05:31 Beam dump due to QPS trigger in sector 78.  Quench heaters discharged in MB10.L8. 07:28 Quench heaters charged ok again in cell B10L8.  Was a EN/EL.

Slides:



Advertisements
Similar presentations
Sat 17/9 – Sun 18/9 07:00 Cryo problem in point 4 From E. Blanco: First beam dump caused by a cryo PLC not reachable anymore (UX45_QUI) and then 14 minutes.
Advertisements

8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
MEF - Machines & Experimental Facilities Technical Stop #4 29 th August - 2 nd September 2011 Summary Julie Coupard Schedule and Coordination LHC-TS4 -
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
LHC – week 48 finishing up the ioning Coordination: Gianluigi Arduini & Mike Lamont.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
:30 meetingEBH 1  7:53 start VdM scans LHCb  8:18 beam dump: RF M2B1 crowbar (3 rd time within 24 hours)  Access for RF  Changed thyratron.
Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
Friday morning Dump fill due to the trip of the RQF.A78  intervention had been just planned for the morning on the circuit Access, interventions:  RQF.A56/78,
Fri – Sat - Sunday 30 Sept - 2 nd October Friday  06:00 Operator dump fill #2171, integrated lumi 75 pb-1.  90 m  * optics Optics ok, collisions at.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC progress Tuesday 28 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
08:30 Machines in stand-by 12:30 Access in LHC for QPS and PC:  QPS quench heater power supply RB.A12  EPC for RSF2.A67B2 and RQ9.R8B1.  RCBH27.L1B2.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
Tuesday 26 th April – morning shift 08:00 Great news, cryo is back! Unluckily it was followed by many other problems, one after the other one. So, spent.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Another typical LHC day. 06:15 Fill 2000 dumped 08:44 Stable beams – fill 2001  1.675e14  1.21e11  ~2 microns normalized emittance 11:34 Beams dump.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Wednesday September 14th
Summary Friday h38: Ramp down and pre-cycle.
Tuesday 11th September LHCb dipole presently fault off
Monday 11/07: Recovery Plenty of accesses.
Thursday 09:30 VdM scan for CMS, standard ADT gain.
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Report Week 40 (R. Assmann & E.B. Holzer)
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
LHC Morning Meeting - G. Arduini
Thursday 10th May - morning
LHC Morning Meeting - G. Arduini
Wednesday 30th November 10:00 Access PZ33 for RP, Cryo, EPC, ELQA
Tuesday Loss maps in the night:
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
Not the most productive 24 hours on record
Programme for Saturday 10 July
LHC Morning Meeting - G. Arduini
Tue/Wed 12/ :00 Probe beam back again
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Tuesday 20 September 2011.
Thursday 30th September De-bunching test
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday 15th February - morning
Monday 27th August & night
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Saturday 26 November 2011.
Thursday 10:00 Fill 1986 in stable beams.
Presentation transcript:

05:31 Beam dump due to QPS trigger in sector 78.  Quench heaters discharged in MB10.L8. 07:28 Quench heaters charged ok again in cell B10L8.  Was a EN/EL circuit breaker (cell 32, EOJ106/78.32R7). nr. Q3. 08:29 Cryo back. 08:20 RF tests without beam.  Check for problem of debunching observed during fill # :51 Vacuum leak in TI2 TED bellows. Access breaks patrol. Initial estimate for repair and recovery: 48h. 15:16 Open LHC for access.  ELQA access in P8.  Planning for beam 2 program over night: abort gap cleaning and 25ns setup. Wednesday LHC morning report

On Tuesday 4th from 12:15 to 14:30 we prepared the upgrade of the LHC tuner loops needed for the 25 ns MD scheduled Thursday 6th.  The “old” algorithm needed a 1 microsec long beam segment to converge to the optimal tune. The new one needs 300 ns so that the tune will be OK after the injection of the first 12bunches batch.  We first installed the upgrade on all 16 cavities but could not get it to lock after RF ON around 13:30. We struggled a bit. As we were under pressure from CCC, we made a roll-back and reverted to the old algorithm. RF was back ON OK at 14:30. Then we worked off-line and found the problem with the new algo and corrected it.  As the LHC was down, we installed it on one cavity (1B1) at 17:00 and it worked OK. As the next fill was high-intensity physics, we did not leave it overnight (Machine Protection issue) and reverted 1B1 to the old algo at 18:00 RESULT: the new algo is tested, ready for installation on all cavities at the very start of the 25 ns MD on Thursday (~8:00, 30 min needed). RF Summary I (P. Baudrenghien) LHC morning report

Next fill (physics) showed large debunching, beam 1, ~ 1 hour after start physics, clearly due to RF noise.  John Molendijk and me came in ~ 23:00 and found noise on 1B1, caused by a so- called Klystron Polar Loop that reduces the RF noise and gain/phase changes due to klystron HV ripples and droop.  We switched loop off and physics fill continued till 6:00 on Wednesday. We made a series of observations with beam but could not “touch” the hdw until the end of the fill.  On Wednesday morning we went in the cavern, replaced the VME modulator card and found one SMC connector loose. The klystron loop is back on now. Strong debunching beam 1 had already been observed for a short time on Sept 14 th but not explained. It had disappeared since. On Sept we had another RF noise B1 episode that was traced to an intervention on 1B1 following change of a bad cable on Sept 9 th …. Cables and loose connectors are the weak points of the LHC RF….  We will replace ALL SMC cables during shutdown Our observations last night also suggest a potential problem with the loop in presence of strong power spikes (needed to compensate transient beam loading with high beam current). John will investigate off-line. All cavities are back, ready for beam. The above two events (new tuner algo - RF noise 1B1) are unrelated. RF Summary II (P. Baudrenghien) LHC morning report

18:09 Vacuum group identifies correct spare part.  Recovery time revised to Thursday morning.  TED repair starting.  Beam 2 program for the night cancelled. Plan TI8 stability checks overnight (during pump down of TI2). 18:32 Starting the PNO.a7 on RQ5.L8 and RQ6.L8. 19:03 Going through access list to check who wants to go into LHC over night and during early morning. 20:10 Access in P8 (vac expert + RP) for preventive check of the TED bellows in TI8. Wednesday LHC morning report

Access Requests =============== we contacted most of the access request this is the summary: Group: EL Location: Various points Duration: 2hrs per point during normal hrs Contact: D Ricci ( ) Reason: Optical fibres: measurement of attenuation factor contacted no answer Group: BI Location: RR47/43 Duration: 15 min/side Contact: M. Gasior Reason:tune no answer Access List I LHC morning report

Group: BLM Location: IP7/tunnel Duration: 2 hours Contact: E. Effinger, J. Emery, I. Savu Reason: Replacement of BLM Diamond monitor Request date: 29/09/ Group: EN/EL Location: All REs (tunnel) Duration: 2hrs per point Contact: Antonio Gonzalez (160454) Reason: Optic fiber measurements Request date: 28/09/2011 contacted only available during working hrs Access List II LHC morning report

Group: ALICE Location: Duration: 2h + 1h notifications Contact: Reason: Request date: on access today Group: CS/CV, RP needed Location: UJ32 Duration: 1h30 (in the tunnel) Contact: Frederic Juban (165669) Reason: verification de drain - as soon as possible Request date: No answer Access List III LHC morning report

Group: BT Location: UA87 Duration: 2h (during normal working hours) Contact: Etienne Carlier (160093) Reason: measurement of "no trigger clock" of MKI-B2 Request date: done today Group: kicker Location: Pt4 Duration 1H Contact: Barlow (164831) Reason Aperture kicker intervention Request Date: no answer Access List IV LHC morning report

Group: EN/EL Location: US15 and UJ56 Duration: 1hr Contact: Consuelo Goncalves (168896) or Jean-Claude Guillaume (163194) Reason: Inspection prior to technical stop they will go IN tomorrow morning at 7: Group: Access Location: PM45 Duration: 1hr Contact: Serge di Luca (164000) Reason: Door closer removal done today Access List V LHC morning report

Group: EN/EL Location: US15 and UJ56 Duration: 1hr Contact: Consuelo Goncalves (168896) or Jean-Claude Guillaume (163194) Reason: Inspection prior to technical stop they will go IN tomorrow morning at 7: Group: Access Location: PM45 Duration: 1hr Contact: Serge di Luca (164000) Reason: Door closer removal done today Access List VI LHC morning report

Group: BLM Location: IP7/tunnel Duration: 2 hours Contact: E. Effinger, J. Emery, I. Savu Reason: Replacement of BLM Diamond monitor Request date: 29/09/2011 closed untill tomorrow Group: Vacuum Location: point 8 Duration: 4 hours (normal working hours) Contact: Vacuum piquet Reason: Modify cabling at A4L8 and A4R8, to have a clearer view of pressure increases. Request Date: 26/09/ Access List VII LHC morning report

Group: CS/CV, RP needed Location: UJ32 Duration: 1h30 (in the tunnel) Contact: Frederic Juban (165669) Reason: verification de drain - as soon as possible Request date: will access tomorrow morning at 8: Access List VIII LHC morning report

Recovery from accesses, TED repair. Patrol. Change back of RF system. Switch LHCb polarity. 25 ns MD (estimate ~ 10h00). Thursday night: Physics Friday day: Abort gap cleaning. Friday pm/Sat/Sun: Physics Monday day: High pile-up MD. Ahead LHC morning report