during ramping (means inductance < 200 mH), Nb-Ti leads for connection to the bus, joint resistance < TBD µΩ, provisions for routing SC bus in cooling channels without heat exchangers Instrumentation: three quench detection voltage taps, two voltage taps for each quench strip heater (VTs for joints?) Voltage limits in table below. Must pass hipot test in liquid helium at 1 atm according to: Impulse test? Is inductance range a requirement? 13 Circuit ElementVmaxV hi-potI hi-pot Quench Protection Heaters - Coil500 VTBD< TBD µA Magnet Coil - Ground1,000 VTBD (2,500 V?)< TBD µA

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Quench Requirements Temperature margin ≥ 4.2K, MIITs ≤ 37, coil voltage to ground after quench < 1,000 Volts Training to 105% of nominal operating current (18.3 kA). Must remember training and reach nominal operating current in no more than 1 quench after a room temperature thermal cycle Must not quench while ramping down at 300 A/s from nominal current and up at TBD A/s to nominal current 14

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Radiation Hardness Requirements Survive maximum radiation dose of 30 MGy – Assumes beam screen with tungsten absorber (provided by CERN): 15

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Reliability Requirements Survive 6 years under nominal luminosity conditions, 25 thermal cycles, 3,000 powering cycles, and 10 quenches 16

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Interface Requirements Comply with Interface Specifications for: – Other LMQXFA(B) cold mass components – CERN Cryogenic System – CERN Power System – CERN Quench Protection System – CERN Instrumentation System 17 All these interface specifications To Be Defined

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Safety Requirements Comply with the corresponding CERN Work Package Launch Safety Agreement (LSA) specification (TBD) 18

Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 Path Forward Are there any missing requirements? Are requirements properly stated? – Is there agreement on parameters in black/blue? – Is there enough information to verify/provide parameters in red? What is the process to converge on a final set of requirements acceptable to CERN? We are going to need a final, approved MQXFA requirements document in less than a year from now – Goal to complete draft by next collaboration meeting (Sep 2015)? 19