PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015. PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.

Slides:



Advertisements
Similar presentations
PIP Update Oct Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken Domann.
Advertisements

Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Tom Kubicki.  Booster HLRF System to be upgraded using 1kW Solid State Driver (SSD) Amplifiers.  Used to drive the 200kW Power Amplifier  Eliminates.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update July Agenda Summary Update – Budget/RLS – Current Activities – Upcoming Activities/ Changes Update Slides High-Power Ferrite TestingDennis.
PIP Update June 26 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
PIP Update Aug 15 th Agenda Summary Update – Current Activities Dennis Barak / Kiyomi Seiya - High-Power Ferrite Testing Ryan Crawford - Linac and.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Proton Improvement Plan (FY13 PMG Q4). William Pellico, Fermilab PMG, Nov PIP FY13 Q4 Summary Task Highlights Budget and Labor Review Summary.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Proton Improvement Plan (FY12 PMG Q4). William Pellico, Fermilab PMG,October FY12 Summary Q4 Task(s) Summary – Highlights RFQ Injector Budget.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
Proton Improvement Plan (PIP) William Pellico PIP and MI 700 kW review 21 – 22 January 2015.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Proton Improvement Plan (FY13 PMG Q1). William Pellico, Fermilab PMG, January FY13 Summary Q1 Task Summary – Highlights RFQ Injector Budget.
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
PIP Update Feb 11 th Agenda Summary Update – Current Activities – Updates (Tom Kubicki) – Additional Meetings/Notes.
PIP Update Jan Agenda Summary Update – Current Activities – Updates (Ken, Pat and John) – Additional Meetings/Notes.
Proton Improvement Plan Bob Zwaska July 7, 2014 All-Experimenters Meeting.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
PIP FY14 PMG W. Pellico 7/8/14 7/8/2014PIP PMG. PIP Activities RIL & Linac – 200MHz RF Power System High Level RF Linac Modulator 7835 Procurement – Accelerator.
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
PIP PMG Project Controls Elmie Evans-Peoples PIP PMG Oct 25, 2012.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
PIP Update Sept. 18 th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Pat.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
PIP Update Oct Agenda Summary Update – Current Activities Updates/Talks: Dave Johnson – Linac Notching (laser)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (Joe Compton - shutdown) – Additional Meetings/Notes.
PIP FY15 Q4 Report W. Pellico PIP PMG November 5 th 2015.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 07/01/2013.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Accelerator Status and Plans
Proton Improvement Plan Overview Bob Webber July 13, 2011.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Alexander Valishev - Simplified Modeling of Space Charge Losses in Booster.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Proton Improvement Plan (FY13 PMG Q3). William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary.
PIP Update April 10 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Eliana.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Proton Improvement Plan (PIP) William Pellico Fermilab Annual Science and Technology Review September 5-7, 2012.
PIP Update April 3 rd Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
PIP Update Dec 17 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
PAC Meeting, December 12, Prebys 1 The Problem.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update May 28 th Agenda Summary Update – Current Activities/Updates – Ken Domann.
Booster High Power RF at PIP-II Era John Reid February 18, 2014.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Presentation transcript:

PIP FY15 PMG W. Pellico PIP PMG March 5 th 2015

PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls –FY15 Plans 3/5/2015bp | PIP FY15 Q1+ PMG2

PIP FY15 Milestones 3/5/2015bp | PIP FY15 Q1+ PMG3 LVLWBSDescriptionBaselineDate Beam shaping technology chosen10/8/ Linac Notch Final Optical Cavity Certified2/2/1510/22/ Specifications for Anode Power Supply Documented 10/15/1411/26/ Complete 55 LCW Spare Syst12/9/1412/18/ Complete Installation of New Dual Temp System 3/24/1512/30/ Linac LCW System Complete11/24/1412/30/ Booster BPM System, Hardware & Firmware Prototype Design Complete 12/22/145/1/ Prototype Klystron Final Assembly Drawings Complete 12/17/143/2/ Booster BPM Specification Complete12/8/143/27/ Linac Notcher (FA) Certify all three stages ready for installation 12/2/143/6/ Specifications document for Booster longitudinal dampers complete 12/1/143/27/15

PIP 200 MHz RF Power Systems (WBS 1.1.1) Linac High Level Klystron effort –Work has shifted from design to drafting of the klystron Continuing dialogue on hardware specifics Continuing discussion on testing at vendor –Looks like this is a viable option –Will not require Fermi to build test stand Long lead-time acquisitions nearly complete 3/5/2015bp | PIP FY15 Q1+ PMG4 ActionDate Preliminary Design Review4/2/2014 Critical Design Review7/11/2014 Seal in Drawings Complete10/6/2014 Final Assembly Drawings Complete 12/17/2014 Seal in Assembly Complete6/17/2015 Final Dress Complete7/15/2015 Testing Complete8/26/2015 Customer Source Inspection8/27/2015 Package and Ship9/8/2015

Activities 28 cell enclosure design completed received enclosure waiting on vendor to build internal support structure (4 weeks away) Gate driver circuit board design/layout done Designing control cards for both 28 and 54 cell prototype design Short circuit testing completed for 9 cell prototype Performed corona testing on cells and made design changes Selected charging supply manufacturer, ordered units, will initial use to do thermal analysis of main switching element Learning / feed-forward control system work underway Proceeding with 54 cell design Most parts ordered for building 54 cell design, some have already arrived 3/5/2015bp | PIP FY15 Q1+ PMG5 9 cell timing tests completed upgrades completed snubber capacitor (one added) gate clamp B-dot coil design new low inductance stripline PIP 200 MHz RF Power Systems (WBS 1.1.1) Linac Modulator

PIP Accelerator Physics (WBS 1.1.2) Linac Laser Notcher 3/5/2015bp | PIP FY15 Q1+ PMG6 Linac Notch Creation (Dave Johnson will give more details) Started environmental testing of mirrors using test laser Successfully performed verification test of laser power and optics Buildup of final laser system got underway Mirror Laser Input Port RFQ 200 MHz Bunched Beam

Power Distribution Completed task LCW distribution Completed task Vacuum Completed task PIP Linac Utilities (WBS 1.1.5) 3/5/2015bp | PIP FY15 Q1+ PMG7 Oct ‘12 DTL roughing station

PIP Booster Anode Supplies (WBS ) Anodes to be installed in the FY15 shutdown…. –Slower than expected…. Issues finding vendors that can meet the specifications Issues with enclosure Lots of components to test before final install 3/5/2015bp | PIP FY15 Q1+ PMG8

PIP Booster Bias Supplies (WBS ) Upgrading the west gallery supplies for reliable 15 Hz operations –Replacing transformers for 15 Hz operation –Also requires re-plumbing and re-wiring –Adding heat sinks in several areas This effort is not as far along as projected, largely due to labor –5 out of 10 in west gallery upgraded/tested –Should not impact initial 15 Hz testing 3/5/2015bp | PIP FY15 Q1+ PMG9

PIP Booster Cavity & Tuner Refurbishment (WBS ) Since this summer progress continues at an increased pace –Cones for tuners is still a time constraint –TD is used to do some re-work; AD team does majority –New AL cones are now part of the process Worked out vendor quality issues Saves time – but still labor intensive to complete process Labor –Another contract tech left!!!! New one just hired this week – not sure of status –Will take time to train (typically on the order of 6 months) Concern about shutdown – do not want to lose tech/fall behind Goal of PIP/AD is to have 17 certified by June 2015 –This will allow us to test entire system at 15 Hz –East gallery has had several months of 15 Hz testing 3/5/2015bp | PIP FY15 Q1+ PMG10

3/5/2015bp | PIP FY15 Q1+ PMG11 Planned install of #17…. A failure of refurbed BRF5 last Tuesday may impact schedule… No details yet on what failed These cavities will never be like new cavities and will have long term operational issues PIP Booster Cavity & Tuner Refurbishment (WBS )

PIP Booster New Tuners (WBS ) Vendor has now met speciation's for both types of ferrites –Partial orders have been delivered buildup of tuner components underway (TD leading effort) –Second tuner completed…third tuner getting started –Releasing order for more ferrite 3/5/2015bp | PIP FY15 Q1+ PMG12

PIP Booster New Cavities (WBS ) Splitting into three thrusts: –Rework of Proton Driver cavities and original prototype Original cavity (20) installed and operating Two more (Cavity 21 & 22) work and schedule being developed Will have 22 stations installed and operating when completed –Harmonic Cavity System (Perpendicular Bias) Initial design plan is for injection and transition Modelling progressing Building up mock cavity for testing purposes Plan to order components for full cavity by end of FY15 –Replacement RF system compatible with PIP II (PIP III RCS) This is on going discussion – hope to settle question soon! 20 Hz capable 3/5/2015bp | PIP FY15 Q1+ PMG13

PIP Booster Radiation Shielding (WBS ) TLM system installed in Booster –8 detectors (each covering 3 Booster periods) –No single detector covers more than 1 expected “lossy” region Injection, extraction, collimators, notcher Will run series of beam tests in next couple of weeks to characterize system –destructive studies – will impact operations ES&H assessment group is working on dosages through the shielding & penetrations –Have done several rounds of test to confirm assumptions on loss pattern/levels –At least one more scan is planned 3/5/2015bp | PIP FY15 Q1+ PMG14

BPM The Booster BPM front end test-stand is running a Linux/RTAI kernel and the AD/Control's department ACSYS software –this is the Linux equivalent of MOOC Running Linux in a VME crate required some effort to build and test the VME drivers for Linux Testing the VME interface to the 250MHz digitizer Dampers Several problems encountered with initial frontend –Lock issues –Card debugging Transfer measurements Phase control work – to match present system Compared old and new system amplitudes and rates of CB instabilities ACNET software just completed and now being tested PIP Booster Instrumentation (WBS ) 3/5/2015bp | PIP FY15 Q1+ PMG15 Working on the BPM control and readout software

Transformers Last transformer to install (East side) –Will be completed this shutdown Vacuum Cabling and associated rack work is on-going Tunnel work awaits personnel availability & will be fill-in work this shutdown PIP Booster Utilities (WBS ) 3/5/2015bp | PIP FY15 Q1+ PMG16

PIP End of Year Budget and Labor Summary 3/5/2015bp | PIP FY15 Q1+ PMG17

PIP FY15 Initial Upload (some small differences – will be corrected) 3/5/2015bp | PIP FY15 Q1+ PMG18 CHOOSE OHAP ROLEPIOHAP Category (will fill)ADAPCFESSPPDCDTD TOTAL FTEs TOTAL FTE LABOR COST (will calculate) TOTAL LABOR COST $1,923.6$357.4$1.2$0.0 $275.9$0.0 $2,558.1 LABOR OH RATE 97.37% 54.19%73.47%70.00%87.34%0.00% LABOR OH $1,873.0$348.0$0.7$0.0 $240.9$0.0 $2,462.6 M&S (enter) Standard $1,848.5 Pass-Through $0.0 Exempt - $ of POs > $500K $2,126.1 Exempt - # OF PO > $500K 2 2 TOTAL M&S $3,974.6$0.0 $3,974.6 M&S OVERHEAD RATES M&S Standard 21.28% M&S Pass-Through 3.00% Exempt - M&S on first $500k $106.4 TOTAL M&S OH $606.2$0.0 $606.2 BUDGET SUMMARY SWF $1,923.6$357.4$1.2$0.0 $275.9$0.0 $2,558.1 SWF OH $1,873.0$348.0$0.7$0.0 $240.9$0.0 $2,462.6 M&S $3,974.6$0.0 $3,974.6 M&S OH $606.2$0.0 $606.2 TOTAL BUDGET SUMMARY $8,377.3$705.4$1.9$0.0 $516.8$0.0 $9, ,000.0 Over (Under) Guidance(2,398.6) Adjustments are being planned: Code structure, Some task plans and Labor needs PIP FY15 budget reduced by 2 million – to 10M working out RLS changes

Summary Most PIP tasks continue to align to schedule –Refurb rate has greatly improved Recent setbacks in labor and RF5 vacuum leak New Tuners AL cones Recent reviews have gone very well… –DOE PIP & 700 KW Review PIP well-defined achievable, etc. - Half of tasks completed - delivering beam improvements - Impressive progress Remaining FY15 PIP will be busy – preparing for shutdown and 15 Hz RF cycling… 3/5/2015bp | PIP FY15 Q1+ PMG19