BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel.

Slides:



Advertisements
Similar presentations
Refrigeration Systems
Advertisements

Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Page 1 MDS Installation. Page 2 Contents  Introduction  Outdoor Unit Installation  Indoor Unit Installation  Refrigerant Pipe Work  Gas Charge 
Summery of Cooling System Teflon Leaks* *This is independent of the internal problems Rob Pisani.
© 2012 Rinnai America Corporation Rinnai Circ-Logic (RCL)
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
Warm magnets and the remote handling system in the J-PARCν beam line E. Hirose, K. H. Tanaka, Beam Channel Group.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Low Voltage Power Requirement of TOF FEEs. Maximum tray. Low Noise:  Periodic and Random Distortion (PARD) < few mV RMS Floating.
Point 5 - Cooling Network - Key Primary Water Chilled Water Mixed Water Eau Bruite Standard Power Diesel Backup Comp Air Primary Water at 20-25C – Produced.
Cryogenics for LCGT Technical Advisory Committee for LCGT ICRR SUZUKI, Toshikazu High Energy Accelerator Research Organization.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
GIF++ gas systems 21/01/2014Ernesto, Roberto PH-DT-DI gas service1.
Utilities 14 October 2008 Martin Nordby, Gordon Bowden.
Camera Pieces in Box TV Battery Battery Charger Camera Sun shade.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
IPN Lyon ILD Mechanical structure April 2012 DHCAL Assembly, Tooling, Cooling J.C Ianigro - IPN Lyon -
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Safety Requirements and Regulations 10/3/20121Safety Requirements & Regulations James Sears.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
J. Direito - M. Battistin – 28 th May 2010EN/CV/DC J. Direito, M. Battistin (EN/CV/DC) 28 th May 2010 Detector Cooling Project III Thermosiphon Workshop.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Chiller control system Specification meeting Lukasz Zwalinski – PH/DT.
Claudio Bortolin 03/09/2012. SPD (RP analyses required) 1) Pump 17b replacement and leak test 2)Pressure test on the old inlet lines (technicians coming.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Water Detectors The materials included in this compilation are for the use of Dwyer Instruments, Inc. potential customers and current employees.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Cooling plant upgrade Jose Botelho Direito, Michele Battistin, Stephane Berry, Sebastien Roussee 2 nd SPD Cooling Workshop 30/11/201112nd SPD.
Integration studies – Part 1 Inner triplet Y. Muttoni TS-ICC-LI 31 July 2008.
January 4, 2007 RHIC II Project Internal Cost Review Existing RHIC power supply Modifications Don Bruno & George Ganetis January 4, 2007 Power Supply Modifications.
IBL Mock up Mounting procedure V.2 François-Xavier Nuiry Simon Feigl
BGV 03-nov-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : status and TS3 installation plans Valdir & Massi.
YETS activities in n_TOF O. Aberle, S. Montesano (EN/STI)
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
Installation of the T600 at Fermilab CSN2, September 22,
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Design of the thermosiphon Test Facilities Thermosiphon Cooling Review A. MORAUX PH Dpt / DT Group CERN SEPTEMBER.
Preparation for TS3 Mariana Rihl. Known issues Implications on light leaks on all modules – Visible on current feedback of bias – Confirmed by study performed.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
05/12/2014 Gerrit Jan Focker, BE/BI/PM 1 PSB-Injection H - and H 0 Dump detectors and Stripping Foil current measurement.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Tracker cooling status General status Production: Manifolds, Distribution lines Work at P5 Plan Conclusions 19/05/091E. Focardi.
DCal-ALICE integration and installation plan and status A. Tauro.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
MVD COOLING STATUS COOLING PLANT UPDATE: -ADDITION of the NEW CIRCUITS FOR GBT AND DC-DC Converter BOARDS IN THE COOLING PLANT -THERMAL STUDY OF GBT AND.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 LHCb - Install Meeting 24/05/06 TS/CV/DC activities for LHCb: - IT, TT, OT & SPD/PS, RICH.
MVD COOLING STATUS COOLING PLANT: -UPDATE of THE HYDRAULIC SYSTEM -INTEGRATION OF THE MVD COOLING CIRCUIT PATHS INSIDE THE PANDA AREA -DEFINITION OF THE.
BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 1 BGV cooling : status and plans reporting on behalf of EN-CV (Sylvain Nichilo & Olivier Crespo-Lopez)
Fan Coil Controller FC/S 1.1
Status CO2 Cooling IBBelle: Reconnection after Belle II Roll in
Installation of the T600 at Fermilab
Cryomodule test stand at ESS site
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
Gas System Commissioning
VELO Thermal Control System
cooling for BGV modules
Christian Veelken last updated 11/09/06
Pixel cooling specifications
Tracker cooling loop “check out” draft for discussion
Teleconference ACS – FREIA 31st October 2017
VELO Thermal Control System
COOLING & VENTILATION INFRASTRUCTURE
ROD assembly and test in US
First Assembled Rod in US
Presentation transcript:

BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 2reminder  estimated length = 20m, by Yvon Muttoni  insulation: Armaflex 48m  Will cut to exact length in situ chiller manifold box UA43 RA43

BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 3 Future tests Point 8: 1. check of manifold integrity (closed-loop test), check for frost and leaks 2. connect external PT100 in manifold and test 3. connect to network and test remote control 4. integrate PrestoA80 winCC control to BGV winCC 5. define approximate valve adjustements for flow equalization 6. cross check 4 visual flow-meters with Petr's flowmeter 7. test with dummy restrictions (simulating modules) on all 4 lines. 8. test interlock from gas flow do we need filters on chiller ?

BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 4 Future tests: LHC tunnel Install1: (chiller & manifold) 1. transport chiller and manifold (with closed loops) from point to LHC-TNL 2. make electrical connection of chiller 3. connect TL to chiller (finalize insulation after Tests!) 4. fix manifold in tunnel floor (bolts ?), connect TL to manifold (finalize insulation after Tests!) 5. connect PT100 cable (chiller manifold) 6. connect compressed air to manifold 7. connect interlock cable (chiller airflow) 8. connect network cable for Presto A80 Test1: 1. fill chiller, circulate, refill, check coarse losses (have enough C6F14) 2. test air flow to manifold, test interlock from gas flow 3. check circulation, frost & leaks=> if success, finalize insulation 4. test external PT test remote control Install2: (manifold detectors) 1. install cooling lines and compressed air lines 2. connect cooling and compressed air lines (manifold - modules) Test2: 1. test module cooling, circulation, readjust valves for flow equalization 2. check for frost & leaks on modules=> if success, finalize insulation in red : prepare in advance in blue: mostly in RA43 in black: mostly in UA43 in red : prepare in advance in blue: mostly in RA43 in black: mostly in UA43 independent of detector modules

BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 5 prepare in advance  manifold: –connect the four supply lines to the 4 returns lines –PT100 installed inside, connector outside. –fixation bolts ? who ?  cables from chiller to detector: –PT100 external (4-wire shielded cable, could be a cat6 network cable) –interlock from air flow (what cable ?)  cable from chiller to racks: –network cable  other stuff: –enough spare C6F14 (20 liters ?) –spare insulation material (tape, armaflex, etc) –velcroz strips

BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 6 Who ? When ? Who:  mostly Valdir and Massi, but contributions by others are welcome  maybe some help from EN-CV ? When:  cables should/could be prepared beforehand (short access ?)  Install1 & Test1 is probably an 8h day of work  Install2 & Test2 is another 8h day of work  Long-term leak/frost tests would of course require more time