Reliability Must-Run Analysis 2006 – th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006
4th BTA 2 Outline of Presentation 2006 RMR Study Process Description of network and constraint SIL/MLSC determination RMR - demand, energy and duration Economic impact of transmission constraint Observations Comparison of RMR Studies to FERC SIL Studies
June 6, th BTA RMR Study Process Transmission Provider Coordination January 21, 2005 meeting to coordinate plan Decision to study 2008 and 2015 SSG-WI cases to be developed Basic Case Development SWAT Involvement Approve study plan May 4, 2005 Update on study August 23 and October 25 Preliminary results presentation Jan 17, 2006
June 6, th BTA 4 RMR Economic Analysis ABB GridView production-cost simulator Entire WECC modeled Hourly least cost dispatch with transmission constraints Annual cost to serve area load determined Study repeated ignoring local import limit Difference is the RMR cost Environmental impact determined for each generator using emission rates
June 6, 20064th BTA 5 Phoenix Area Load 2008 Critical OutageLimiting Element Jojoba-Kyrene 500kV Kyrene-Corbell 230kV West Phoenix- Lincoln Street 230kV Agua Fria- Glendale 230kV
June 6, th BTA Phoenix Load Serving Capability
June 6, th BTA Phoenix Load Duration and RMR Conditions MW
Phoenix Area Energy Phoenix Area Total Load = 56,651 GWh $0M incremental cost
June 6, 20064th BTA 9 Phoenix Area Load 2015 Critical OutageLimiting Element Jojoba-Kyrene 500kV Voltage Instability
June 6, th BTA Phoenix Load Serving Capability
June 6, th BTA Phoenix Load Duration and RMR Conditions MW
Phoenix Area Energy Phoenix Area Total Load = 72,083 GWh $0M incremental cost
June 6, th BTA 13 Expected Phoenix Reserves
June 6, th BTA 14 Phoenix RMR Observations APS load is expected to exceed import capability for 845 hours in 2008, and 548 hours in RMR energy represents approximately 1% of the total energy. The projected reserves in both 2008 and 2015 are greater than the 99% reliability reserve requirement of 865 MW. Cost to run local generation outside of economic dispatch is less than $1M in both 2008 and Expected RMR costs do not justify Construction costs to relieve RMR requirements.
June 6, 20064th BTA Yuma Transmission System Critical Outage: Hassayampa-N.G. 500kV Limiting Element: Pilot Knob-Yucca 161kV
June 6, th BTA Yuma Load Serving Capability
June 6, th BTA Yuma Load Duration and RMR Conditions
APS Yuma Energy APS Yuma Area Total Load = 1,892 GWh $1.3M incremental cost
June 6, 20064th BTA Yuma Transmission System Critical Outage: Cocopah-Riverside 69kV Limiting Element: Riverside-10 th Street 69kV
June 6, th BTA Yuma Load Serving Capability
June 6, th BTA Yuma Load Duration and RMR Conditions
APS Yuma Energy APS Yuma Area Total Load = 2,492 GWh $0M incremental cost
June 6, th BTA 23 Expected Yuma Reserves
June 6, th BTA 24 Yuma RMR Observations Yuma load is expected to exceed import capability for 1,703 hours in 2008, and 553 hours in The projected reserves in both 2008 and 2015 are greater than the 99% reliability reserve requirement of 138 MW. Cost to run local generation outside of economic dispatch is $1.3M in 2008 and less than $1M in Addition of 100mw of generation in Yuma in 2008 and a new 500kV line from the PV area to North Gila and a 230kV line from North Gila into the Yuma load area effectively manage RMR conditions.
June 6, th BTA 25 Overall RMR Observations Benefits of local generation Increase reliability Local voltage support Contingency response Operating flexibility Reduced losses Lower transmission investment
26 ACC RMR Studies Compared to FERC SIL Studies SELIGMAN ROUND VALLEY POWER PLANT 115KV & ABOVE SUBSTATION (EXISTING) LEGEND NORTH SAGUARO N.GILA PALO VERDE- HASSAYAMPA YUCCA GILA BEND TO CALIF. 500KV REDHAWK JOJOBA GILA RIVER RUDD LIBERTY KYRENE SANTA ROSA DESERT BASIN WEST WING YAVAPAI VERDE PINNACLE PEAK PREACHER CANYON CHOLLA TO CALIF. TO CRYSTAL TO MEAD / MARKETPLACE MOENKOPI NAVAJO FOUR CORNERS TUCSON 5/23/06 Transmission Planning COCONINO Substation locations and line routings depict an electrical connection only and donot reflect any assumed physical locations or routing. CASA GRANDE TAT MOMOLI KNOX GAVILAN PEAK FLAGSTAFF GLEN CANYON EXISTING 500 KV LINES EXISTING 345 KV LINES EXISTING 230 KV LINES EXISTING 115 KV LINES NUCLEAR POWER PLANT CORONADO BROWNING SILVERKING RMR Load Pockets APS control area used for FERC SIL
June 6, th BTA 27 ACC RMR Studies Compared to FERC SIL Studies ACC RMR Studies Load Pockets Phoenix - Combined APS/SRP Yuma SIL Load Pocket import capability with no generation FERC SIL Studies Control Area simultaneous import limit Decrease internal control area generation Increase external control area generation Stop when reach reliability limit
June 6, th BTA 28 ACC RMR Studies Compared to FERC SIL Studies FERC SIL Studies (cont.) Issues FERC methodology not consistent with operations in Western Interconnection TTC calculation Oasis posting Scaling of generation Uniform vs. maximize imports RMR limits for Phoenix & Yuma used in SIL Study FERC did not have issues with Phoenix & Yuma RMR limits