ATLAS Inner Detector MO_B 2012 closure 2013 mid-year status 2014 request H. Pernegger / Pixel PL & ID Resource Coordinator D. Robinson / SCT PL and ID.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

The Control System for the ATLAS Pixel Detector
M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
ALICE © | RRB | 17 April 2013 | Catherine Decosse 24 th meeting of the ALICE Resources Review Board CERN-RRB
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
1.ATLAS and ID 2.SCT 3.Commissioning 4.Integration 5.Latest Runs 6.Conclusions Commissioning the ATLAS Silicon Microstrip Tracker IPRD08 - Siena Jose E.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
TRT Detector Status Report Konstantin Zhukov (Lebedev Physics Institute) for the ATLAS TRT group ID week, 19 May
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Pixel Upgrade Plans ROD/BOC PRR July 17, 2013 T. Flick University of Wuppertal.
ATLAS Pixel Upgrade Phase 0 (IBL) ACES Workshop , CERN T. Flick University Wuppertal for the IBL collaboration.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Design and Performance of a PCI Interface with four 2 Gbit/s Serial Optical Links Stefan Haas, Markus Joos CERN Wieslaw Iwanski Henryk Niewodnicznski Institute.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
SLHC SG: ATLAS Pixel G. Darbo - INFN / Genova SLHC SG, July 2004 ATLAS Pixel at SLHC G. Darbo - INFN / Genova Talk overview: A table with different High.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Active gas system status. S.Konovalov, K.Zhukov. Active gas system operation. S.Konovalov "Active gas system..."TRT Overview  Good design.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Technical Support Activities in PH-ADO-PO
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
G. Pugliese RPC requests for GIF++ G.Pugliese, N. Zaganidis and I. Pedraza on behalf of the RPC group 1.
Main priorities for the next years. Where do we stand Muon system in good shape (in my opinion) – Sub-systems hardware quite robust (see later for main.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
July 17, 2013 CERN T. Flick University of Wuppertal.
Overview and Status of the ATLAS Pixel Detector Claudia Gemme, CERN/INFN-Genova on behalf of the ATLAS Pixel Community 10th ICATPP Conference, Como, Oct.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
Pigi Paolucci & Anna Colaleo – RPC project 2012 RPC M&OB scrutiny Anna Colaleo (INFN-Bari) RM Pierluigi Paolucci (INFN-NA) PM 1.
U.S. ATLAS Executive Meeting Silicon M&OWBS 3.1 August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI New recuperation system for n-Pentane:  Installation of the module in parallel of the first.
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
ATLAS Upgrade Plans ATLAS Hardware – Challenges and Opportunities Norwegian CERN “Town Meeting” Bergen
Active gas system status & plans. S.Konovalov, K.Zhukov, K.Vorobev.
News and Misc Didier Contardo, Jeff Spalding UPO 3/2/12 1 UPO 2/2/12 o The MM, cost estimates and reporting o Milestones and scheduling o Chamonix Meeting.
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
ATLAS Inner Detector MO_B 2013 to-date status 2014 approve budget H. Pernegger / Pixel PL & ID Resource Coordinator D. Robinson / SCT PL and ID PL A. Romaniouk.
Status of Contributions, Draft Budget Request for 2005 and Outlook for the Longer Term Future Martyn Davenport 8 TH October 2004 CAST FRC-D
ATLAS DCS ELMB PRR, March 4th 2002, H.J.Burckhart1 Embedded Local Monitor Board ELMB  Context  Aim  Requirements  Add-ons  Our aims of PRR.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
ID week 27 th of April 15 C3F8 cooling- Compressors & C3F8 status O. Crespo-Lopez EN/CV.
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
ATLAS M&O General Comments
HCAL M&O-B Budget CMS Finance Board
4th FRC meeting, Antti Onnela, CERN-PH-DT
Status of ATLAS Resources
Status of ATLAS Resources
Presentation transcript:

ATLAS Inner Detector MO_B 2012 closure 2013 mid-year status 2014 request H. Pernegger / Pixel PL & ID Resource Coordinator D. Robinson / SCT PL and ID PL A. Romaniouk / TRT PL 3/7/20131

Report from April RRB Book closing Balance IDPixelSCTTRTTotal EntryAmount (kCHF) Budget Carry over from Total payments Carry over to /7/2013 H. Pernegger / CERNRRB July 2013

Book closing 2012 Expenses by categories Totals payments IDPixelSCTTRT CategoryAmount (KCHF)Total Mech+gas+cool Elec+control Areas Comms Stores Sub-det spares0.00 Manpower TOTAL /7/2013 H. Pernegger / CERNRRB July 2013

2013 Budget 443/7/2013 H. Pernegger / CERNRRB July 2013

Mid-year spending So-far spent about 53% of the budget Pixel L2 and SCT TX still to come Expenses to-date include much of 2013 manpower commitments Balance 2013 IDPixelSCTTRTTotal (kCHF) Budget carry-over from Budget Spent (by June 2013) Remaining /7/2013 H. Pernegger / CERNRRB July 2013

Main Cost Drivers and LS1 activities Manpower for LS1 scheduled work: Pixel : Integration of IBL and Pixel detector new Service Quarter Panel replacement ID: Installation of the new thermo-siphon C3F8 cooling system TRT: Address leak issue and consolidate gas system Consolidation of SCT readout: Order of new TX plug-ins and production of new BOC card. This consolidation of SCT readout is carried out with the current budget during the shutdown. The overall budget of the SCT is maintained at 637 kCHF 663/7/2013 H. Pernegger / CERNRRB July 2013

Pixel extraction / nSQP New Service Quarter Panels (nSQP) will replace current Pixel services to move new opto-boards outside the Pixel detector volume (decided by ATLAS & Pixels in January 2013) Thereby also repair of Pixel RO channels, redundant links, faster, installation of Diamond Beam Monitor,...) Extraction of PIXEL done in April, now in SR1 clean room, un-cabling has been completed Re-installation in UX15 from January to March 2014 followed by commissioning Consolidate readout system to cope with Run 2 beyond-design luminosities 73/7/2013 H. Pernegger / CERNRRB July 2013

Integration of IBL IBL Module and Staves –Module production now in full swing, expect to finish in September –Stave loading with modules has started with first 5 of 14 installed staves done –First tests on production stave in SR1 show good results IBL integration –Tooling prepared –Work now on final assembly of support structures –Expect to start integration during August IBL installation in March 2014 Full commissioning of pixel starts May/June /7/2013 H. Pernegger / CERNRRB July 2013

Data taking in 2012 SCT and PIXEL operated with pileup and physics occupancy which far exceeded the original design levels for the highest foreseen LHC luminosities (e.g % SCT occupancy with  ~23 at L ~ 1x10 34 cm -2 s -1 ) Design Physics Test runs Pixel occupancy Bunch Luminosity [10^30] Design Pixel Occupancy for different Layers 93/7/2013 H. Pernegger / CERNRRB July 2013  =80

SCT DAQ Expansion 100kHz at  ~87 Maximum sustainable L1 rate as a function of pileup, 14TeV, 25ns FE  ROD 8176 data links ROD  ROS Existing 90 Slinks ROD  ROS With 128 Slinks and data compression ✗ 100kHz at  ~33 100kHz at  ~87 We will adapt the existing DAQ system to cope with the high pileup conditions in Run2 90  128 RODs and BOCs Improved data compression on ROD Both FE and ROD bandwidth compatible with pileup close to 90 at 100kHz 103/7/2013 H. Pernegger / CERNRRB July 2013

SCT New Optical Transmitters (TX) Currently installed VCSELs were operationally robust during 2012, but two significant issues developed which impact on future operation: 1.10% drop in optical power 2. Small but significant death rate Optical power (IPIN data) vs Date Number of deaths vs channel number SCT will move to commercially packaged optical array assemblies, back engineered to match the mechanical and connectivity constraints of the existing BOC hardware and fibres Installation scheduled for Spring/Summer /7/2013 H. Pernegger / CERNRRB July 2013

Consolidation of Pixel readout Pixel readout: During next run LHC will reach “beyond-design luminosity” which will lead to data rates for which the Pixel readout was not built. The beyond-design peak luminosity leads to saturation on backend electronics This caused pixel detector inefficiency already in Layer 2 and will later cause inefficiency on Layer 1 The saturation and resulting inefficiency is a function of Luminosity, L1A rate, hit rate per double column, error rate and number of FE- chip with hits 12 3/7/2013 H. Pernegger / CERNRRB July 2013

Pixel Readout The bandwidth between module and ROD depends on the layer: 160 Mb/s (2x80Mb/s) on two optical fibers for the B-layer 80 Mb/s on one fiber for layer 1 and disks 40 Mb/s on one fiber for layer FE.. 16 x 40 Mb/s FE/MCC links Col pairs EOC buffer and logic..9.. MCC ROD 40, 80 or 160 Mb/s MCC/ROD links MCC buffers ROD buffers 133/7/2013 H. Pernegger / CERNRRB July 2013

Link occupancy at future luminosities Pixel readout link Link Occupancy for different luminosities : 7x10 33 at 50ns 1x10 34, 2x10 34 and 3x10 34 at 25ns MCC  ROD link occupancy at 75 and 100 KHz LVL1 rate: At and above 2x10 34 first Layer 2 will saturate, then followed by Layer 1 –Run 1 limitations at start of fill and due to ROD computing power limits when  >> design Priority for consolidation: Fix now Layer 2, followed later by Layer /7/2013 H. Pernegger / CERNRRB July 2013

Layer 2 limitations already in 2012 Observed already limitations during Run 1 at start of fill –Observe high number of desynchronized modules in Layer at start of fill. Decrease follows luminosity decrease 13/6/2013 H. Pernegger / CERNPixel IB15

Consolidation of Pixel readout Consolidation of Pixel Layer 2 readout system by using IBL ROD/BOC for Layer 2/1. –Bandwidth increase : –L2: from 40 Mb/s to 80 Mb/s on a single fibre –L1: from 80 Mb/s to 160 (2x 80) Mb/s on two fibres Usage of IBL boards for Pixel readout consolidation –Boards provide bandwidth and computing power safety margin also at high pileup –Adoption to Pixel can be done in firmware B-Layer and disks shall remain with present ROD/BOC –opto packages will need replacements Cost estimate based on IBL production number is 315 kCHF for Layer 2 consolidation 120kCHF included in 2013 MO_B budget Request additional 70kCHF for 2014 and 100kCHF for /7/2013 H. Pernegger / CERNRRB July 2013

This pipe should be repaired. Access outside is blocked. The only way to repair is from inside of the pipe. Pictures from inside of the PEEK pipes taken with Endoscope. A special tool was developed and All active pipes at the exit of the TRT ECs were replaced (including not leaking ones). However some leaks were in inaccessible areas. and only way to keep leaks under control is a modification of the TRT Active Gas System. TRT Gas system 173/7/2013 H. Pernegger / CERNRRB July 2013

Modification of TRT Active Gas system Modification or replacement of different parts of the gas system to allow parallel operation with Argon Distribution racks in UX area which includes a remote control of the gas flows through individual gas supply lines (80 channels). Fully controlled Ar-mixer rack and analysis system to supply some parts of the TRT with Ar-mixture Distribution module for Ar mixture (UX area) direct supply (without circulation) of some parts of the TRT with Xe-mixture with detailed monitoring of the gas consumption Pressure control system in the gas return lines (USA area) Improvements for better stability 183/7/2013 H. Pernegger / CERNRRB July 2013

Projection to end % of the budget spent to date; Large cost drivers which will come in next months include: –Pixel consolidation of readout for Layer 2/1 component order –SCT order for Lightable VCSEL arrays for TX plug-ins and BOC cards Integration of IBL and new Pixel services integration, the change of the ID C3F8 cooling system and the TRT leak fixes are the core activities of the LS1 shutdown. Those activities dominate the manpower expenses SCT will fully absorb -94kCHF negative carry-over not this year but in /7/2013 H. Pernegger / CERNRRB July 2013

Requests for 2014 Budget numbers in kChF 20 EXPERIMENT: ATLAS request 2014 Subsystem: ID PixelSCTTRTIDGENTotal Mechanics00000 Gas-system Cryo-system00000 Cooling system00000 FE electronics (spares)00000 Standard electronics, PS (LV, HV) Standard electronics, Crates Standard electronics, RO Modules Controls, (DCS, DSS) Sub-Detector Spares00000 Areas SR-maintenance facility (buildup) SR-maintenance facility (operation) Testbeam and irradiation Systemtests Communications Store Items Hired CERN (CHF)00000 Standard tasks Special interventions TOTALS [kCHF] (excl. FTEs) Technical Manpower [FTE], OTP /7/2013 H. Pernegger / CERNRRB July 2013

2015 and beyond For 2015 and beyond preserve a flat MO budget –Add IBL core electronics maintenance into 5% model of pixel. The readout of Layer 2/1 with IBL ROD/BOC will still contribute to 2015 expenses 213/7/2013 H. Pernegger / CERNRRB July 2013

Summary Preserve model of spending 5% of core for electronics –Excellent experience, this is a good match to our needs, always sufficient number of spares available; –SCT managed to absorb TX failures in 5% maintenance model Request for a 100 kCHF IDGEN manpower increase for 2014 as the shutdown is now the full two years –Main objectives are consolidation of C3F8 cooling, maintenance of heater system and re-commissioning of ID with new cooling systems (thermo- siphon and C02) –Cover the LS1 activities with today’s knowledge and based on 2013 experience Request of additional kCHF in 2014 and 2015 for electronics for Pixel readout consolidation –This is consolidate the Layer 2 readout ready for Run-2 In Jan 2013 it was decided to de-install pixel and replace service quarter panels. The Pixel and IBL integration, installation and commissioning is the major LS1 activities for /7/2013 H. Pernegger / CERNRRB July