Presentation to the Chamber of Commerce Friday, April 23, 2010
Overview Project Timeline 2010 Construction Season What’s Next Questions?
Project Timeline Project initiated 1997 Safety Pavement Village Infrastructure Design approved 2006.
Project Timeline Bid in January Construction began Spring Water and sewer lines from Pleasant Street to Prince Street. Drainage improvements starting at Pelton Street through neighborhood south of Broadway. Reconstructed pavement west of Pleasant Street. Spring Street drainage improvements.
What’s Going On: 2010 Season Continue water, sanitary sewer, and storm sewer improvements to West Broadway. Including additional Village Project to install sanitary sewer connections to Pelton Street. Continue full depth pavement reconstruction.
Pavement Reconstruction NYSDOT will: Keep driveways open. Provide notification. Please contact Engineer-in-Charge with any problems or issues.
Pavement Reconstruction Example of Signage at Construction Zone Example of Signage at Business Entrance
What’s Going On: 2010 Season Install stamped concrete median. Install foundations for decorative sidewalk lighting. Partnership between Village, Congressman Hinchey, Sullivan Renaissance, and NYSDOT.
What’s Next: 2011 Season Originally anticipated to be two-season project, but delayed due to changes during construction. Spring-Summer 2011: Finish pavement. Install curbs. Install new sidewalks Plant trees and other landscaping elements.
What’s Next: 2011 Season NYSDOT intends to replace all trees removed during construction.
What’s Next: 2011 Season Planned Landscaping includes: Replacing trees removed during construction. Installing low-growing juniper shrubs to prevent weed growth in the planting beds. One year of maintenance provided by landscape contractor. Traffic control plan. A plan the community can build on.
What’s Next: 2011 and Beyond
Route 26/17C Reconstruction Village of Endicott (2006/07)
Thank You! Any questions? Contact Information: Katy Mangan Project Manager Glenn Sanders Engineer-in-Charge