Fermilab February 1, 2007 J. Tompkins -1- Comments on the EDR and Magnet Systems JCT for the Magnet Systems Group 070201.

Slides:



Advertisements
Similar presentations
February 7, 2007-Beijing (Zisman-DR) Global Design Effort 1 Damping Ring EDR Plans Michael S. Zisman, Jie Gao, Susanna Guiducci, Andy Wolski DR Area System.
Advertisements

Oct 24, 2007 C.Spencer Magnet EDR Planning 1 GDE Generating Magnet Work Packages: Planning for the Engineering Design Phase Cherrill Spencer, SLAC with.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Damping Rings Baseline Lattice Choice ILC DR Technical Baseline Review Frascati, July 7, 2011 Mark Palmer Cornell University.
CLIC Kickers: Status and activities for 2013 in view of the budget discussions for 2013 CTC #65 M.J. Barnes CLIC Technical Committee, November M.J.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
Global Design Effort BDS KOM Opening remarks/comments from EDR Project Management SLAC Marc Ross / Nick Walker.
Global Design Effort - CFS CLIC 09 Workshop - WG 5 Technical Systems 1 CLIC 09 WORKSHOP Working Group 5 - Technical Systems ILC REBASELINE ILC.
1 Process Water and Air Treatment 01 June 2007 Emil Huedem, Maurice Ball, Lee Hammond Fermilab.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP GENERAL.
Global Design Effort U.S. ILC Cost Translation R. Stanek, et al. Vic Kuchler 1/26/07.
BDS Magnet-Power System-Facility Optimization1 ILC BDS Kickoff Meeting Basis for Magnet, Power System and Cooling Facility Optimization Discussion Paul.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
F Project X Overview Dave McGinnis October 12, 2007.
RDR Report Writing Nan Phinney SLAC. 7/20/06 VLCW06 Global Design Effort 2 GLC Report Working model is the 2003 GLC Report ch 4-7
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
19 July 2006 Vancouver Global Design Effort 1 Cryogenic Systems Review Tom Peterson for the cryogenics global group.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Operations, Test facilities, CF&S Tom Himel SLAC.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
Global Design Effort 1 Possible Minimum Machine Studies of Central Region for 2009 Reference, ILC Minimum Machine Study Proposal V1, January 2009 ILC-EDMS.
DESY_ILCW07 Global Design Effort-CF&S 1 Beam Delivery System & Interaction Region Fred Asiri CF&S Point of Contact.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
ILC BDS Kickoff Meeting Magnet Power Supplies RDR Concepts and Completeness Paul Bellomo SLAC Power Conversion Department October, 2007.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
1 V. Kashikhin for ILC ALCPG 2007, FNAL Meeting October 23, 2007 Ring to Main Linac Magnets.
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
1 The ILC Control Work Packages. ILC Control System Work Packages GDE Oct Who We Are Collaboration loosely formed at Snowmass which included SLAC,
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
October 25, 2007 A. Brachmann Slide 1 ILC polarized Electron Source EDR Work Packages ALCPG/GDE Meeting Fermilab, October 25, 2007 Axel Brachmann.
DRWS07 KEK Global Design Effort ILC Damping Rings Mini-Workshop December, 2007 High Energy Accelerator Research Organization KEK,
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
How the NCSX Project Does Business
ILC Cryogenic Systems Status and EDR Plans Tom Peterson 25 October 2007.
Introdcution to Workpackage/Activity Reflection D. Schulte.
Costing review Extract from slide of Philippe: The Panel was impressed by the quality of the presentations and degree of detail to which the value.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
J.C. Sheppard, SLAC Americas Region February 7, ILC Source Systems Work Packages and EDR Discussions ILC GDE Meeting IHEP, Beijing, China J. C.
Beijing ILC Workshop Global Design Effort 1 Main Linac EDR: Cavity & Cryomodule Discussion Lutz Lilje DESY.
Report of HLRF KOM/ALCPG07 S. Fukuda(KEK) R. Larsen(SLAC)
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
1 R&D Plans for Impedance Driven Single-Bunch Instabilities (WBS 2.2.1) M. Venturini ( presented by M. Zisman) LBNL LCWS07 DESY, Hamburg May 30 - June.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
O. Kester, NuSTAR annual meeting, 27/02/2013
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
CTC Work Packages ver 2.1 HS for CTC. CTC-001SC wigglers Cooling design, hor. or ver. Racetrack coil Nb3Sn or NbTi cable Prototypes construction Experimental.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
ILC Beam Instrumentation – Introduction Remarks –
ILC Cryogenics Work Package Status and Plans
Oct 22 Group Leaders Planning meeting
Meeting for S1-Global module design Cryomodule and Cryogenics
Americas KlyCluster Cost Analysis Overview
BDS Cryogenic System RDR Status and EDR Plans
The ILC Control Work Packages
EDR HLRF Work Packages Draft Summary
DR Magnets & Power Supply System ILC-ADI Meeting March 14, 2012
ILC Cryogenic Systems Draft EDR Plan
CLIC/ILC Collaboration Meeting: Objectives & Organization
ILC Cryogenics -- Technical Design Report Planning
RF System (HLRF, LLRF, Controls) EDR Plan Overview
Presentation transcript:

Fermilab February 1, 2007 J. Tompkins -1- Comments on the EDR and Magnet Systems JCT for the Magnet Systems Group

Fermilab February 1, 2007 J. Tompkins -2- The ILC EDR (Engineering Design Report) What is it? –Detailed design report as a basis for approval to proceed as a project What is the Scope? –Early discussions: “~25-30% design level” Sufficient detail to establish technical design package 3-D magnetic field calculations Define all interfaces – pedestals, stands, power, lcw, sensors, etc. Develop accurate beamline layouts with real space allocations Estimate of tooling requirements, design concepts Sufficient information for detailed cost estimate Magnets

Fermilab February 1, 2007 J. Tompkins -3- EDR Scope, cont. Scope, recent discussions… –“complete design package” for all magnets –Detailed design of all components completed –Tooling design completed –Drawing packages completed –Ready to begin procurement… In either case, the resources required are a factor of ≈(3–10)x more than have been used in the RDR –Magnet physicist/engineers –Design/drafters –Tooling designers –Etc. Clearly, an EDR definition needs to be “published” by management Magnets

Fermilab February 1, 2007 J. Tompkins -4- Organization of EDR Work We are told that work will be done through Work Packages issued by Area Systems Groups –Nominally consistent with organization of RDR/BCE, but… Area Systems, in general, didn’t fund design work Management structure above Area Leaders still to be developed Program manager Integration function still lacking in ILC organization –Quasi-independence of work packages leaves some concerns on uniformity of approach, duplication of effort, ‘enforcement of standards” Are we designing 6 independent machines…? Magnets

Fermilab February 1, 2007 J. Tompkins -5- Our View of Magnet Systems Work Packages Three distinct components –Magnets (12 ea) –Power Systems (6 ea) –Test and Measurement Facilities (2 ea) Magnets and Power Systems divide among Area Systems in a natural fashion –Exception – pulsed magnet systems are still R&D intensive and have significant commonality across several areas; it is not sensible to split it up (abort kicker systems) TOTAL about = 23 WP’s (not incl. kicker pulsers) Magnets

Fermilab February 1, 2007 J. Tompkins -6- A Generic Magnet Work Package Format stolen from P. Bellomo, M. Zisman, M. Palmer, et al.P. Bellomo, M. Zisman, M. Palmer 1.Objective 1.1Develop and design Area System conventional DC magnets, support stands, and interfaces to other systems. 2.Task Description 2.1Work with Area System physicists, engineers, and designers to develop conventional magnet designs and specifications which meet the magnetic field requirements, alignment and stability requirements, aperture, length, and other dimensional requirements, availability requirements, electrical power requirements, heat generation requirement, radiation hardness requirements, and any other achievable system requirements. 2.2Explore options to provide a cost-effective design meeting the above criteria and carry out the necessary engineering design work required by the Engineering Design Report. 2.3The scope of work includes DC magnets, associated support stands, and definitions of interfaces with other systems; it does not include pulsed magnet systems. 3.Deliverables 3.1Furnish, by the following performance specifications, drawings and cost estimates: 3.1.1Magnet specifications, including field strength, effective length, field uniformity/magnitude of allowed, aperture, physical dimensions, total weight, electrical properties, including total resistance and inductance, required LCW flow rate and pressure drop (if applicable), operating temperature, conductor cross section, and other parameters necessary for design, fabrication, installation, and operation Magnet support stand specifications, including support points, adjustment range along and transverse to beam line, adjustment resolution, 3.1.2Definition of interfaces with other systems: including vacuum systems, power systems, LCW, alignment, installation fixtures, etc Complete set of design and fabrication drawings suitable for procurement 3.1.7Other information as necessary for the Engineering Design Report Magnets

Fermilab February 1, 2007 J. Tompkins -7- Work Package Discussion, cont. “Bottom line” questions: –Can Area Systems manage the magnet design and cost work? –Do Area Systems have the budget to do it? –Is an overall Magnet System coordination/management function required? Answers to the questions –Possibly, depending on Area, but neither their priority nor strength –Probably not –Yes (Feed – down of requirements caused delays at the start of RDR, this is not so much of a problem now) Magnets

Fermilab February 1, 2007 J. Tompkins -8- EDR Comments, cont. A Magnet Systems Design Coordination/Management function is necessary (3 ea WP) –It should be independent of specific Area Systems –It should set standards, review work, and be responsible for magnet system interfaces to other Technical Systems Vacuum Controls CFS – LCW, power, etc. It should have three components –DC Magnets – both conventional and SC,… –Power Systems –Pulsed Magnet Systems Magnets

100% of Magnet design – “EDR+2” Magnets

Fermilab February 1, 2007 J. Tompkins -10- Summary (Tompkins for the Magnet Group) A formal definition of EDR scope is needed –Level of design detail, Target completion date, Resources to be committed Without sufficient support, this is a futile exercise –Cannot carry out the EDR at the RDR level of support for Magnet Systems –At present, there does not appear to be sufficient resources in existing US R&D budgets for the EDR work (even for the 25-30% design level) (e.g. DR Magnets: 1.4, 2 FTE in 08/09 resp. ~ 50% less than requested, 50% less than scaled estimate) Magnets

Fermilab February 1, 2007 J. Tompkins -11- Summary, cont. There must be a mechanism for overall management & coordination of Area System based ‘magnet’ work packages: –Best mechanism to aggressively apply ‘value engineering’ (MCR) –Coordination/integration issues –Minimize number of different magnet styles for cost savings –Design standards for availability/reliability and cost savings –Review function –R&D overlap or gaps Design should be coupled to R&D results in EDR R&D and Work Package review and assignment needs a more formal approach with external reviewers Magnets

Fermilab February 1, 2007 T. Peterson -12- The ILC EDR – Cryo (Peterson) Work packages arising from unique ILC cryogenic system problems –many of these issues will be addressed by XFEL at DESY and/or by LHC at CERN, –a significant engineering effort needed for ILC cryogenic system designs, just rough concepts now. some overlap with cryomodule development and design work. –Other areas cryogenic system design requires collaboration with RF and magnet system designers. There has been and will be significant international collaboration; the work listed below is intended to be international, distributed among all the collaborators. Cryo - Peterson

Fermilab February 1, 2007 T. Peterson -13- Summary of topics: liquid control, heat loads and flow rates, cryomodule thermal optimization, plant design (with industry), repair scenarios, reliability 2 K heat exchangers, emergency venting, grouping surface components, ODH, compliance with engineering standards, cryo box design, damping ring system, beam delivery system. This list is certainly not comprehensive; other topics will no doubt be added to the work list. Cryo - Peterson

Fermilab February 1, 2007 T. Peterson -14- Total effort A total of ~10 man-years of engineering and design labor are identified below, with effort for tasks estimated in man-months. –The RDR cryogenic system effort has had less than 1 FTE of effort through the past year. –A minimum of an FTE in each region is needed through the EDR phase. –If cryogenic experts around the world all continue to have other, local commitments in addition to ILC, this work will require part-time (but significant fraction) efforts from at least 2-3 people in each region. Cryo - Peterson

Fermilab February 1, 2007 T. Peterson -15- Effort Summary – 30% - Peterson Liquid Control Heat Loads Thermal optimization Plant Design Maintenance, rel,… 2K HX Emergency Venting Surface components ODH Engineering Standards Cryo Box design 0.5 person-years industrial study industrial study Cryo - Peterson

Fermilab February 1, 2007 M. Ross -16- Comments: The above is a ‘bottoms – up’ basic estimate of the EDR effort and organization required for Magnet/Power Supply & Cryo Structure needed is different –A 3 rd example would be controls ‘Global’ integration issues not directly singled out –RDR effort has examples/counter-examples of how well this went T. S. Group Leaders ‘eager’ to contribute further to organizing task, especially given additional framework