CERN/BENE meeting, July 04 2006 Marcos Dracos Collection system for future neutrino beams horn and target integration 2 LoI's sent –CERN –Strasbourg Who.

Slides:



Advertisements
Similar presentations
WP2: Targets Proposed Outline Work Programme Chris Densham.
Advertisements

EuroNu CERN February 5, 2008 Marco Zito Super-Beam work package Marco Zito Dapnia-Saclay On behalf of the SB w2 team EuroNu 5/2/2008 Thanks to M. Dracos.
Participants WP3total Imperial College CERN STFC University Warwick CRNS University Oxford6 6 Total Euro  - WP3.
25/10/2007M. Dracos1 EURO The European Design Study for a high intensity neutrino oscillation facility (Rob Edgecock, Mats Lindroos, Marcos Dracos)
Studies of solid high-power targets Goran Skoro University of Sheffield HPT Meeting May 01 – 02, 2008 Oxford, UK.
Target & Capture for PRISM Koji Yoshimura On behalf of PRISM Target Group Institute of Particle and Nuclear Science High Energy Accelerator Research Organization.
Harold G. Kirk Brookhaven National Laboratory Meson Production Efficiencies IDS Target Meeting CERN December 17, 2008.
Primary Target Systems for a Muon Collider / Neutrino Factory. What has the experimental effort taught us thus far. N. Simos, H. Kirk, S. Kahn, P. Thieberger,
Above: Energy deposition in the superconducting magnet and the tungsten-carbide shield inside them. Approximately 2.4 MW must be dissipated in the shield.
Kirk McDonald Monday, 28th May Report of the International Working Group on Muon Beamlines Bruno Autin, Roberto Cappi, Rob Edgecock, Kirk McDonald,
Collection device : status report Semen Mitrofanov Marc Loiselet Thierry Delbar Flerov Laboratory of Nuclear Reactions Joint Institute for Nuclear Research.
NuFact2004, Osaka, Japan MATERIAL R&D FOR HIGH-INTENSITY PROTON BEAM TARGETS Nicholas Simos, H. Kirk, W-T. Weng, P. Thieberger, (BNL) K. McDonald, Princeton.
Harold G. Kirk Brookhaven National Laboratory Target Baseline IDS-NF Plenary CERN March 23-24, 2009.
30 June 2008M. Dracos, NuFact081 Challenges and Progress on the SuperBeam Horn Design Marcos DRACOS IN2P3/CNRS Strasbourg NuFact 08 Valencia-Spain, June.
17 Dec. 2008M. Dracos, EUROnu-WP21 Collector and the SPL Super-Beam Project Marcos Dracos IPHC-IN2P3/CNRS Strasbourg.
Above: Power deposition in the superconducting magnets and the tungsten-carbide + water shield inside them, according to a FLUKA simulation Approximately.
The MERIT experiment at the CERN PS Leo Jenner MOPC087 WEPP169 WEPP170.
Solid Target Options NuFACT’00 S. Childress Solid Target Options The choice of a primary beam target for the neutrino factory, with beam power of
Harold G. Kirk Brookhaven National Laboratory The High-Power Target Experiment at CERN Muon Collaboration Meeting LBNL February 16, 2005.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
KT McDonald MAP Spring Meeting May 30, Target System Concept for a Muon Collider/Neutrino Factory K.T. McDonald Princeton University (May 28, 2014)
Fermilab Neutrino Beamline to DUSEL Mike Martens Fermilab PAC November 3, 2009.
RAL/BENE meeting, April Marcos Dracos Collection system for future neutrino beams horn and target integration 2 LoI's sent –CERN –Strasbourg.
Horn design for the CERN to Fréjus neutrino Super Beam Nikolas Vassilopoulos IPHC/CNRS.
EUROnu Target and Horn Studies Nikolaos Vassilopoulos/IPHC-CNRS on behalf of WP2 1ECFA Review PanelDarensbury, 02/05/2011.
Brookhaven Science Associates U.S. Department of Energy AGS Upgrade and Super Neutrino Beam DOE Annual HEP Program Review April 27-28, 2005 Derek I. Lowenstein.
The CNGS Horns Electrical Systems The CNGS Horns Electrical Systems 4th workshop on Neutrino Beams and Instrumentation 7 – 11 November 2003 at KEK Gilles.Maire.
Thermomechanical characterization of candidate materials for solid high power targets Goran Skoro, R. Bennett, R. Edgecock 6 November 2012 UKNF Target.
Target & Capture for PRISM Koji Yoshimura Institute of Particle and Nuclear Science High Energy Accelerator Research Organization (KEK)
European design study on Neutrinofacilities - Euronu within FP7.
BENE-CARE meeting, November 14, 2006 Collector work in Strasbourg 2 contributions : preparation of horn tests and definition of supplies and infrastructure.
26/3/03J.E Campagne LAL Horn R&D J.E Campagne, A. Caze (Ph. D), CNGS Horn: G. Macé, S. Wallon New persons: J. Bonis, M. Omesh,… Other IN2P3 members: J.
Harold G. Kirk Brookhaven National Laboratory Targetry Concept for a Neutrino Factory Muon Meeting BNL January 26, 2004.
J. Pozimski UKNF WP1 meeting 10 March 2010 UKNF WP1 milestone table status.
Secondary Particle Production and Capture for Muon Accelerator Applications S.J. Brooks, RAL, Oxfordshire, UK Abstract Intense pulsed.
Harold G. Kirk Brookhaven National Laboratory Target Considerations for Nufact and Superbeams ISS Meeting RAL April 26, 2006.
KT McDonald MAP Tech Board Meeting Oct 20, The MAP Targetry Program in FY11 and FY12 K. McDonald Princeton U. (Oct 20, 2011) MAP Technical Board.
Current Status and Possible Items around ‘neutrino beam’ Horn Target Remote maintenance tools Decay volume window and collimator muon monitor Many items.
RAL/ISS meeting, April Marcos Dracos Collection system, horn (work mainly done by Francis Osswald) goals and perspectives suppliers and collaborations.
Revised SPL-study work-plan W. Weingarten 3 May 20101SPL Cavity WG Meeting.
The CNGS Target Station By L.Bruno, S.Péraire, P.Sala SL/BT Targets & Dumps Section.
K. McDonald MAP Technical Board Meeting Nov 1, FY11 Target System Budget Proposal K. McDonald Princeton U. (November 1, 2010)
ESS based neutrino Super Beam for CP Violation discovery Marcos DRACOS IPHC-IN2P3/CNRS Strasbourg 1 10 September 2013M. Dracos.
Proton Source & Site Layout Keith Gollwitzer Accelerator Division Fermi National Accelerator Laboratory Muon Accelerator Program Review Fermilab, August.
10/9/2007 Global Design Effort 1 Optical Matching Device Jeff Gronberg / LLNL October 9, 2007 Positron source KOM - Daresbury This work performed under.
Jefferson Lab Muon Collider Design Workshop December 2008 Lithium Lens for Muon Final Cooling UCLA K. Lee, D. Cline and A. Garren.
PHIN Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand WP 4 of the JRA2 PHIN 1.Status of the construction of RF guns.
J-PARC neutrino experiment Target Specification Graphite or Carbon-Carbon composite cylindrical bar : length 900mm, diameter 25~30mm The bar may be divided.
DESIGN OF THE BNL SUPER NEUTRINO BEAM FACILITY W. T. Weng Brookhaven National Laboratory Neutrino Super Beam, Detectors and Proton Decay BNL/UCLA/APS Workshop.
Harold G. Kirk Brookhaven National Laboratory The E951 Targetry Program Targetry Meeting CERN September 19, 2003.
EURO EURO A High Intensity Neutrino Oscillation Facility in Europe Introduction Aims Structure Tasks Link to other activities Future dates.
1 BROOKHAVEN SCIENCE ASSOCIATES N. Simos, BNL EUROnu-IDS Target Meeting December 15-18, 2008 Superbeam Horn-Target Integration.
Horns, Hadron production etc. (from hadron production to neutrino beam) A.K.Ichikawa KEK 200/9/26 Study on horns Changing -beam energy Hadron.
From the SPL to the 4-target-horn system: Preliminary design of a beam switching yard WP2: Super Beam 4 th EUROν Annual Meeting, Paris, June 13, 2012 E.
Design for a 2 MW graphite target for a neutrino beam Jim Hylen Accelerator Physics and Technology Workshop for Project X November 12-13, 2007.
Horn and Solenoid options in Neutrino Factory M. Yoshida, Osaka Univ. NuFact08, Valencia June 30th, A brief review of pion capture scheme in NuFact,
BNL solenoid capture workshop: magnet challenges are not trivial Summarized by Tengming Shen
Challenges and Progress on the SB Horn Design
Horn and Solenoid Options in Neutrino Factory
Target and Horn status report
Sébastien Bousson (CNRS-IN2P3-IPN Orsay)
Outline: Why now ? What ? How ?
Accelerator R&D for Future Neutrino Projects
STUDIES TOWARDS TARGET-HORN INTEGRATION Institute of Applied Mechanics
Collector and the SPL Super-Beam Project
EUROnu Beam Window Studies Stress and Cooling Analysis
Superbeam Horn-Target Integration
A High Intensity Neutrino Oscillation Facility in Europe
Explanation of the Basic Principles and Goals
J.-P. Koutchouk CERN & Uppsala University
Presentation transcript:

CERN/BENE meeting, July Marcos Dracos Collection system for future neutrino beams horn and target integration 2 LoI's sent –CERN –Strasbourg Who is working in Europe on solenoid for Neutrino Factory?

CERN/BENE meeting, July Marcos Dracos After some discussion between CERN and Strasbourg Start the collection study for SuperBeam option Taking into account previous tests done at CERN, prepare a setup to pulse the horn at 50 Hz (nominal value) and a current as high as possible Proton beam –2.2 GeV –4 MW –50 Hz rep. rate Horn focusing –First horn 300 kA –Reflector 600 kA Low energy pion beam:  500 MeV –proton energy below kaon threshold –Short decay channel < 100 m Low energy neutrino beam:  250 MeV CERN horn design tests already done at CERN: pulse repetition frequency: 1 Hz Imax: 30, 100 kA C: 1 mF pulse duration: 100  s

CERN/BENE meeting, July Marcos Dracos CERN LoI Target R&D Horn and solid target integration 1.Improve existing infrastructure (at BA7) to allow realistic tests of a NuFact prototype horn at nominal conditions. Analysis of fatigue tests and possible corrective actions. 2.Investigation of the material structure of the existing Nufact horn (480 k€, available) with a 50 Hz power supply (300 kA, 5 kV, <100  s). The investigation will be based on laser vibrometer (100 k€, available) measurements of the horn’s resonance frequencies and of their damping constants with increasing number of cycles. A mechanical analysis (mechanical engineers from Poland/Krakow via T. Kurtyka) should be derived to assess the fatigue of the system (horn and strip line) and its life time (expected to be few month of operations at nominal parameters). 3.Development of a test bench using the NuFact horn and the 50Hz power supply to validate multi-physics simulations in order to reduce the experimental working load and costs (collaboration with Strasbourg). 4.Address the integration issues of the horn. Complete the design of the existing horn including possibly the studies for a target station located in the inside. Investigate the cooling issues involved. (collaboration with BNL). total cost for the collector: 1.35 M€

CERN/BENE meeting, July Marcos Dracos Strasbourg LoI The cavity is submitted to: an electromagnetic wave, thermo-mechanic stresses, vibrations, fatigue, radiation damages. The proposed project intends to quantify all the above parameters in order to propose a robust collector design. Main challenges: design of a high current pulsed power supply (300 kA/100 μs/50 Hz), cooling system in order to maintain the integrity of the horn despite of the heat amount generated by the energy deposition of the secondary particles provided by the impact of the primary proton beam onto the target, definition of the radiation tolerance, integration of the target. Goal establish an experimental setup in Strasbourg, proceed to the qualification and ageing tests develop numerical simulation tools in parallel Estimated cost for 3 years R&D: 2 M€ (less if some parts of the power supply could be provided by CERN)

CERN/BENE meeting, July Marcos Dracos Super-Beams Santa Fe 17/06/2006 (Neutrino06) strengthen the collaboration with these institutes

CERN/BENE meeting, July Marcos Dracos "Physics" studies to be restarted energy deposition z (cm) P (kW) z (cm) corne corne 2

CERN/BENE meeting, July Marcos Dracos New collaborators BNL (Harold Kirk et al.) Princeton U (Kirk McDonald et al.) … CC target He IN He OUT Horn Stationary target:

CERN/BENE meeting, July Marcos Dracos the power supply values considered by CERN

CERN/BENE meeting, July Marcos Dracos Contacts by Strasbourg Comsol, Paris, November 2005 conférence, simulations IN2P3, Paris, October 2005 réseau mécaniciens, simulations ISS, KEK, January 2006, technical discussion with K2K engineers working on horns Atesys, Haguenau, March 2006, discussion on capacitors and strip lines CERN, Genève, March 2006 discussion and technical visit ISL, St Louis, March 2006, discussion on pulsers Technix, Créteil, March 2006 discussion on capacitors charger OpenEngineering, Lièges, March 2006 ABB et ISL, Lenzburg, April 2006, discussion on switches and commutation system ISL, St Louis, April 2006, discussion TPC-AVX, IReS, April 2006, discussion on capacitors and charger MegaGauss, Berlin, May 2006, discussion on pulsers GDR neutrinos, LAL, May 2006, presentation of the project LNCMP CNRS, Toulouse, May 2006, discussion on pulsers and capacitors Certim, Toulouse, May 2006, discussion on commutation systems ISL, ABB et ISP, St Louis, June 2006, establish a collaboration between institutes

CERN/BENE meeting, July Marcos Dracos the power supply Due to the high price go to a modular system and increase small by small the current

CERN/BENE meeting, July Marcos Dracos Charger and commutation 2 MW proposed by Technix 43 racks of 40 kW 400 V / 11 A 40 k€/rack one of the three solutions proposed by ABB commutation

CERN/BENE meeting, July Marcos Dracos Possible financial sources EU (FP7) ANR ( Agence Nationale de la Recherche), 2007 CERN? Alsace Region IN2P3 …

CERN/BENE meeting, July Marcos Dracos preliminary schedule Design of Power Supply: R&D, tests and simulations, feasibility: new horn prototype: 2009