ICEE Demonstration Project by Dr W T Fok / Prof K P Cheung December 7, 2009 Proposals on location of the demo items The time line events of demo project Other discussion
Existing layout of the Yam Pak Bldg 2/F Proposed demo room area
Proposed layout of the demo room Visitor path Zone A Zone B Zone C Zone D A door should be opened between zone B and zone C Streamlined artistic partition Project 1 Project 2 Project 4 Project 7 Project 3 Project 6 Video show Project 8 Project 9Project 12 Project 11 Project 10 Project 13 Project 14 Project 5
Zoning ZoneRoom Capacity A Energy Collection 2 projects B Grid and Control 5 projects C Energy Storage 5 projects D Energy Saving faculties 2 projects Roof Energy Collection GE Agrobiotech projects
Project (Indoor demo) Proj.TitleIn-chargeProj.TitleIn-charge A1Solar PV Energy*Prof K Y Chan / Prof F.Liu C8Energy Storage (small scale in the indoor demo room, real scale at the roof) Prof K Y Chan A2Wind Energy*Prof D Leung / Prof M Leung C9Solid-State LightingDr Anthony Choi B3Delivering Renewable Energy in DC Microgrids Prof. FF wu/ Dr J Zhong C10Reserved for future B4Smart GridProf V Li Dr Yang C11Reserved for future B5Reserved for futureC12Reserved for future B6Reserved for futureD13Urban ventilationDr CH Liu/ Prof Yuguo Li B7Reserved for futureD14GE AgrobiotechnologyDr Wallace Lim * For energy collection: poster display and web monitoring in the demo room, real installation at the roof
At the roof Facing Chow Yei Ching Bldg Battery and Equipment room at the roof Green roof Micro wind turbine N S
PV panels
The existing solar facilities will be removed except that the supporting frame can be reused. New PV panels will be installed. 10 pcs of 500W PV panels can be hosted in the existing frame. Capacity: 5kW
Covering the building service facilities
Existing building facilities will be covered by plastic grass carpet for appearance improvement and easy maintenance plastic grass carpet
Covering the building service facilities
Existing building facilities will be covered by plastic grass carpet for appearance improvement and easy maintenance
Existing solar facilities to be removed Anther solar facilities including the frame should be removed to provide space for the green house
Existing solar facilities to be removed
Greenhouse for GE agrobiotech demo
Micro wind turbine
Before
After
Battery and Equipment room at the roof Battery and Equipment Room
Project Schedule TasksNovDecJanFebMarAprMayJunJulAug Finalize overall designxxXx Tender building worksxxXx Building worksxxXx Finalize the detailed design of each project Xx Purchase demo materials Xx Lab installation and testing xxXx Installation in the demo room Xx x Posters, display, brochures Xx Testing and dry runXxX Official launch and Opening ceremony xx
Other discussions -The pamphlet for each project [ref. Wallace’s pamphlet – when? Web cam and internet display of demo items? Summer students to help, budget ? ….