Measurement and Payment Module #5 Prepared by Dr. Randy R. Rapp July 2005.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Construction Engineering 221
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
Contract CloseOut.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
CARLIN LAW GROUP, APC Dispute Resolution Procedures Contract Claims Requirements Public Contract Code § (schools) Public Contract Code §20104 Government.
Cargo Direct International
Funds administration, also referred to as funds control, funds disbursement, funds management, and escrow, is a method that sureties use to offset the.
NMDOT 2013 Specifications- Section 100 Presented by: Rod Billingsley Billingsley Engineering, P.C. Las Vegas, NM.
Chapter18 Contract Construction 1CE 417, King Saud University.
Security of Payment workshop Andrew Robertson Important Disclaimer: The material contained in this publication is comment of a general nature only and.
4/13/2017 1:54 PM.
1 MOSS ADAMS LLP | 1 Case Studies in Contract Close Out Audits May 2014.
14.21 Contract Closeout Procedure Update Notice of Completion, Release of Retention and Punchlist Resolution December 8, 2005.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
I n t e g r i t y - S e r v i c e - E x c e l l e n c e Pacific Air Forces 1 Contractor Progress HQ PACAF/LGC.
Chapter 5 Cost Estimating and Bidding BCN 4708 Fall 2008.
On-Call Signal Contract Options for Discussion March 13, 2015 Cape Cod Joint Transportation Committee.
/1.401/ESD.018 Project Management Lecture 20 Project Reporting Project Close-out Samuel Labi and Fred Moavenzadeh Massachusetts Institute of Technology.
Project Close Out CTC-470.
Conditions of the Contract for Construction
Subcontracting. Subcontractors % of work is subbed –Significant impact on costs and schedule –Want to develop a working relationship with good.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
AN INTRODUCTION TO: from the leading resource for education and information in the repair industry... TECHNICAL GUIDELINE S Guide for Methods of Measurement.
State Auditor’s Office Change Order Pricing Practices Performance Audit of Eight Local Governments Puyallup City Council February 7, 2012 Chris Cortines,
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Construction Accounting & Financial Management, 3/e Steven Peterson © 2013 by Pearson Higher Education, Inc Upper Saddle River, New Jersey All Rights.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
Changes To California’s Mechanic’s Lien Laws: Effective January 1, 2012 and July 1, 2012 Hanson Bridgett LLP.
CEM 520 Construction Contracting Dr S. Almohawis Course Content.
IDENTIFYING THE STRENGTHS & WEAKNESSES OF YOUR CONSTUCTION PROJECT McCune Construction Services Group, L.C.C.
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
CIVL202 Construction Engineering I Tutorial 5 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
CVE 4070 Construction Engineering Disaster Recovery Prof. Ralph V. Locurcio, PE.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Measurement and Payment
CHANGE ORDER & BACKCHARGES PREPARED BY ABDULAZIZ M. AL-BESHR ID# PREPARED FOR Dr. ABDULAZIZ BUBSHAIT.
CONSTRUCTION CONTRACTS DOCUEMENTS
TYPES OF CONTRACTS.
Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)
Chapter 15 Payments. Payments typically made monthly. Retainage typically withheld (5% - 10%) Project payment: –series of periodic payments –single final.
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
Project Cash Flow.  In order to make a workable project plan, the resources needed for the project and their availability must be checked.  Money is.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
1 Test Operations Contract RFP Volume III ITO Briefing RFP NNS09ZDA008R – TEST OPERATIONS CONTRACT (TOC) Ground rules This presentation is intended to.
Service Quality Innovation Trust Safety The Samet Way “Managing the Company Cash Position” Accounts Payable (AP) should always be less than Accounts Receivable.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
 Section Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days.
Office of Procurement Services.  Vendor Application Website: 
Measurement and Payment
TOPIC-7- PROJECT CASH FLOW
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
P ART A - S TANDARDS A NNUAL ‘A’ B OOK R EVIEW  Conducted by City of Toledo -Division of Engineering Services  Review Typically performed in Q4.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Subcontractors and Suppliers Procedures for Receipt of Payment.
Presented by: Brienne Berscheid Assistant Vice President & Construction Escrow Underwriter Construction Escrow Documentation Requirements.
COST PLUS. Reasons for Cost-Plus Can’t agree on a price Specialty work Notice of Changed Conditions.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Administration of a FIDIC Contract - Financial Management
Estimating Project Costs
What Small and Emerging Contractors Need to Know Understanding Funds Administration © Copyright 2017 NASBP.
TOPIC-7- PROJECT CASH FLOW
Kick-Off Meeting Administrative Items
TOPIC-7- PROJECT CASH FLOW
ARCH 435 PROJECT MANAGEMENT
Presentation transcript:

Measurement and Payment Module #5 Prepared by Dr. Randy R. Rapp July 2005

2005, Randy R. Rapp2 Contractual Payment Lump-sum or fixed-price Unit-price Fixed-price with cost incentives Time and materials (T&M)

2005, Randy R. Rapp3 Progress Payments Typically monthly Contractor request maybe 10 days prior Lump-sum vs. unit-price verification Inspector role –Measure quantity and type of work –Claims for extra work and change orders –Calculate payment due, minus retention –Prepare and forward recommendation Lump-sum vs. unit-price payment basis

2005, Randy R. Rapp4 Conflicting Bases of Payments? Specification writer misunderstands? Lump-sum contract –Schedule of values OR –Cost-loaded critical path method (CPM) network Unit-price –Neither schedule of values NOR –Cost-loaded CPM

2005, Randy R. Rapp5 Payment Request Evaluation Lump-sum: completed work package –Discernable fraction thereof is usually OK –Consider change orders, if any Unit-price: quantity x unit-price –Measurement accuracy absolutely essential –Renegotiate unit-price, if quantity exceeds allowable variation (15% to 25%) Equipment and materials delivered but not yet installed –Maybe pay actual cost for long-lead, high-cost items –Only if contract specifically stipulates

2005, Randy R. Rapp6 Force Account Day work Measurement and Payment section OR Changes and Extra Work section “Reasonable” allowance for overhead and profit? Categories –Labor –Materials –Equipment Payment is full compensation for the work

2005, Randy R. Rapp7 Force Account (Cont’d) Labor –Trade classification wage rate and numbers –Foremen included, not general supervisors –Any allowances? Materials: cost and freight Equipment –DOT rates or Rental Rate Book –Active and standby times Markups (p.85)

2005, Randy R. Rapp8 Payment for Extra Work Often detailed in Supplementary General Conditions

2005, Randy R. Rapp9 Payment for Mobilization Lump-sum contracts –Not included as a bid item: likely inflated –Include as a calculated allowance in separate technical section, per contract requirements –Not a matter of Measurement and Payment Unit-price contracts –Properly in Measurement and Payment –Lump-sum amount stipulated in extended column

2005, Randy R. Rapp10 Partial Payments Partial waivers of lien (subs’ waivers maybe one payment behind prime contractor’s) Total cost pricing of change orders Forward pricing of change orders Retainage Liquidated damages

2005, Randy R. Rapp11 Field Measurement for Payment Pipeline lengths –Beware delivered vs. plan or in-place –If in-place, measure centerline on top Earth and rock volume –Bank vs. compacted –Weight vs. volume (survey profile prior to work) Curbs: top edge toward street Sewers: do not include manholes Fence: plan or top rail in-place

2005, Randy R. Rapp12 Field Measurement for Payment (Cont’d) Pavement –Areas or weights –Unit-prices for handwork vs. equipment Retaining walls –Inside vs. outside surface measurement –Calculate non-overlapping prism volumes

2005, Randy R. Rapp13 Final Payment Additional requirements 1.Pay all project debts 2.Submit receipts, releases, waivers of lien 3.Obtain consent of surety Besides retainage 1.Liquidated damages 2.Punch list work (1.5 to 2 times value) 3.Liens already filed Upon filing Notice of Completion or Substantial Completion –Sometimes time limitation to announce intent to file lien –Time limitation to actually file