20 FEBRUARY 2013 STANDING COMMITTEE ON APPROPRIATIONS (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)) 1.

Slides:



Advertisements
Similar presentations
BUCKET ERADICATION PROGRESS SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS 22 & 23 February 2007 Presented by Ms. T. Mpotulo Department of.
Advertisements

REPORT ON PROCUREMENT AND DELIVERY OF LTSM FOR THE 2015 SCHOOL YEAR PORTFOLIO COMMITTEE ON EDUCATION 24 FEBRUARY 2015.
20 August 2013 SCOA (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI) 1.
BRIEFING ON NATIONAL SCHOOL NUTRITION PROGRAMME PORTFOLIO COMMITTEE ON EDUCATION 15 MAY 2007.
1 ALLOCATIONS for the Integrated National Electrification Programme 2009/10 Presentation to the Select Committee on Finance 25 February 2009.
Department of Arts and Culture Presentation to the Select Committee on Appropriations: 08 May 2013 Community Library Services Grant Mr Sibusiso Xaba Director.
1 PRESENTATION TO THE STANDING COMMITTEE on APPROPRIATIONS FOR 2008/09 12 August
1 Water Services to Schools and Clinics Programme 20 June 2007 Presentation to Select Committee on Education and Recreation By DWAF.
Eradication of Mud Schools and other Inappropriate Structures Presentation to Portfolio Committee 22 September 2008.
Technical Secondary Schools Recapitalisation Grant Framework – 2011/12 Interim Report - 31 March 2012 Conditional Grant, Division of Revenue Act, 2011,
NATIONAL RECTIFICATION PROGRAMME SELECT COMMITTEE ON APPROPRIATIONS 11 SEPTEMBER 2012 NATIONAL RECTIFICATION PROGRAMME SELECT COMMITTEE ON APPROPRIATIONS.
1 2009/10 DIVISION OF REVENUE BILL Presentation to Select Committee on Finance 24 February 2009.
1 PROGRESS MADE AND RECOMMENDATIONS OF THE PORTFOLIO COMMITTEE ON THE RURAL HOUSING IINFRASTRUCTURE PROGRAMME 09 NOVEMBER 2011.
02 JUNE 2015 EDUCATION INFRASTRUCTURE GRANT PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATIONS.
Department of Arts and Culture Presentation to the Select Committee on Appropriations: 05 June 2012 Community Library Services Grant Mr Sibusiso Xaba Director.
12 SEPTEMBER 2012 SELECT COMMITTEE ON EDUCATION AND RECREATION (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)) 1.
LIBRARY AND INFORMATION SERVICES (LIS) PRESENTATION- PORTFOLIO COMMITTEE Presentation to Portfolio Committee 20 AUGUST 2013 Mr HM Mweli 1.
MASIBAMBANE CO-ORDINATING COMMITTEE MEETING PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 22 nd JUNE 2012 MASIBAMBANE CO-ORDINATING.
DBE BRIEFING TO THE STANDING COMMITTEE ON APPROPRIATIONS 03 September 2014 Cape Town.
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
Programme 4: Housing Development Finance Purpose: Fund national housing and human settlement development programmes in terms of the Housing Act (1997),
29 MAY 2012 HEARING ON FOURTH QUARTER CONDITIONAL GRANT School Infrastructure Backlog Grant 1.
EPWP Progress Reports to Portfolio Committee Presented by: Stanley Henderson DDG: EPWP 01 March
DEPARTMENT OF EDUCATION EDUCATION INFRASTRUCTURE PROGRAMME OF ACTION Portfolio Committee Presentation Cape Town 15 February 2005.
AGRICULTURE, FORESTRY AND FISHERIES CASP & ILIMA-LETSEMA 28 MAY 2013 PROJECT MANAGEMENT COORDINATOR: ELDER MTSHIZA.
THUBELISHA HOMES CLOSURE REPORT Presented to the Portfolio Committee on 8 July 2009.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
Integrated National Electrification Programme (INEP): Overall Performance (End of January 2012) Dr Wolsey Barnard.
DEPARTMENT OF BASIC EDUCATION School Infrastructure.
Hospital Revitalisation Joint Budget Committee 23 May 2005.
Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
19 OCTOBER 2012 STANDING COMMITTEE ON APPROPRIATIONS (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)) 1.
PROGRESS REPORT ON LAND RESTITUTION CLAIMS PRESENTATION TO THE PORTFOLIO COMMITTEE ON RURAL DEVELOPMENT AND LAND REFORM 07 FEBRUARY 2012 MR T. A MAPHOTO.
1 Select Committee on Economic Development Progress relating to the implementation of Integrated National Electrification Programme (INEP)
1 Presentation of the Financial Performance of the Department to the Standing Committee on Appropriations 23 March 2011 Presented by Cathy Motsisi Chief.
1 Reporting on Conditional Grants Presentation to Portfolio Committee 19 February 2007.
ASIDI Select Committee On Appropriations 02 June 2015.
Financial and Fiscal Commission
COMMISSION ON RESTITUTION OF LAND RIGHTS ANNUAL REPORT 2012/2013
Legislation Constitution of the Republic of South Africa, 1996 (Act No. 108 of 1996) Housing Act No.107 of 1997 The Housing Consumers Protection Measures.
National Department of Health Presentation to the Standing Committee on Appropriations Public Hearings on the Adjustments Appropriation Bill 05 November.
Presentation of the 4th Quarter Financial Performance of the Department to the Standing Committee on Appropriations (SCOA) 24 August
Commission on Restitution of Land Rights Briefing session on Annual Reports to the Portfolio Committee on Rural Development and Land Reform 12.
PRESENTATION TO SELECT COMMITTEE ON APPROPRIATIONS EDUCATION INFRASTRUCTURE GRANT AND ASIDI PERFORMANCE 30 MAY 2018.
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
SELECT COMMITTEE ON PUBLIC SERVICE: REPORT ON QUALITY SANITATION TO HOUSEHOLDS PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP)
27 November 2018 PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE ON APPROPRIATION 16 MAY 2018 MANCO.
GREEN FUND PROJECT PROTFOLIO
Progress Report on Payment of Suppliers
Select Committee on Finance Water Services Operating and Transfer Subsidy 10 May 2006 Department of Water Affairs and Forestry Jabulani Sindane : DG Trevor.
BUCKET ERADICATION : KWAZULU-NATAL
Basic Education Supplementary Presentation: National &Provincial Education Expenditure Trends and Projections Presentation by Dept of Basic Education to.
COMPREHENSIVE AGRICULTURAL SUPPORT PROGRAMME
Select Committee on Appropriations Dinaledi Schools Grant, 3rd and 4th quarter Expenditure /13 Presenter: Edgar Sishi | Chief Director – Provincial.
Progress on the Bucket Eradication Programme
Portfolio Committee on Health Parliament
2011/12 Provincial Business Plans & Outcome 8 Targets Human Settlements Portfolio Committee 29 April 2019.
PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL.
SCHOOL INFRASTRUCTURE
EPWP PROGRESS REPORT TO PORTFOLIO COMMITTEE ON PUBLIC WORKS
Summary of Presentation
IMPLEMENTATION OF IPID RECOMMENDATIONS
EPWP Incentive Grant 4th Quarter 2009/10 performance 18th May 2010
Select Committee on Finance National Council of Provinces
Presentation to the Standing Committee on Appropriation
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
PORTFOLIO COMMITTEE 20 FEBRUARY 2019
Presentation transcript:

20 FEBRUARY 2013 STANDING COMMITTEE ON APPROPRIATIONS (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)) 1

ASIDI BACKGROUND 2

SCHEDULE 7: SCHOOL INFRASTRUCTURE BACKLOGS GRANT The purpose of the grant is – for the eradication of entire inappropriate schools; – provision of basic level of water, sanitation and electricity to schools. The grant is also referred to as the ASIDI (Accelerated School Infrastructure Delivery Initiative) 3

ASIDI Targets The targets are as follows: Infrastructure CategoryBaseline2011/ / /2014 Inappropriate Structures Water Electrification Sanitation Specialist Classrooms50 MTEF ALLOCATIONS 2011/12R /13R /14R5 189 TOTALR8 204 The budget allocation for the ASIDI programme over the MTEF period is R8.2 billion and allocated as indicated in the table below: 4

ASIDI PROGRESS 5

ASIDI TARGETS AND ALLOCATIONS The targets are as follows: 6

ASIDI TARGETS AND ALLOCATIONS Current allocation is R2.065bil and MTEF projections per province are as follows: 7 DepartmentName of allocationProvince Column A Column B 2013/14 Allocation Forward Estimates 2014/152015/16 R'000 Basic EducationSchool infrastructure backlogs Eastern Cape Free State Gauteng KwaZulu-Natal Limpopo Mpumalanga Northern Cape North West Western Cape Unallocated TOTAL

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 8 ProvincesIAs Appointed No of Inappropriate Schools /Fin yrTotal 2012/132013/14 ECDBSA EC IDT EC 11 COEGA 24 DPWEC 16 TBA 32 Free StateDBSA FS 10 IDT FS 10 TBA 10 KwaZulu-NatalAdopt A Schools 3 3 LimpopoDBSA Lim 3 3 MpumalangaDBSA Mpu 5 5 Northern CapeDBSA NC 1 1 North WestDBSA NW 1 1 Western CapeWCED Total In Summary the following IAs have been appointed for implementation of the inappropriate schools on ASIDI

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 9 ContractorContract NoNo. SchSch IDSchool NameBuilding Progress Building Progress (Mean) Armstrong RFP 29/2011-E 12 Schools 1Qaka JPS93.70% 85.00% 2Ntsonyini JSS82.00% 4Ngidini SPS96.20% 10Ndluzula JPS83.10% 11Nomandla SPS98.60% 15Gcinizizwe SPS97.30% 20Maqolo SPS83.20% 24Jonguxolo JSS93.20% 27Vuyani SPS80.10% 30Sidanda SPS72.90% 36Tembeni SPS73.50% 38Sizwe JPS66.60% Keren Kula Construction RFP 31/2011-I 9 Schools 5Mpatiswa SPS100.00% 76.40% 7Zingisile SPS74.20% 14Goso JPS59.30% 18Eludikidi SPS60.00% 25Upper Mbange SPS81.70% 32Welese JSS96.40% 33Sizane JSS95.60% 46Nginza SPS67.20% 50Lower Mpako SPS53.20%

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 10 ContractorContract NoNo. SchSch IDSchool NameBuilding Progress Building Progress (Mean) SSI Mafuri JV RFP 29/2011-F1 6 Schools 12Manzabila SPS76.90% 87.10% 13Gqweza SPS97.50% 28Tshantshala SPS88.00% 29Mseleni SPS75.70% 31Mceteni SPS58.50% 37Maphindela SPS99.20% Ishvuyo RFP 29/2011-F2 6 Schools 16Gungubele SPS48.60% Sizisa Ukhanyo 21Mahahane SPS36.90% Ishvuyo 22Madwaleni SPS49.40% Alfdav 23Ludeke SPS44.40% Alfdav 34Sompa SPS22.40% Sizisa Ukhanyo 35Nkonkoni SPS59.20% Trencon Construction RFP 31/2011-G 5 Schools 3Notsolo SPS97.40% 96.50% 6Mqokolweni SPS91.40% 9Ndlovayiphathwa SPS100.00% 19Mdavuza SPS99.60% 26Dumile SPS99.90%

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 11 ContractorContract NoNo. SchSch IDSchool NameBuilding Progress Building Progress (Mean) Alfdav Construction RFP 31/2011-F x145Vulindlela JPS100.00% Base Major Construction RFP 31/2011-H x140Mazama SPS85.20% Cecils RFP 29/2011-C x148Kwezilethu JPS99.60% Inyameko / Vukukahnye JV RFP 31/2011-B x117Dikiso JSS58.40% Inyameko Deck Steel JV RFP 31/2011-C x141Thabatha SPS100.00% Ishvuyo Building ConstructionRFP 31/2011-E x144Dakhile JSS100.00% Leungo Construction RFP 31/2011-D x143Dumakude JPS81.30% Marnolda RFP 29/2011-B x147Kwenxura SPS99.00% Mauga Projects cc RFP 31/2011-A x18Nogaya SPS84.60% Setheo RFP 29/2011-A x139Mandlobe SPS53.60% Sizisa Ukhanyo RFP 29/2011-D x149Nobantu JPS99.60% 80.40%

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 12 DBSA is implementing 49 inappropriate schools and on average construction progress is at over 80.4%. 16 of the 49 schools have reached practical completion and handed over. 10 schools were planned for practical completion by end of Jan, however only 3 schools reached practical completion. 5 of the 10 schools are from Armstrong who is going through liquidation process and the schools could therefore not be taken. 17 schools were planned for practical completion by end of February, however 3 of 17 are from Armstrong cluster. 5 schools were planned for practical completion by end of March, 4 of 5 schools are from Armstrong cluster. 5 schools are planned for practical completion by end of April. DBSA received an initial and further cautionary announcement on Armstrong’s business state on the 24 January 2013 and 04 February 2013 respectively. DBSA is currently in the process of finding a replacement contractor to complete the 12 Armstrong schools. To date 2 contracts have been terminated and 1 is under going liquidation.

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 13 Terminated contracts and financial implications: Two contractors were terminated. The terminated contractors are InyamekoVukukhanye JV and TBP Civils. The terminated contract for InyamekoVukukhanye was R15.3 million. The replacement contractor was appointed at R14.0 million. The terminated contract of TBP Civils was R88.5 million and by the time of termination R19.4 million was already paid to the contractor as at September The costs for replacement contractors is R100.0 million bringing the contract value over with R11.5 million which will be recovered from the construction guarantee amounting to R8.85 million and a retention of approximately R2.3 million.

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 14 Company Name RFP 31/2011 Maunga Projects cc Luengo Construction Enterprises cc ALFDAV Construction cc Trencon Construction Base Major Construction Keren Kula Construction RFP 29/2011 Setheo Investment JV Marnolda Cecil's Building Sizisa Ukhanyo The following contractors were granted an extension of time to 20 Sept 2012: Company Name RFP 31/2011 Armstrong Construction RFP 29/2011 Stewart Scott/Mafuri JV The following contractors rejected an adjudication granting extension of time to 20 Sept 2012:

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 15 DBSA has now been issued with a second batch of 70 schools to implement. – 50 of the schools are in EC, – 10 in FS, – 5 in Mpumalanga, – 3 in Limpopo, – 1 in NW and – 1 in NC. – Projects are at the planning stage. The target is to complete these schools by end 2013/14 financial year.

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 16 CDC, IDT and DRPW have been appointed to implement 24, 11 and 16 new schools respectively in EC. CDC has completed contractor procurement process for 22 schools. Approvals to appoint accepted tenders on 20 schools have been granted to CDC by DBE. CDC handed over 17 schools to contractors and construction work has commenced, and 2 of the 24 schools are at planning stage. IDT has completed contractor procurement process for 10 of 11 schools and 1 school is at planning stage. Approval for appointment of accepted tenders for 10 of 11 schools has been granted to IDT. On DRPW, 6 schools are at approval stage for appointment of accepted tenders, 4 of DRPW schools are at contractor procurement stage, 3 at design stage and 3 at planning stage.

ASIDI PROGRESS ON INAPPROPRIATE SCHOOLS 17 WCED has been appointed to implement 14 schools in WC. A contractor has been appointed at 1 of the schools. 9 schools are at approval stage for appointment of accepted tenders and 4 schools are at contractor procurement stage. IDT has been appointed to build 10 schools in FS and all 10 schools are at design stage.

ASIDI PROGRESS ON WATER PROJECTS 18 Of the 1120 projects 1039 will be implemented by the implementing agents indicated in Table 5 below and respective financial years. 81 of 1120 schools have been provided with basic water by others. Water ProvinceNo of Schools Eastern Cape619 Free State101 Gauteng0 KwaZulu Natal230 Limpopo121 Mpumalanga17 North West16 Northern Cape12 Western Cape4 Total1 120

ASIDI PROGRESS ON WATER PROJECTS 19 ProvinceAppointed IATotal No of ProjectsNo of Projects per Financial year 2011/122012/13 and 2013/14 Eastern Cape 583 TBA 91 Mvula trust IDT 135 CSIR 152 Free StateFSDoE GautengGauteng DoE Kwa-Zulu Natal 230 KZNDoE 10 IDT 69 Mhlathuze 79 CDC 72 LimpopoMvula Trust MpumalangaMvula Trust17 North WestNWDoE16 Northern CapeNCDoE6 6 Western CapeWCED44 Total In Summary the following IAs have been appointed for implementation of the water projects on ASIDI

ASIDI PROGRESS ON WATER PROJECTS 20 In EC: – Mvula Trust provided 35 schools with water, 49 are in the process of being provided with boreholes and the remaining projects are in planning. – IDT and CSIR are implementing agencies and their projects are still at planning stage. In FS DoE completed 30 water projects In Gauteng there are no schools without access to basic water. In KZN: – 10 KZN DoE projects are in construction stage. – IDT, Mhlathuze Water and CDC water projects are still at planning stage. In Limpopo Mvula Trust has completed 38 water projects. In Mpumalanga the projects are at planning stage In Northwest the projects are at planning stage. In Northern Cape the projects are at planning stage. In Western Cape and DoE completed 4 water projects and there are no schools without access to basic water.

ASIDI PROGRESS ON SANITATION PROJECTS 21 Currently there are 741 sanitation projects nationally in various stages of project progress and are indicated in the following table by province. 107 of 741 schools have been provided with basic sanitation by others. ProvinceNo of Schools Eastern Cape344 Free State68 Gauteng28 KwaZulu Natal140 Limpopo77 Mpumalanga8 North West29 Northern Cape26 Western Cape21 Total741

ASIDI PROGRESS ON SANITATION PROJECTS 22 In Summary the following IAs have been appointed for implementation of the sanitation projects on ASIDI ProvinceAppointed IAsTotal No of ProjectsNo of Projects per Financial year 2011/122012/13 Eastern Cape TBA59 Mvula trust IDT79 CSIR63 Free StateFSDoE GautengGauteng DoE28721 KwaZulu Natal TBA77 KZNDoE50 IDT19 Mhlathuze13 CDC18 LimpopoMvula Trust MpumalangaMvula Trust88 North WestNWDoE12 Northern CapeNCDoE21 Western CapeWCED21 Total

ASIDI PROGRESS ON SANITATION PROJECTS 23 In EC: – Mvula Trust in EC has completed 55 projects and is in the process of procuring PSPs and contractors. – IDT and CSIR projects are at planning stage. In FS DoE completed 13 water projects and is in the planning stage for batch no 2. In Gauteng, DoE completed 7 projects and are in planning stage for batch no 2. In KZN: – KZN DoE is in the process of completing 60 sanitation projects and planning to completion the projects by end march – 54 schools have reached practical completion – IDT, Mhlathuze Water and CDC water projects are still at planning stage. In Limpopo Mvula Trust has completed 40 sanitation projects and are in the process of procuring PSPs and contractors for their 2 nd batch. In Mpumalanga the projects are at planning stage. In Northwest, NWDoE is in the process of procurement of contractors.

ASIDI PROGRESS ON ELECTRIFICATION PROJECTS 24 Currently there are 916 electricity provision projects nationally in various stages of project progress and are indicated in the following table per province. 384 of 916 schools have been provided with electricity by others. ProvinceNo of Schools Eastern Cape317 Free State143 Gauteng2 KwaZulu Natal116 Limpopo142 Mpumalanga148 North West41 Northern Cape0 Western Cape7 Total916

ASIDI PROGRESS ON ELECTRIFICATION PROJECTS 25 In Summary the following IAs have been appointed for implementation of the electrificationprojects on ASIDI No of SchoolsFinancial year ProvinceIA2011/122012/13 Eastern CapeEskom Free StateFSDoE GautengGDoE22 KwaZulu NatalEskom61 LimpopoEskom752 MpumalangaEskom North WestEskom2 2 Northern Cape 0 Western CapeWCDoE77 Total

ASIDI PROGRESS ON ELECTRIFICATION PROJECTS 26 In EC, Eskom has electrified 85 schools, 15 at construction stage, 200 at planning stage. In FS DoE completed 23 electrification projects, 1 is awaiting Eskom to energise, 64 are at planning stage. In Gauteng DoE has completed 2 electrification projects and there are no schools without access to electricity. In KZN projects are at planning stage. In Limpopo 4 projects are completed and 1 awaiting outage. The remaining projects are at planning stage. In Mpumalanga 10 projects are completed, 11 in construction process and the remaining projects are at planning stage. In Northwest the projects are at planning stage. In Northern Cape there are no schools without electricity. In Western Cape and DoE completed the 7 electrification projects and there are no schools without electricity.

ASIDI BUDGETS,EXPENDITURE AND ADVANCE PAYMENTS 27

ASIDI BUDGET, EXPENDITURE AND ADVANCE PAYMENTS 28 The 2013/14 projects are estimated at R4,65 bil. Expenditure as at the end of the 3rd quarter was R476 mil An amount of R423mil has been made in advance to IAs as indicated in the table above. ProvincesIAs AppointedOldDecJanuaryFebruaryTotal ECDBSA EC R R R IDT EC R COEGA R CountrywideESKOM R Total R R R R R

OTHER ASIDI MATTERS 29

OTHER ASIDI ISSUES Framework Agreements, DBE is in the process of finalising a panel on Implementing Agencies, Built Environment Professionals and contractors. This resource is valid for a period of 3 years and should reduce the procurement period. DBE is in the process of evaluating suitable alternative building methods. The process will be concluded at the beginning of On approval by DBE, suitable alternative building methods will be used to implement some of the new schools. Rationalisation and Mergers, DBE awaits decisions from affected Provinces. Communication on ASIDI progress, DBE has established a webpage on the DBE website and a Quarterly Newsletter to give updates on ASIDI to stakeholders. 30

THANK YOU 31