LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 14 December 2010.

Slides:



Advertisements
Similar presentations
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
Advertisements

Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 25 May 2011 Overall.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Compressor status AWAKE Technical Board meeting 19 May 2015.
NTOF11 Collaboration Meeting Non-Design Issues for the Mercury Jet Target P.T. Spampinato V.B. Graves T.A. Gabriel Princeton University April 29-30, 2005.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 December 2013 LAV construction & installation status.
LAV construction status Matthew Moulson (Frascati) NA62 Photon-Veto Working Group Meeting CERN, 27 May 2009.
LAV damage and repair – M. Moulson (Frascati) – Photon Veto WG – CERN – 5 April 2011 Damage to A3 during transport 2 10 blocks were broken during transport.
STF EP, VT commissioning by FNAL AES001 H. Hayano, KEK
LAV Software Status Emanuele Leonardi – Tommaso Spadaro Photon Veto WG meeting – 2015/03/24.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
RP detectors CTS Sensors now in production, full delivery between February and June 07 Production GUI and DB being finalised Test Procedure being defined.
Compressor status AWAKE Technical Board meeting 19 August 2015.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
CMS FPIX Cooling System Studies Joe Howell, Fermilab for the FPIX Upgrade Mechanical Working Group CMS Upgrade Workshop April 27,
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 23 May 2012 Notes on A8 transport 2 ShockLog malfunction: fresh batteries consumed.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting Liverpool, 28 August 2013 LAV construction & installation status.
ATLAS Endcap Signal Feedthrough Project Status Report Pin carrier Procurement Summary Feedthrough Production QA/QC Shipment to CERN Reception Tests at.
Status of the Beetle Readout for the MaPMTs  history of events  documentation of setup  prospects of near future RICH meeting, CERN, Stephan.
EMCal Status ALICE Technical Board November 20, 2008 News Schedule.
Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 July 2012 LAV construction & installation status.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
ROBOX with Multi Anode PMT’s Status and plans A.Mestvirishvili, I. Schmidt, S. Sen, F. Ozok University of Iowa.
Ckov status David Lange, Doug Wright LLNL May 4, 2004.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 12 Jul 2011 LAV construction status: a snapshot 2 A1 Arrived at CERN 29 Jun.
Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit.
LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting Brussels, 8 September.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
ProjectImpactResourcesDeadlineResourcesDeadline Forecast Plan Time Resources Risk 001xx 002xx 003xx 004xx 005xx 006xx 007xx TotalXX Example 1: Portfolio.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Dec
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 4 June 2013 LAV construction & installation status.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 11 December 2012 LAV construction & installation status.
SiW ECAL: the status before Fermilab Marcel Reinhard LLR – Ecole Polytechnique CALICE caollaboration meeting 18/03/08, Argonne.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – Siena – 28 August 2012 A11 transport 2 Departure for CERN 24/07 with delivery originally.
LAV HV repair status – M. Moulson (Frascati) – Photon Veto WG – CERN – 09 February 2016 Vaqtec feedthoughs with PEEK base 2 Air side Vacuum side 3 prototypes.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status.
BNL-SLAC-Annecy TeleConference
Cryostats for superconducting magnets
LAV HV repair plans Matthew Moulson
Installation of the T600 at Fermilab
BSS Prep work at CERN and Acceptance of Parts
SCHEDULE Nov 1st - Assembly Table Complete
S1-G Webex meeting Global Design Effort
Renovation of the 45-year old PS magnets
EHN1 Neutrino Installation Plans
Far Detector Activities Late 2017 – Early 2018
Average Monthly Temperature and Rainfall
STAR TOF MRPC Mass Production & Q.C. (USTC)


NEMSIS V3.5.0 Timeline developed at NEMSIS Annual Meeting 2017
Presentation transcript:

LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 14 December 2010

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Summary & timeline from Bruxelles 2 A2 delivered to CERN for test beam at T9 on 05 Aug Currently in storage at B185 All transports smooth, no problems A3 vessel delivered to Frascati 06 Aug All blocks and bananas complete, 1 layer mounted Expect to finish by mid Oct A4 vessel under construction Expect delivery end Sep All bananas ready by mid Oct, can begin mounting when A3 ships A5 vessel delivery planned for end Nov

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Optimization of banana cabling Old cabling New cabling Signal & HV Signal, HV & LED LED LED Signal & HV “Internal” cabling of bananas: Equalizes apparent cable lengths Facilitates vessel cabling Evidence of signal/LED crosstalk at A2 test Separate signal and LED cables

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Cabling optimizations for A3 480 cables in A1-A5 (2.2 km) Strong tendency to get unruly! Cable grille enlarged (40 → 50 cm) Additional TLC used in routing Very good results obtained

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Cabling optimizations near flanges A2 A3 A3 Slack at flange exit difficult to handle Advantages from neater cabling work Add retaining grill to keep cable slack out of acceptance Virtually no cable slack in acceptance!

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 A3 finishing, packing, and shipping 6 A3 rotated to horizontal 26 Nov and closed 27 Nov for final vacuum test Leak tested and pumped down to 2 × 10 −5 mbar by afternoon of 29 Nov Rotated to vertical 29 Nov for final packing Vibration and temperature monitored from start of final handling until arrival at CERN 30 Nov 10:41 30 Nov 11:23

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 A3 transport chronology 7 30 Nov 11:30Departure from Frascati 30 Nov 13:30Return to Frascati to rebalance load 30 Nov 14:30Re-departure from Frascati 30 Nov 19:00Stopped at Ivrea due to road closing 01 DecSupposedly stopped at Ivrea all day 02 Dec 09:00Arrival at Ferney Customs 02 Dec morningLoad shifted at EHN1 02 Dec 16:20Accelerometers dismounted Unloading/rotation at ECN3

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 A3 transport: Vibration log 8 Accelerometer settings Warning/alarm thresholds: 1g/3g 40 Hz low-pass filter to avoid saturation by low-amplitude road noise # fastened to A2 No events during entire period on the road! Accelerometer removed during handling at CERN 107 warnings and 1 alarm during accelerometer removal and return trip #20070 – bolted to truck bed Data useless – battery appears to have died ShockLog unit is currently being tested in our laboratory

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 A3 transport: Temperature log Temp [ ∘ C] 13:30 30 Nov 22:30 30 Nov 07:30 01 Dec 16:30 01 Dec 01:30 02 Dec 10:30 02 Dec 19:30 02 Dec Mass and insulation do provide some protection But, after 2 days in the cold, A3 reached 5 ∘ C

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Problems with temperature logging 10 Some evidence of (battery induced?) temperature logging problems A3 transp.Return transp. Why a broad band? 1000 s 80 s900 s

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Block inventory and testing total in V. Palladino’s database 2095 inspected (incl. 412 top layer) 1382 not inspected (all from top layer) 225 bad 310 “on hold” criteria too strict? 1560 good 742 processed 818 available New LabView interface for oven integrated into production chain: Current and rate tests at 3 HV settings, including individual working point What to do about 1692 blocks of unknown status? Procedure: 1.Temp. HV connector (Burndy) 2.Final signal connector w/ adapter 3.Normal oven run 4.Obtain HV working point 5.Rate and current test Tests performed for all blocks Results added to LAV RDB More than 100 blocks tested so far No blocks with rates > 10 Hz at working point

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Difficulties with top-layer blocks 12 Very sticky residue Anti-corona resin Anti-coronal resin burned through with desoldering tool (250 ∘ C) Toxic fumes Clogging Chemical armamentarium to remove glue Acetone iPr-OH Label removers

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Status of block/banana processing StationLayer 1Layer 2Layer 3Layer 4Layer 5Complete Block type A % A % A515 60% Bananas with long cables* A4: All blocks/bananas complete A5: 60% of blocks/bananas complete 84 blocks in bananas 18 blocks reinforced 10 Dec

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Summary & revised timeline 14 A3 vessel delivered to CERN 30 Nov Some construction delay from re-optimization of cabling scheme Transport rendered difficult by inclement weather A4 vessel delivery postponed until 30 Nov All bananas ready since end of Oct 2 layers currently mounted Expect to deliver to CERN at end of Jan A5 vessel construction on schedule Will take delivery when A4 finished Bananas 60% complete Expect to deliver to CERN mid Mar A1 should return to Frascati on deadhead leg of A5 transport Cannot use (e.g. in synchronization run) without overhaul Expect turnaround by mid May: only slight delay on start of A6

LAV construction status – M. Moulson (Frascati) – CERN – 14 December 2010 Status of A6-A8 and beyond 15 Recall: A9, A10 same dimensions as A11, but are made of stainless steel A12 has open geometry—design is totally different Meeting tomorrow (15 Dec) with Fantini Final A6-A8 design revisions Definition of construction schedule Green-light purchase of construction materials Indicative construction dates for A6 vessel Construction start: first week of Feb 2011 Delivery: mid April 2011 A6-A8 5 layers ∅ 259 cm A11 4 layers ∅ 299 cm