Reliability Must-Run Analysis 2006 – 2015 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.

Slides:



Advertisements
Similar presentations
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Advertisements

WECC TEPPC Meeting SWAT Update
TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.
Arizona Corporation Commission 2008 Biennial Transmission Assessment Workshop I CATS-EHV 2007 Studies Ten Year Snapshot and N-1-1 Jose Silva Salt River.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Arizona Corporation Commission Workshop
Special Open Meeting of the Arizona Corporation Commission Energy Workshop February 16, 2001 Arizona Public Service Company Cary B. Deise Director, Transmission.
2/16/2001ACC Energy Workshop – Summer Preparedness 2001 and SS-1 SRP Summer Preparedness 2001 and 2002 Presented to the Arizona Corporation.
SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW.
9/22/00 1 Jerry W. Smith. 9/22/00 2 Jerry W. Smith.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
Arizona Transmission System Overview November 18, 2014 Tribal Solar Working Group 1.
APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 OATT Attachment K (APS Attachment E) APS Transmission Planning SRP Transmission Planning.
Available Transfer Capability Determination Chen-Ching Liu and Guang Li University of Washington Third NSF Workshop on US-Africa Research and Education.
2006 BTA 8/5/ SSC-1 ACC BTA Requirements SRP’s Ten Year Plan Presentation Chuck Russell Salt River Project June 6, 2006 Phoenix, Arizona Arizona.
Preliminary Analysis of the SEE Future Infrastructure Development Plan and REM Benefits.
NW Transmission System Bottlenecks and Impacts of 2005 Summer Operation BPA Transmission Business Line Mike Viles January 2006.
Arizona Renewable Transmission Task Force BTA Response Chairman of SWAT RTTF Peter Krzykos Peter Krzykos BTA Workshop May
1 STEP Southwest Transmission Expansion Plan. 2 Southwest Transmission Expansion Plan (STEP) Subregional planning group formed in November of 2002 Coordinates.
ISO Grid Planning Presentation to CREPC October 1, 2002
Charles Hosken, General Manager Imperial Irrigation District
5/23/08ACC 5 th BTA Workshop – Phoenix - SWAT – RE Kondziolka 1 SWAT Subregional Planning Group Update Arizona Corporation Commission Fifth Biennial Transmission.
 2005 Pinnacle West Capital Corporation Special Open Meeting of the Arizona Corporation Commission 2005 Summer Assessment March 18, 2005 Arizona Public.
Base Case Draft – For Comment Rocky Mountain States Sub-Regional Transmission Study December 9, 2003.
Arizona ACC Biennial Transmission Assessment Navajo Transmission Project Update May 22, 2008 Presentation by Ben Hoisington Project Administrator, DPA.
CRR Auction Scope John Moseley. To outline aspects of the CRR market process to assure that these proposed CRR market protocols (as interpreted by ERCOT.
APS Ten-Year Plans th BTA Presentation John Lucas Manager Transmission Planning May 22, 2008.
Sixth Northwest Conservation & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Northwest Power and Conservation Council Generating.
BTA Workshop May 22, 2008 Ten-Year Transmission Plan for the Santa Cruz Water & Power Districts Association (“Santa Cruz”) 10/26/2015K.R. Saline & Assoicates,
Arizona Corporation Commission Energy Workshop February 16, 2001.
APS Overview Richard Nicosia. APS Snapshot Largest and longest serving electric utility Operations dating back to th largest employer headquartered.
03/22/07 ACC Open MeetingSummer Preparedness SRP Summer Preparedness 2007 Mike Hummel Manager – Supply & Trading and Gary Harper Manager - System.
Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30,
Updated 1/28/2011.
RGGI Workshop on Electricity Markets, Reliability and Planning Topic Session 3: RGGI Design, Markets and Reliability – Issues Relating to System Operations.
1 Arizona Renewable Transmission Task Force BTA Response Chairman of SWAT RTTF Peter Krzykos Peter Krzykos ACC Meeting Oct
ACC Summer Preparedness Hearing Tucson Electric Power & UNS Electric March 22, 2007 Ed Beck Superintendent Transmission & Distribution Planning.
“DRAFT” RMATS 2008 Base Case (To be presented at the RMATS Stakeholders Meeting) March 17, 2004.
© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.
12/15/ SS-1 Arizona Corporation Commission Special Open Meeting Gary Harper Manager, System Operations July 23, 2004 Phoenix, Arizona.
APS Ten-Year Plans th BTA Presentation
1 CATS HV Status Report Presented to the 2008 BTA Workshop May 22, 2008.
APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility – Scottsdale, AZ December 15 th, 2015.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
Southern California Edison The San Onofre Nuclear Generating Station April 14, 2011.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
Analysis of Demand Response Modeling in GridView Andy Satchwell and Sarah Smith Modeling Work Group December 21, 2015 The work described in this presentation.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects — The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December.
PC21 Coal Retirement Study TAS/TEPPC – Nov W ESTERN E LECTRICITY C OORDINATING C OUNCIL WECC System Adequacy Planning.
ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.
APS Top Renewable Transmission Projects Arizona Public Service Company November 23, 2009 Brian Cole John Lucas.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
A new Nomogram Development POM- based tool - Application results in the Idaho Power System. Orlando Ciniglio, IPC Marianna Vaiman, V&R Energy WECC TSS.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
N-1-1 Contingency Analysis & Relay Protection 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.
Arizona Extreme Contingency Analysis 2009 & th BTA Presentation Jonathan Stahlhut, Ph.D. Transmission Planning Engineer, APS May 22-23, 2008.
3/18/ FUTURE LINES EXISTING LINES FUTURE 500kV SUBSTATIONEXISTING 500kV SUBSTATION ATTACHMENT A SALT RIVER PROJECT 500kV SYSTEM January 23,
TEP RMR Workshop Presentation1 Workshop on ACC RMR study submitted with 2004 ten year plan Tucson Electric Power January 15, 2004 Ed Beck Supervisor Transmission.
APS/SRP 2 nd Quarter Stakeholder FERC Order 890 APS Attachment E SRP Attachment K APS Deer Valley Facility Phoenix, Arizona June 21, AM -12 PM.
Navajo Transmission System
APS Deer Valley Facility Phoenix, Arizona June 22, AM -12 PM
APS Resource Management February 10, 2017
Wind Management at MISO
Barrilla Junction Area Transmission Improvements Project
Deliverability Maps for 2017 Peaking Capacity RFP
Planning Tools Overview
Planning Tools Overview
Acadiana Load Pocket Project
Presentation transcript:

Reliability Must-Run Analysis 2006 – th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006

4th BTA 2 Outline of Presentation  2006 RMR Study Process  Description of network and constraint  SIL/MLSC determination  RMR - demand, energy and duration  Economic impact of transmission constraint  Observations  Comparison of RMR Studies to FERC SIL Studies

June 6, th BTA RMR Study Process  Transmission Provider Coordination January 21, 2005 meeting to coordinate plan Decision to study 2008 and 2015  SSG-WI cases to be developed Basic Case Development  SWAT Involvement Approve study plan May 4, 2005 Update on study August 23 and October 25 Preliminary results presentation Jan 17, 2006

June 6, th BTA 4 RMR Economic Analysis  ABB GridView production-cost simulator  Entire WECC modeled  Hourly least cost dispatch with transmission constraints  Annual cost to serve area load determined  Study repeated ignoring local import limit  Difference is the RMR cost  Environmental impact determined for each generator using emission rates

June 6, 20064th BTA 5 Phoenix Area Load 2008 Critical OutageLimiting Element Jojoba-Kyrene 500kV Kyrene-Corbell 230kV West Phoenix- Lincoln Street 230kV Agua Fria- Glendale 230kV

June 6, th BTA Phoenix Load Serving Capability

June 6, th BTA Phoenix Load Duration and RMR Conditions MW

Phoenix Area Energy Phoenix Area Total Load = 56,651 GWh $0M incremental cost

June 6, 20064th BTA 9 Phoenix Area Load 2015 Critical OutageLimiting Element Jojoba-Kyrene 500kV Voltage Instability

June 6, th BTA Phoenix Load Serving Capability

June 6, th BTA Phoenix Load Duration and RMR Conditions MW

Phoenix Area Energy Phoenix Area Total Load = 72,083 GWh $0M incremental cost

June 6, th BTA 13 Expected Phoenix Reserves

June 6, th BTA 14 Phoenix RMR Observations  APS load is expected to exceed import capability for 845 hours in 2008, and 548 hours in RMR energy represents approximately 1% of the total energy.  The projected reserves in both 2008 and 2015 are greater than the 99% reliability reserve requirement of 865 MW.  Cost to run local generation outside of economic dispatch is less than $1M in both 2008 and  Expected RMR costs do not justify Construction costs to relieve RMR requirements.

June 6, 20064th BTA Yuma Transmission System Critical Outage: Hassayampa-N.G. 500kV Limiting Element: Pilot Knob-Yucca 161kV

June 6, th BTA Yuma Load Serving Capability

June 6, th BTA Yuma Load Duration and RMR Conditions

APS Yuma Energy APS Yuma Area Total Load = 1,892 GWh $1.3M incremental cost

June 6, 20064th BTA Yuma Transmission System Critical Outage: Cocopah-Riverside 69kV Limiting Element: Riverside-10 th Street 69kV

June 6, th BTA Yuma Load Serving Capability

June 6, th BTA Yuma Load Duration and RMR Conditions

APS Yuma Energy APS Yuma Area Total Load = 2,492 GWh $0M incremental cost

June 6, th BTA 23 Expected Yuma Reserves

June 6, th BTA 24 Yuma RMR Observations  Yuma load is expected to exceed import capability for 1,703 hours in 2008, and 553 hours in  The projected reserves in both 2008 and 2015 are greater than the 99% reliability reserve requirement of 138 MW.  Cost to run local generation outside of economic dispatch is $1.3M in 2008 and less than $1M in  Addition of 100mw of generation in Yuma in 2008 and a new 500kV line from the PV area to North Gila and a 230kV line from North Gila into the Yuma load area effectively manage RMR conditions.

June 6, th BTA 25 Overall RMR Observations  Benefits of local generation Increase reliability  Local voltage support  Contingency response  Operating flexibility Reduced losses Lower transmission investment

26 ACC RMR Studies Compared to FERC SIL Studies SELIGMAN ROUND VALLEY POWER PLANT 115KV & ABOVE SUBSTATION (EXISTING) LEGEND NORTH SAGUARO N.GILA PALO VERDE- HASSAYAMPA YUCCA GILA BEND TO CALIF. 500KV REDHAWK JOJOBA GILA RIVER RUDD LIBERTY KYRENE SANTA ROSA DESERT BASIN WEST WING YAVAPAI VERDE PINNACLE PEAK PREACHER CANYON CHOLLA TO CALIF. TO CRYSTAL TO MEAD / MARKETPLACE MOENKOPI NAVAJO FOUR CORNERS TUCSON 5/23/06 Transmission Planning COCONINO Substation locations and line routings depict an electrical connection only and donot reflect any assumed physical locations or routing. CASA GRANDE TAT MOMOLI KNOX GAVILAN PEAK FLAGSTAFF GLEN CANYON EXISTING 500 KV LINES EXISTING 345 KV LINES EXISTING 230 KV LINES EXISTING 115 KV LINES NUCLEAR POWER PLANT CORONADO BROWNING SILVERKING RMR Load Pockets APS control area used for FERC SIL

June 6, th BTA 27 ACC RMR Studies Compared to FERC SIL Studies  ACC RMR Studies Load Pockets  Phoenix - Combined APS/SRP  Yuma SIL  Load Pocket import capability with no generation  FERC SIL Studies Control Area simultaneous import limit  Decrease internal control area generation  Increase external control area generation  Stop when reach reliability limit

June 6, th BTA 28 ACC RMR Studies Compared to FERC SIL Studies  FERC SIL Studies (cont.) Issues  FERC methodology not consistent with operations in Western Interconnection TTC calculation Oasis posting  Scaling of generation Uniform vs. maximize imports RMR limits for Phoenix & Yuma used in SIL Study  FERC did not have issues with Phoenix & Yuma RMR limits