ATLAS + NA62 DIRK MERGELKUHL
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 2 Quoi (quelles activités prévues pendant le LS1) The main works for ATLAS are measurements for: Opening of detector Update of infrastructure (3D + levelling) Muon EEL installation on A-side Muon EES installation on A-side Pixel detector and beampipe (VI) extraction Pixel works in SR1 (surface) Muon chambers in sector 13 Update of infrastructure (3D + levelling) Installation of Pixel, IBL and new VI Detector closing Experience shows that the non-planned activities can be substantial In parallel the analysis and reports for above mentioned works
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 3 Comment (quelles sont les procédures ?) In general as previous installation works but modifications to adapt to the actual situation in the cavern are expected. Update of SU infrastructure will be done as previously but AT401 replaces TC2002 Detector opening and closing measurements as in previous Technical Stops For EEL and EES installation equivalent to C-side in TS 2011/12 Muon in sector 13 as installation of Muon barrel in Works for Pixel and VI replacement partly as for initial installation or as for scale one mock-up in building 180. Some details need still to be defined!
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 4 Matériel Mainly identical as use for the construction and last Technical Stops including most of the tooling. The AT401 should replace TC2002 as often as necessary (or possible) to gain in precision or time following the need. Waiting for offers for AT401 prism supports from main workshop Instruments: TC2002, NA2, D2x, AT401 Software: Carnet4000, PCTOPO32, AICON 3D Studio, Spatial Analyzer
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 5 Quand (planning des activités) Our planning has to follow mainly the ATLAS planning: Opening process daysThu Thu UX15 opened for access 0 daysMon Mon Side A daysThu Wed days Measurement of geometrical network (update) Mon Fri Measurement of TAS-A before opening of detector (reference for VI and for closure) Mon Mon Removing of TAS survey device 1 hrMon Mon Measurement of TAS-C before opening of detector (reference for VI and for closure) Mon Mon Removing of TAS survey device 1 hrMon Mon Survey of monobloc A -1Wed Wed Survey of monobloc C -1Wed Wed EE installation side A 63.5 daysThu Tue Survey of monobloc C -2Fri Fri days Stability of ground Mon Thu Survey of monobloc A -2Tue Tue EEL installation daysTue Tue Survey S15Tue Tue Survey S1Mon Mon Installation of T2 for EBA opening (beampipe) Tue Tue Installation of T2 for EBC opening (beampipe) Wed Wed days network for VI measurement Wed Fri VI-A surveyFri Mon VI-C surveyFri Fri Survey S1Mon Mon days Stability of feet Tue Wed Survey S9Thu Fri Survey S7Fri Fri Survey S9Mon Tue Survey S7 4Tue Wed EES side A daysMon Wed Measurement of EES12 before final adjustment - Measurement of EES10 before final adjustment - Measurement of EES08 before final adjustment - Measurement of EES06 before final adjustment - Measurement of EES14 before final adjustment - Measurement of EES16 before final adjustment - Measurement of EES02 before final adjustment - Measurement of EES04 before final adjustment
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 6 Quand (planning des activités) Our planning has to follow mainly the ATLAS planning: Rails installation & surveyWed Wed Survey and adjustment ID rotation stageThu Thu Survey and adjustment of Pit tableThu Fri Survey and adjustment of DSTMon Tue Measurement of TX1STF-A (at beginning) Wed Wed Measurement of TX1STF-C (at beginning) Thu Thu hours Maintenance of HLS system Fri Fri Measurement of maximum of BOL/BOS/BML/BMS/BIL/BIS chambers New chambers sector daysFri Mon Adjustment of Muon brackets/rails BOS Sector 13 A - Adjustment of Muon brackets/rails BOS Sector 13 C - Adjustment of Muon brackets/rails BME Sector 13 A - Adjustment of Muon brackets/rails BME Sector 13 C - Adjustment of chamber BOS Sector 13 A - Adjustment of chamber BOS Sector 13 C - Adjustment of chamber BME Sector 13 A - Adjustment of chamber BME Sector 13 C - Installation of automatic HLS control system in trench C - Installation and calibration of BCAM system Installation of new positioning system 20 daysMon Wed days Stability of ground (before VI and Pixel installation) - 5 days Measurement of geometrical network (update before VI and Pixel installation) - 3 days local network for VI and Pixel installation Pixel Installation daysFri Wed Align DST to PSTWed Wed Package Injection & Transfer to PSTFri Wed
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 7 Quand (planning des activités) Our planning has to follow mainly the ATLAS planning: Close EBA and JD-A 9.63 daysFri Wed Installation of T2 for EBA closure (beampipe) Mon Mon EBA surveyMon Mon Survey JD-A + decisionWed Wed Fixed point surveyThu Thu Survey ECT-A + decisionFri Mon Installation of T2 for EBC closure (beampipe) Fri Fri EBC surveyFri Mon Survey of Monobloc-A during closure operation (without load of JFC1-3) Survey of VT-ATue Tue Survey of VJ-A Tue Tue Survey of LUCID-A - Survey of Monobloc-A during closure operation (with load of JFC1-3) Survey JD-C + decisionWed Wed Survey of VA-C fixed point during closure operation Survey ECT-C + decisionThu Fri Survey of Monobloc-C during closure operation (without load of JFC1-3) Survey VJ & VTFri Fri Survey of LUCID-C - Survey of Monobloc-C during closure operation (with load of JFC1-3) - Measurement of TX1STF-A (close to end) - Measurement of TX1STF-C (close to end) days LArg stability measurement Beam pipe bake-out filled with Ne) 10 daysFri Thu Survey of TAS (checking)Mon Mon Survey of TAS and adjustmentFri Mon Cleaning of side C 2 daysFri Tue works in SR1 for the Pixel and/or VI - Alignment of the DST (in SR1 Dec ‘12) - ITT alignment (in SR1 Dec ‘12) - Alignment of the ITT w.r.t. DST ( in SR1 Feb ’13) - Survey of the IST w.r.t the Pixel mounts (in SR1 March ’13) - Adjustment of the Pixel mounts (in SR1 Late ’13) - Alignment of the DST w.r.t. ITT ( in SR1 Late ’13)
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 8 Par qui (quelles sont les personnes qui vont intervenir) Dirk MERGELKUHL Vitali BATUSOV (100%) Mikhail LYABLIN (partly) Additional Russian person to replace Mikhail (partly) Contract personnel Others following needs and availability
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 9 Status de la préparation/problèmes non résolus Different measurements are well integrated in ATLAS planning Level of radiation unknown for beampipe measurements Targets and supports for VT beampipe still in design phase (ATLAS) Procedure to open UPS doors to LHC not really clear Full integration of AT401 including transfer to LGC and automation BCAM system for ATLAS closure still in design phase (ATLAS+SU)
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 10 Quoi (quelles activités prévues pendant le LS1) The main works for NA62 are measurements for: GTK STRAW 2, 3 and 4 RICH LAV 8-12 Vac Tank 1, 2a, 2b, 3a, 3b IRC MUV1 Network update Measurement of detectors before start In parallel the analysis and reports for above mentioned works
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 11 Quand (planning des activités) Our planning has to follow the NA62 planning: Autumn 2013MUV1 and SAC Sep-Oct 2013RICH Vessel installation, mirror and PMT after that Summer/Autumn 2013Straw 1+2, LAV9 Spring 2014Straw 3+4, LAV , IRC, Vac Tanks, CHOD Summer 2014Control and final adjustments Time estimation ~ 4-6 month for a team + reports and analysis To be ready for data taking September 2014 Par qui (quelles sont les personnes qui vont intervenir) Mateusz BORUCHOWSKI Dirk MERGELKUHL Others following needs and availability
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 12 Statut de la préparation/problèmes non résolus Planning less detailed than LHC experiments Some parts in design phase So far regular delays for nearly all parts Matériel Mainly identical as use as before technical run. The AT401 could replace TC2002 if helpful for certain measurements Instruments: TC2002, NA2, AT401 Software: Carnet4000, PCTOPO32, Spatial Analyzer
Dirk MERGELKUHL| SU pendant LS1 day| | EDMS | page 13 Conclusion Works for ATLAS are well understood and prepared Open issues are mostly linked to beampipe replacement where some late decisions are still outstanding LS1 will be charged but different than a xmas-TS for these 18 months Reports must be done in parallel ATLAS works only partly in two shifts From the actual planning the simultaneous intensive periods for ATLAS+NA62 are spring 2014 and autumn 2014 From experience delays could be possible for NA62 Main concentration with very charged period at end of LS1